Revise Time Frame of FHS & FDS For SFBL & STL
Revise Time Frame of FHS & FDS For SFBL & STL
Revise Time Frame of FHS & FDS For SFBL & STL
Frame of Fire Hydrant System for SFBL & STL Project
Work Start date 8th April. to 8th May,2021
Field
Sl Works Details 1 4 5 2 2 2 3 3 3
Colo Remarks
No. day day day day day day day day day
r Pipe length
Area Description Of Work s s s s s s s s s
(Rft)
Front Side of RMS room RCC
Laundry bar to SFBL gate RCC removing, U/G piping, Red
1 40 casting dismantling and debris
to FBC oxide paint, Pipe rapping,
removing
6" size core cutting ‐7 Pcs, Railing
Riser & Fire Hose box installation,
2 Admin building 80 removing and wooden board set up
red oxide paint
for 4pcs hose box install.
Wait for confirmation from
3 SFBL FG store Riser & Fire Hose box installation 25 engineering of work starts inside the
FG store
STL CWP to 4 storied
4 63
pickle Boring, Underground pipe through
New HRD corner to SFBL into the boring line, Boring‐ RCC and CC removing for Pit
5 60
FG store 3pcs(6days), pipe fitting, alignment making of boring & pipe laying
Chips & chanachur to old & final welding(6days)
6 30
pickle
RCC removing, U/G piping, Red
7 Admin building to FBC 20 Soil digging, 8" size wall cutting‐1 pcs
oxide paint, Pipe rapping,
Underground pipe through into Slab removing, Pit making for boring
8 Old pickle to noodles 100
the drain line and pipe laying
Underground pipe through into
9 Pump room 100 3pcs boring
the boring line to water reservoir
Note‐
1. Need 10days for pump room work after finished civil work.
2.Testing and commissioning with as built design‐8days.