Revise Time Frame of FHS & FDS For SFBL & STL

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Time 

Frame of Fire Hydrant System for SFBL & STL Project
Work Start date 8th April. to 8th May,2021
Field 
Sl  Works Details   1  4  5  2  2  2  3  3  3 
Colo Remarks
No. day day day day day day day day day
r Pipe length 
Area Description Of Work s s s s s s s s s
(Rft)
Front Side of RMS room RCC 
Laundry bar to SFBL gate  RCC removing, U/G piping, Red 
1 40 casting dismantling and debris 
to FBC oxide paint, Pipe rapping, 
removing
6" size core cutting ‐7 Pcs, Railing 
Riser & Fire Hose box installation, 
2 Admin building 80 removing and wooden board set up 
red oxide paint
for  4pcs hose box install.
Wait for confirmation from 
3 SFBL FG store Riser & Fire Hose box installation 25 engineering of  work starts inside the 
FG store
STL CWP to 4 storied 
4 63
pickle  Boring, Underground pipe through 
New HRD corner to SFBL  into the boring line, Boring‐ RCC and CC removing for Pit 
5 60
FG store 3pcs(6days), pipe fitting, alignment  making of boring & pipe laying
Chips & chanachur to old  & final welding(6days)
6 30
pickle
RCC removing, U/G piping, Red 
7 Admin building to FBC 20 Soil digging, 8" size wall cutting‐1 pcs 
oxide paint, Pipe rapping, 
Underground pipe through into  Slab removing, Pit making for boring 
8 Old pickle to noodles 100
the drain line and pipe laying
Underground pipe through into 
9 Pump room  100  3pcs boring
the boring line to water reservoir

Note‐ 
1. Need 10days for pump room work after finished civil work.

2.Testing and commissioning with as built design‐8days.