CM Overdue Work Order List
CM Overdue Work Order List
870778 Damietta ELEC MRAZEK Troubleshooting for security gate main power cable.
829754 Damietta ELEC PLANNER2 (Rescheduled due to under overhauling at ABB work shop )overhaul maintenance and replace
bearing of BM-201-B
880184 Port Said ELEC PLANNER3 Inspect MS2-1 & PMCC 2-2 PLCs errors
882202 Port Said ELEC MRAZEK Check frequent trip for mist fan#2 in 40-G-01A
868763 Port Said ELEC MRAZEK Materials need for April 2020 S/D activities
679881 Port Said ELEC PLANNER2 Replace Old Deteriorated CONTROL HVAC condenser coil by new oneMaterial
required:Complete kit of Condenser coil. Consist of (RH/LH) marine coated for Raul700
(Accepted Copper tube thickness is 0.48- 0.5 mm)Include installation s
855446 Port Said ELEC PLANNER2 the 3 air condition units of OPS store cold room #2 , W/H supervisor office & leftover store cold
room are not working , no cooling at all , and due to the criticality precisely of the two cold
rooms , need to check and repair to put
860457 Port Said ELEC PLANNER3 Please fix the defected buttons of the pushbutton controller of the overhead crane at mech.
W/shop
883224 Port Said INST MRAZEK the valve output is 0% while the feedback is 7%, so please check
657628 Port Said INST PLANNER1 ( material received) check malfunction of hydrogen gas detector in LER 2
882189 Port Said INST ASWEED FIX fluctuations in readings of 40-VI-2X (Compressor radial X vibration for NDE bearing)
883249 Port Said INST MRAZEK Check all the LL level switches located at all the storage spheres/bullets in the loading area due
to switches inactivation in case of reaching the LL level setting (minimum level in sphere or
bullet)
883228 Port Said INST MRAZEK Check 80-TIC-37 on the De-methanizer tower quench line due to unsteady performance
883255 Port Said INST MRAZEK please kindly calibrate the abovementioned valve opening with its feed back
883259 Port Said INST MRAZEK kindly check the status of "TV-37" demethanizer quench loop as the valve opening is highly
fluctuated and unstable and need to be in manual mode to work properly.
882191 Port Said MECH ASWEED Install a new wheel of the MV for pump drain drain as it is loose.
745477 Port Said MECH PLANNER3 The time of the alarm list events is delayed from the computer time by half an hour and needs to
be corrected by Siemens
843262 Port Said MECH PLANNER3 Mist fans malfunction and GTA trip due to high lube oil tank pressure
874760 Port Said MECH PLANNER3 Replace the vibrations pads of GT room ventilation fans of Siemens turbines and spare flexible
ducts as per attached mail
870768 Port Said MECH MRAZEK Fix loose metal sheet at the shed of Solar turbine
880174 Port Said MECH PLANNER2 Replace greasing hoses for cooler 40-A-01BB2 due to damage
880175 Port Said MECH PLANNER2 Replace greasing hoses for cooler 40-A-01BD1 due to failure
600018 Port Said MECH ASWEED (Replace WO # 438298) 40-PSV-24: Missing bolts at US 3/4" bleed valve + US MV is very heavy in
movement.
750478 Port Said MECH PLANNER2 The rad. temp. readings of bearing 2 (MBT10CT045) are appearing as question marks on the HMI
display of Siemens GTB and signal error alarm (MBT10CT045ZA03) are triggered due to burnt
cables and needs to fixed next S/D
847482 Port Said MECH PLANNER2 Inspect and repair if needed for GG868 due to high 2nd harmonics of BRG#1 vibration issue
843261 Port Said MECH PLANNER3 Replace actuator of shutoff valve MBP05AA015 for GTB due to air leakage
882187 Port Said MECH MRAZEK Replace spark plug of Siemens GTB
745486 Port Said MECH PLANNER3 (Rescheduled to NOV.2019)Please check the current performance of the sodium hypochlorite
pump as the tank level does not decrease by the normal values and the LAB samples show that
the injection is ineffective
868761 Port Said MECH MRAZEK Materials need for April 2020 S/D activities
800579 Port Said MECH PLANNER2 (Rescheduled to Jan.2020)refabricate the box of AHU expansion valves
870801 Port Said MECH MRAZEK Please fix the leakage from greasing plug of 1st MV (ball valve) bypass of 40-PV-11.
879771 Port Said MECH ASWEED Check the manual valve downstream 40-SDV-09 due to detected internal passing .
872762 Port Said MECH PLANNER3 Eliminate water leakage from the potable water UV sterilization package 95-X-02
835140 Port Said MECH PLANNER2 please repair the opened hole of port cabin 7 to avoid person falling .
872765 Port Said MECH PLANNER3 fix leak detected from plug of 16" MV D/S Anti-Surge valve of 10-K-01A
880179 Port Said MECH PLANNER2 Kindly check C.R door for loose/missing bolts and leaking lubricant oil.
771497 Port Said MECH PLANNER2 we need to fabricate new bar for cylinder support in gas lab
883205 Port Said MECH MRAZEK Kindly check cooler A1 for high sound.
875767 Port Said MECH PLANNER3 Kindly check MV U/S 51-PSV-03 as it is corroded.
872777 Port Said MECH PLANNER1 Kindly check 51-PSV-05 bypass MV as it's stuck close.
880177 Port Said MECH PLANNER2 Kindly check for reported abnormal sound from pump.
Page 1 of 1
WO Issue Date Asset Tag Asset Critically Asset Working Condition Unit
Released 12 12
Released 0 0
Released 4 4
Released 0 0
Released 8 8
Released 4 4
Released 4 4
Released 0 0
Released 12 12
Released 6 6
Released 0 0
Released 0 0
Released 0 0
Released 0 0
Released 3 3
Released 3 3
Released 16 16
Released 5 5
Released 1 1
Released 0 0
Released 0 0
Released 6 6
Released 7 7
Released 1 1
Released 2 2
Released 1 1
Released 32 32
Released 4 4
Released - Pending 10 10
Released 5 5
Released 3 3
Released 0 0
Released 0 0
Released 4 4
Released 3 3
Released 0 0
Scheduled Start Date Scheduled End Date