Size
S. No. Description
L B H
1 Toe Slab 14.9 5.5 0.5
2 Heel Slab 14.9 2.6 0.5
3 Front Counterfort 5.5 0.5 4.5
4 Main Counterfort 2.6 0.5 14.5
5 Shear Key 14.9 0.5 0.5
Stem
6 Above Ground Level 14.9 0.5 12
Below Ground Level 14.9 0.5 2.5
Estimate of Concrete
S.No. Description Unit Quantity Length Width Height Volume / Area / Kg Rate Amount Remark
1 Toe Slab Cum 2.00 14.90 5.50 0.50 81.95 5000.00 409750.00 At Site
2 Heel Slab Cum 2.00 14.90 2.60 0.50 38.74 5000.00 193700.00 At Site
3 Front Counterfort Cum 8.00 5.50 0.50 4.50 49.50 5000.00 247500.00 At Site
4 Main Counterfort Cum 8.00 2.60 0.50 14.50 75.40 5000.00 377000.00 At Site
5 Shear Key Cum 2.00 14.90 0.50 0.50 7.45 5000.00 37250.00 At Site
6 Stem Cum 2.00 14.90 0.50 14.50 216.05 5000.00 1080250.00 At Site
7 PCC Cum 2.00 15.00 8.60 0.15 38.70 3800.00 147060.00 At Site
8 Excavation Cum 2.00 15.00 9.00 2.65 715.50 150.00 107325.00 At Site
9.0 Shuttering Sqm
9.1 PCC Sqm 4.00 14.90 0.15 8.94 263.00 2351.22 Precast
9.2 PCC Sqm 4.00 8.60 0.15 5.16 263.00 1357.08 Precast
9.3 Shear Key Sqm 4.00 14.90 0.50 29.80 263.00 7837.40 Precast
Sqm 4.00 14.90 0.50 29.80 263.00 7837.40 Precast
9.4 Base Slab
Sqm 4.00 8.60 0.50 17.20 263.00 4523.60 Precast
Sqm 16.00 5.50 4.00 176.00 263.00 46288.00 Precast
9.5 Front Counterfort
Sqm 8.00 6.80 0.50 27.20 263.00 7153.60 Precast
Sqm 16.00 2.60 14.00 291.20 263.00 76585.60 Precast
9.6 Front Counterfort
Sqm 8.00 14.25 0.50 57.00 263.00 14991.00 Precast
Sqm 12.00 3.50 14.00 588.00 263.00 154644.00 Precast
Sqm 8.00 1.20 14.00 134.40 263.00 35347.20 Precast
9.7 Stem
Sqm 8.00 0.50 10.00 40.00 263.00 10520.00 Precast
Sqm 4.00 0.50 14.00 28.00 264.00 7392.00 Precast