University of Sargodha: Analysis of Rates For

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

UNIVERSITY OF SARGODHA

Analysis of rates for


Providing and fixing of Iron Window Slider/Stay In M.S Box Section Window, i/c Screws & fixing at site
and painting etc.,complete in all respects and satisfaction of Engineer Incharge.

Unit = Per No.

Sr. No. Description Qty. Unit Rate Amount Remarks


A Material
1 Iron Window slider 1.00 No. 80.00 80.00 Market
2 Screws L-S 20.00 6.024
Total Rs. 100.00
Contractor's Profit & Overheads @ 20 % 20.00
Sub Total (A) Rs. 120.00
B Labour
1 Black Smith 0.10 No. 625.00 62.50 LB-028
Total Rs. 62.50
Sundries @ 10% 6.25
Total 68.75
Contractor's Profit & Overheads 20 % 13.75
Sub Total (B) Rs. 82.50
Total (A+B) Rs. 202.50

Composite Rate of Each Rs. 202.50


SAY Rs. 203 P/Sft

Sub Engineer Assistant Engineer (Civil) University Engineer

Approved By:- Project Director (Works