COUNTERFORT WALL ESTIMATION

Size
S. No. Description
L B H
1 Toe Slab 14.9 5.5 0.5
2 Heel Slab 14.9 2.6 0.5
3 Front Counterfort 5.5 0.5 4.5
4 Main Counterfort 2.6 0.5 14.5
5 Shear Key 14.9 0.5 0.5
Stem
6 Above Ground Level 14.9 0.5 12
Below Ground Level 14.9 0.5 2.5

Estimate of Concrete
S.No. Description Unit Quantity Length Width Height Volume / Area / Kg Rate Amount Remark
1 Toe Slab Cum 2.00 14.90 5.50 0.50 81.95 5000.00 409750.00 At Site
2 Heel Slab Cum 2.00 14.90 2.60 0.50 38.74 5000.00 193700.00 At Site
3 Front Counterfort Cum 8.00 5.50 0.50 4.50 49.50 5000.00 247500.00 At Site
4 Main Counterfort Cum 8.00 2.60 0.50 14.50 75.40 5000.00 377000.00 At Site
5 Shear Key Cum 2.00 14.90 0.50 0.50 7.45 5000.00 37250.00 At Site
6 Stem Cum 2.00 14.90 0.50 14.50 216.05 5000.00 1080250.00 At Site
7 PCC Cum 2.00 15.00 8.60 0.15 38.70 3800.00 147060.00 At Site
8 Excavation Cum 2.00 15.00 9.00 2.65 715.50 150.00 107325.00 At Site
9.0 Shuttering Sqm
9.1 PCC Sqm 4.00 14.90 0.15 8.94 263.00 2351.22 Precast
9.2 PCC Sqm 4.00 8.60 0.15 5.16 263.00 1357.08 Precast
9.3 Shear Key Sqm 4.00 14.90 0.50 29.80 263.00 7837.40 Precast
Sqm 4.00 14.90 0.50 29.80 263.00 7837.40 Precast
9.4 Base Slab
Sqm 4.00 8.60 0.50 17.20 263.00 4523.60 Precast
Sqm 16.00 5.50 4.00 176.00 263.00 46288.00 Precast
9.5 Front Counterfort
Sqm 8.00 6.80 0.50 27.20 263.00 7153.60 Precast
Sqm 16.00 2.60 14.00 291.20 263.00 76585.60 Precast
9.6 Front Counterfort
Sqm 8.00 14.25 0.50 57.00 263.00 14991.00 Precast
Sqm 12.00 3.50 14.00 588.00 263.00 154644.00 Precast
Sqm 8.00 1.20 14.00 134.40 263.00 35347.20 Precast
9.7 Stem
Sqm 8.00 0.50 10.00 40.00 263.00 10520.00 Precast
Sqm 4.00 0.50 14.00 28.00 264.00 7392.00 Precast
Calculation of Steel

Per Mtr Length of No. of


S. No. Description Quanitity Dia of Bar Total Quantity Rate Amount Remark
Wt of Bar Bar Bars

8.00 0.40 7.00 40.00 235.20 78.00 18345.60 Precast


10.00 0.62 14.90 20.00 388.00 78.00 30263.69 Precast
12.00 0.89 3.00 132.00 740.12 78.00 57729.67 Precast
1 Toe Slab 2
12.00 0.89 3.50 78.00 510.24 78.00 39798.49 Precast
12.00 0.89 14.90 31.00 863.29 78.00 67336.71 Precast
12.00 0.89 3.00 136.00 762.55 78.00 59479.06 Precast
8.00 0.40 13.00 108.00 1179.36 78.00 91990.08 Precast
10.00 0.62 5.70 144.00 1068.68 78.00 83357.16 Precast
2 Heel Slab 2
16.00 1.58 13.00 92.00 3968.33 78.00 309529.58 Precast
16.00 1.58 6.00 125.00 2488.50 78.00 194103.00 Precast
12.00 0.89 5.50 10.00 411.18 78.00 32072.04 Precast
3 Front Counterfort 8 16.00 1.58 5.30 2.00 140.68 78.00 10973.29 Precast
25.00 3.86 3.50 20.00 2269.68 78.00 177035.04 Precast
10.00 0.62 11.20 94.00 2741.49 78.00 213836.31 Precast
12.00 0.89 30.00 55.00 6167.70 78.00 481080.60 Precast
4 Main Counterfort 8
25.00 3.86 15.15 11.00 5403.46 78.00 421469.85 Precast
25.00 3.86 12.00 11.00 4279.97 78.00 333837.50 Precast
10.00 0.62 15.00 113.00 2206.89 78.00 172137.42 Precast
5 Stem 2 20.00 2.47 2.00 624.00 6473.38 78.00 504923.33 Precast
20.00 2.47 13.00 70.00 4720.17 78.00 368173.26 Precast

TOTAL 6644134.78 Rupees