Balikpapan, April 27th 2021

No. : 26071-CV009-PPU-JO-LT-00259
Attn. : PM of RDMP JO
Cc : Mr. Didit Fernandi (Subcontracting of RDMP JO)
Mrs. Leviyona
Project : Interconnecting Pipe Rack Foundation (Civil Work #09)
Contract : RDMP-R-SC-CV-009
Subject : Notice Extension of Time (EoT) Meeting

Dear Sir,
Refers to Minutes of Meeting dated on 14 th April 2021 between PP Urban and RDMP JO about
Extension of Time (EoT) of subcontract period of Interconnecting Pipe Rack Foundation, we would
inform as below:
1. We Agree with Extension of Time of subcontract period with details:
Description Subcontract Period Remarks
Original Subcontract 20/12/2019 - 20/02/2021 429 days
1st Amendment 20/12/2019 - 30/01/2022 773 days
With terms of handover schedule each area is on time with the detail execution plan that agreed
between PP Urban and RDMP JO. (Attachment 1)
2. With the agreement of Extension of Time (EoT), we would like to demand provisions as below:
a. Compensation for Claim of Indirect Cost
The Extension of Time of subcontract period is not caused by PP Urban failure, but late
workfront handover from RDMP JO that refers to our letter
No.012/EXT/PPUB/DKP/III/2021 dated on 18th March 2021. (Attachment 2)
b. Adjustment new price due to global price raise issue for material rebar, anchor bolt, embedded
plate. This issue is caused by delay of work period that should be finished on February 2021,
but extended until January 2022 and impacted price rise of those materials.
We propose those materials supplied by RDMP JO (SBO). (Attachment 3)
c. Approval new item for concrete coating that refers to RFC dated on 6th October 2020 for R80
that on construction. (Attachment 4)
Thank you for your attention and cooperation

Best regards,
PT. PP Urban

Agung Nugroho
Project Manager