Take off Parameters for Falkon Construction Inc

Preface: We are a professional Concrete & Masonry company. We provide Concrete & Masonry services for Commercial, Public and Private
Projects. Please see below for specific breakdowns of what we specifically expect to be included your Quantity Takeoff for the plans we provide to
you. “Sample” plan take-offs are also provided below for additional clarity. Please email us with any questions.

 Include in your Quantity Take-Off “TOTALS” for the following units of measure ONLY.
LEGEND:
LF (Lineal Feet), SF (Square Feet), W (Width) H (Height), LBS (Pounds), D (Depth), CY (Cubic Yards), Thickness for the following:

Concrete Site Work (Exterior concrete work only)

1.) Highlight in Color Takeoff Areas on Plan. (See Sample below)


2.) Driveways & Driveway Approaches- Total SF & Thickness
3.) Concrete Slabs- Total SF & Thickness
4.) Concrete Curb- Total LF, SF (W & Thickness of Curb)
5.) Concrete Gutter- Total LF, SF, (W & Thickness of Gutter)
6.) Walkways- Total SF (W & Thickness of Walkway)
7.) Sidewalks- Total SF (W & Thickness of Sidewalk)
8.) Bollards Footings- Total CY, (Depth & Width of footing)
9.) Pavers- Total SF and Border/Perimeter LF
10.) Rebar- Total LF, LBS
Note: Provide itemized legend for each item Qtty.
Sample Plan Concrete Takeoff (A)
Take off Parameters for Falkon Construction Inc

Preface: We are a professional Commercial Concrete & Masonry company. Please see below for specific breakdowns of what we specifically expect
to be included your Quantity Takeoff for the plans we provide to you. “Sample” plan take-offs are also provided below for additional clarity. Please
email us with any questions.

 Include in your Quantity Take-Off “TOTALS” for the following units of measure ONLY. 1.) LF (Lineal Feet), 2.) SF (Square Feet), 3.) W
(Width) 4.) H (Height), 5.) LBS (Pounds) 6.) D (Depth) 7.) CY (Cubic Yards) 8.) Thickness for the following:

Masonry CMU Site Work (Exterior CMU work only for 1.) Standalone CMU Walls 2.) Retaining Walls and 3.) CMU Trash
Enclosures.)

1.) Highlight in Color Takeoff Areas on Plan. (See Sample below)


2.) Concrete Footing(s) – Cubic Yards, Total Depth & Width.
3.) Wall- Total Length & Height
4.) Concrete Grout/fill Volume to fill “required” reinforced CMU cells- Total CY
5.) Vertical Rebars- Total LF, LBS (Itemize per specific rebar size as indicated on plans)
6.) Horizontal Rebars- Total LF, LBS (Itemize per specific rebar size as indicated on plans)
7.) Rebar Dowels & Ties “L”, “[ ]”- Total LF (Specify Length & Width segments per plan)
8.) Rebar- Total LF, LBS

Sample Plan (B) “Overview” for Typical CMU takeoff (B)- PLEASE PROVIIDE QUANTITY TAKEOFF ON EXCEL SPREADSHHET