Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

APPENDIX A – “Schedule of Builders' Works and Facilities to

be provided by OTHERS/EMPLOYER/OWNER”
The Main Contractor will undertake or procure that parties other than JSEC carry out the
following works and provide the following facilities free of any charge to JSEC in accordance
(wherever appropriate) with the Delivery and Installation Programme and JSEC’s builders' work
and layout drawings, and the terms and conditions of the Sub-Contract Agreement:

A. SITE FACILITIES Lift shafts and lift motor rooms are to be free of non-lift
related services and other obstructions.
From date of delivery to the Site until installation,
adequate and suitable, dry, illuminated and secure All required structural floors and staircases providing
storage space for all materials, tools and equipment access to the lift shafts and lift motor rooms at each
adjacent to hoist way or other mutually agreed location floor level.
on site.
Lift shafts, lift motor rooms, pit and related or adjoining
Adequate and suitable areas for erection by JSEC of structural concrete works are to be capable of
its offices and other amenities including free use of sustaining without damage or deflection, all loads and
mess room’s latrines, water consumption, canteen, forces generated in both temporary (i.e. during
toilet and other usual facilities of the project site. installation testing and commissioning) and
permanent conditions.
Suitable access routes including all shoring,
strengthening and protection of the structure for All holes, door openings and chases, including any
movement of labor, materials, tools and equipment necessary cutting, and all masonry work related to lift
within the Site in compliance with local regulations. All installations. The door and floor openings for cables
these items shall be provided at no additional cost to and ducts as detailed on JSEC drawings with a
JSEC. 100mm above floor finish line (AFFL) protective curb
about opening to prevent water ingress.
Provide for use at no cost to JSEC all standing
craneage facility on site (tower crane, mobile crane, Datum lines for finished floor levels and alignment of
external passenger hoist) for the purpose of loading wall finishes at each door opening on each floor level
and unloading and relocating of the imported adjacent to each lift shaft.
equipment throughout the installation period, including
the passengers and authorized representatives of Lift shaft separator beams and trimmer beams (if
JSEC. necessary) as required in the approved shop drawings
together with any other structural steelwork (excluding
A centrally located area in which JSEC is able to guide rails and brackets) within lift shafts and machine
deposit rubbish for removal, by others, from site rooms, unless otherwise it is specifically provided in
without charge to JSEC. the Sub-contract.

Any metal ducting requirement (metal sheet or


B. SHAFT REQUIREMENTS expanded metal) shall be supplied and fitted by others
between operating elevators/counterweights located
Dry, clean, watertight lift shafts and pits, properly within the same shaft for ventilation purposes.
framed, enclosed and ventilated, are to be made
available for the exclusive use of JSEC. Shafts are to Note where phased handover is required by the Client,
be of requisite dimensions, square, and vertically temporary internal dividing screens will be required
plumb to be within a tolerance of (plus (+) or minus (- between operating lifts and the work area even if not
) 25mm). Shaft and pit walls shall form a smooth stated on the drawings. Furthermore, for staged
continuous surface and, where necessary in order to installations or phase installations for both elevator
achieve the same finishes, inside the shafts shall be and escalator works, proper installation of water-
provided and built by others. JSEC is obliged to proofed crash deck and hoisting points shall be
immediately check the shaft dimensions once made provided at no additional cost to JSEC.
available to it prior to commencement of lift
installation. Should the dimensions of the lift shafts Safety protection such as fences, kick boards and
and/or pits exceed the tolerance, JSEC reserves the removable barricades at all openings into shafts or
right to reject site possession of the shafts and/or pits pits, including installation and removal together with all
until rectification have been properly executed. JSEC other necessary safety measures and signage.
shall not be subjected to any liquidated damages claim
because of the delay.

Schedule of Builder’s Works (Elevators) Page 1 of 2


Grouting-up of openings including the space between commissioning stages as set out in the Delivery and
the edge of the slab and landing door sill, channels Installation Programme). Such permanent power
and chases, including making good around push- supply capacity is to satisfy the electrical power
button boxes, indicators, architraves, brackets and the loading requirement provided by JSEC in respect of
other embeds must be carried out in accordance with the installation and to permit the simultaneous
JSEC Installation Programe. operation of all lift and escalator units). The circuit
should be tested and labeled correctly. These facilities
Reinforced Pit to support buffer and rail loads including all cabling, accessories, termination and the
transmitted to pit slabs. Provide structural supports in consumption supply shall be provided at no cost to
pit floor for car and/or counterweight buffers and rail JSEC.
impact loads. The pit must be cleared of rubbish and
must be water-proofed in order to avoid and prevent 1. The permanent power supply is to include fused
water ingress. disconnect switches (for both three-phase and single-
phase supply) for each elevator, together with all cut-
Provide wall pockets and/or structural beams for outs, circuit breakers, lightning arrestors and other
adequate support of the elevator equipment. devices necessary to satisfy all applicable codes and
regulations. Any power factor correction is to be
Provide structural up-thrust tie down beams in elevator undertaken by others.
pit floor for compensation sheave assembly, when
required. Verify load and reaction on JSEC shop 2. As a minimum requirement, there should be one (1)
drawings. 40 watts fluorescent fixture over each machine, as
applicable. Shaft lighting shall span the full-height of
The Main Contractor shall be responsible for the cost each lift shaft (with light points at not more than 6
for the replacement of lift equipments that will be meter intervals) with accessible switching adjacent to
damaged or contaminated by or as a result of the lift pit ladder, and machine room. A separate three-
operations of other trades, such as but not limited to way switch for individual pit lighting together with a
water ingress and material damage. 220-volt socket outlet with cover (weather and water-
proofed) shall be provided. All permanent lighting must
C. POWER SUPPLY AND ELECTRICAL WORKS be completed prior to our commissioning activities. All
light fittings shall be protected by guarded fittings.
Permanent power supply (in accordance with our
electrical requirements and approved JSEC contract Single phase 220V temporary electric power for
shop drawings), 3-phase power including earth wire hand-tools provided at earthed outlets in machine
and neutral (400V / 60Hz), terminating at each circuit rooms and in each lift shaft at intervals of not more
breaker in the lift machine room/machine-room-less than 3 floors, together with adequate temporary
control panel (unless otherwise stated, the permanent lighting for safe working in each such area.
power is required during the testing and

Schedule of Builder’s Works (Elevators) Page 2 of 2

You might also like