Professional Documents
Culture Documents
Spd0008ern - 2 - Basic Engineering Design Data
Spd0008ern - 2 - Basic Engineering Design Data
Spd0008ern - 2 - Basic Engineering Design Data
SPD0008ERN
PROCESS DESIGN MANUAL
REV. : 2
DATE : 2013.08.14
CONTENTS
PAGE
1. SCOPE ------------------------------------------------------------------------------------- 3
2. FORMAT ------------------------------------------------------------------------------------ 3
1. SCOPE
This manual describes the preparation of the Basic Engineering Design Data.
The Basic Engineering Design Data is abbreviated to BEDD which name is not fixed in all cases, but
such a basic matter must be confirmed in writing before starting the design work.
The Basic Engineering Design Data is a summary of basic points to be followed in the basic and
detailed design which range over all specialty fields.
While a Process Design Basis contains information specific to each individual process unit, the Basic
Engineering Design Data documents is standardized and applicable to all process units at the plant
site.
2. FORMAT
2.1 Blank Form
The BEDD should be preapred in advance with the content headings outlined in Sec.2.2 below. The
BEDD should be filled out in detail by reviewing and compiling information for each item prior to
starting the design work. This will allow the project to be carried out in the most efficient
manner once started.
(6) Other matters: Owner's requests, desires and thoughts such as those on entire plants and
plant buildings which are to be reflected in the basic design.
3. BEDD PREPARATION
3.1 Timing
As a general rule, all items included within the BEDD should be determined prior to the start of
the process design. However, some items may not be fully defined at this stage. These items may
continue to be developed as the project work progresses, and should be clearly identified as
"Holds" in the BEDD.
Since some details of the detailed design cannot be covered by BEDD, detailed engineering design
SPD0008ERN
PROCESS DESIGN MANUAL
REV. : 2
BASIC ENGINEERING DESIGN DATA
DATE : 2013.08.14 PAGE 4 OF 7
data (abbreviated to BEDD) are prepared in some cases to maintain the unification of equipment
detailed design.
3.2 Procedure
The BEDD must be prepared by the project engineer under the cooperation of each specialty
engineer, with input, as required, from client.
Many components of the BEDD must be decided from the standpoints of overall plant safety and
maintenance rather than from the standpoints of a single unit. Future plans must also be taken
into consideration during the preparation of BEDD.
Equipment Symbols
Columns (Towers) T
Vessels (Drums) D
Reactors R
Exchangers E
Fired Heaters H
Pumps P
Compressors C
These letter symbols are suffixed by numbers (digits) which are assigned on such bases as
the sequence of flow.
In cases where two or more pieces of equipment are placed in parallel and one is used as
service equipment and the other as stand-by, usually the same item number is used for both,
being suffixed by such auxiliary letter symbols as A and B: for instance, P-1A and P-1B in
the case of pumps.
For instruments, the most effective means of documentation is to show their location on the
P & I diagrams and to assign them with their own distinct instrument numbers.
Electrical equipment and piping are also given identifying numbers and symbol letters.
consumption and atmospheric conditions, they must be carefully shown on BEDD, with
consideration given to the service conditions and locations after each condition has been
confirmed, so that the design can be provided without mistaking their applications (such as
process and mechanical services).
(6) Miscellaneous
Conditions desired by the owner for buildings, platforms, steel structures, firefighting
facilities, pavement, painting, insulation, etc. should be included the BEDD.
Plant operating companies have different views on the basis for these details and
requirements. This difference is large and varies, depending on industries such as the
petroleum refining, petrochemical, coal chemical, general chemical and inorganic chemical
industries. Large differences are found between petrochemical companies separated from
petroleum refining companies and those separated from general chemical companies and those
engaged also in coal chemical plant operation. Their superiority and inferiority cannot be
judged by a simple means since their technical backgrounds historically built up are
different. In the case of projects in foreign countries, BEDD is specially important for this
reason.
SPD0008ERN
PROCESS DESIGN MANUAL
REV. : 2
BASIC ENGINEERING DESIGN DATA
DATE : 2013.08.14 PAGE 7 OF 7
4. REVISION HISTORY
개정번호 개 정 일 자 개정 페이지 개 정 사 유
신규 제정
- 작성부서 : 공정팀
0 98.04.17 전 페이지
- 작성자 : 박종헌 임종은
- 검토자 : 이봉일 조석범 노재철
- 승인자 : 오성국
- Made by : Y.J.Ji
2 2013.08.14 전 페이지 - Reviewed by : P.M.HUR, P.S. CHOI
- Approved by : S.B.LEE