Professional Documents
Culture Documents
(2.1) Appendix A1 - Schedule of Builders Works (Elev)
(2.1) Appendix A1 - Schedule of Builders Works (Elev)
be provided by OTHERS/EMPLOYER/OWNER”
The Main Contractor will undertake or procure that parties other than JSEC carry out the
following works and provide the following facilities free of any charge to JSEC in accordance
(wherever appropriate) with the Delivery and Installation Programme and JSEC’s builders' work
and layout drawings, and the terms and conditions of the Sub-Contract Agreement:
A. SITE FACILITIES Lift shafts and lift motor rooms are to be free of non-lift
related services and other obstructions.
From date of delivery to the Site until installation,
adequate and suitable, dry, illuminated and secure All required structural floors and staircases providing
storage space for all materials, tools and equipment access to the lift shafts and lift motor rooms at each
adjacent to hoist way or other mutually agreed location floor level.
on site.
Lift shafts, lift motor rooms, pit and related or adjoining
Adequate and suitable areas for erection by JSEC of structural concrete works are to be capable of
its offices and other amenities including free use of sustaining without damage or deflection, all loads and
mess room’s latrines, water consumption, canteen, forces generated in both temporary (i.e. during
toilet and other usual facilities of the project site. installation testing and commissioning) and
permanent conditions.
Suitable access routes including all shoring,
strengthening and protection of the structure for All holes, door openings and chases, including any
movement of labor, materials, tools and equipment necessary cutting, and all masonry work related to lift
within the Site in compliance with local regulations. All installations. The door and floor openings for cables
these items shall be provided at no additional cost to and ducts as detailed on JSEC drawings with a
JSEC. 100mm above floor finish line (AFFL) protective curb
about opening to prevent water ingress.
Provide for use at no cost to JSEC all standing
craneage facility on site (tower crane, mobile crane, Datum lines for finished floor levels and alignment of
external passenger hoist) for the purpose of loading wall finishes at each door opening on each floor level
and unloading and relocating of the imported adjacent to each lift shaft.
equipment throughout the installation period, including
the passengers and authorized representatives of Lift shaft separator beams and trimmer beams (if
JSEC. necessary) as required in the approved shop drawings
together with any other structural steelwork (excluding
A centrally located area in which JSEC is able to guide rails and brackets) within lift shafts and machine
deposit rubbish for removal, by others, from site rooms, unless otherwise it is specifically provided in
without charge to JSEC. the Sub-contract.