Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

DOC. No.

:
COMMISSIONING CHECK LIST FOR SWLB-MSG-KEN-40MW-F-DOC-CCL-SELLER-
WEATHER METEOROLOGICAL INVSTN-WMS
STATION (WMS) REV. No.: 01
Page No: 1 of 2
PROJECT: 40MW SOLAR PV AT LANGOBAYA, MALINDI, KENYA IEC:61724-1
CLIENT NAME: MALINDI SOLAR GROUP LIMITED LOCATION:

EQUIPMENT DETAILS Date of Test:

Location :
Make :
Type :
Model No. :
Serial Number :

COMMISSIONING CHECKS

Installation Verifications Status Comments


Verify that all WMS components are installed
Verify that the tower legs are properly tightened and levelled

Verify that GHI pyranometer is oriented to the south direction and


levelled
Verify that the wind vane is installed as per the manufacturer
instruction manual
Verify that the pyranometer ventilation fan is functioning properly
Verify that all the sensor cables are connected and tightened
properly
Verify that the PV module Temperature is properly mounted to the
backside of the PV module
Verify that the Power Supply PV modules is installed and oriented to
the south direction
Verify that grounding of the WMS is properly connected
Check the sensors readings locally (using serial connection) through
laptop and verify that the readings are reasonable compared to the
ambient weather conditions.

Check the calibration certificates and make sure that these values
are included in the data logger program
Lighting arrestor installed
Earthing connected to data logger panel
Check the battery connection and Voltage

Tested By Witnessed By Witnessed By


Signature
Name
Date
Company
DOC. No.:
COMMISSIONING CHECK LIST FOR SWLB-MSG-KEN-40MW-F-DOC-CCL-SELLER-
WEATHER METEOROLOGICAL INVSTN-WMS
STATION (WMS) REV. No.: 01
Page No: 2 of 2
PROJECT: 40MW SOLAR PV AT LANGOBAYA, MALINDI, KENYA IEC:61724-1
CLIENT NAME: MALINDI SOLAR GROUP LIMITED LOCATION:

SCADA Connectivity Details Details


IP address
Subnet Mask

Protocol

Communication Media

Device Id

Baud rate

Parity

Bit

Memory card details

Communication cable laid between WMS & SCADA/PLC panel

Communication cable Crimped at Both Ends for WMS & SCADA/PLC panel

Communication cable terminated at Both Ends for WMS & SCADA/PLC panel

➢ Remarks:

WMS SYSTEM found healthy : Yes / No

➢ Observations during Commissioning / Testing (If Any):

1.
2.
3.
4.
5.

Tested By Witnessed By Witnessed By


Signature
Name
Date
Company