Professional Documents
Culture Documents
9 - Global Case Studies
9 - Global Case Studies
Learning Objectives
By the end of this lesson, you will be able to:
- Summarise Global BIM Case Studies
Research Complex 2 (USA)
Client: University of Colorado-Denver Health Sciences
Centre
The scheme shown is a new build research complex for
the university of Colorado-Denver. As part of this
project, Information management used to reduce
programme and identify problems during the design
stage.
This scheme was of particular interest as the same
design team were used on the previous research
complex, therefore comparisons could be drawn from
the traditional approach and the use of building
information modelling.
As part of the design process, BIM was used to
undertake virtual design and construction (VDC)
processes.
BIM was selected on the project to improve the
customer experience, enhance productivity, optimise
the project schedule, and to enhance project team
collaboration.
The Benefit:
The overall benefit of the scheme was that, project
programme reduced by two months due to previously
unforeseen problems identified in the model rather
than in physical conflicts, as well as the efficient
coordination of subcontractors. Additional benefits
were found in the efficient coordination of sub-
contractors utilising 4D modelling.
The Benefit:
Cost of the accumulated rework was less than 0.22% of
the total project cost. In addition, the programme was
reduced by around 30% to 73 months.
Collaboration with Interserve and SSC resulting in pre-
cast cells, reducing the programme by 6 weeks saving
£85,000 on time-related overheads alone.
1.5% through early engagement and review of work
packages to ensure best value.
In addition to its use during design and construction,
BIM will play a vital role to the facility management
and operations to the building, this includes its use to
support asset management and spatial management
processes.
Stakeholder Engagement
As part of the design development, stakeholders
challenge the design to ensure smooth operation, post-
handover. For instance “If what was a glazed screen
was converted back to bars, it would allow sound
transference, enabling staff to more easily hear if there
was a disturbance.”
Had this engagement not occurred in order to monitor
the prison an additional guard would have been
required and this would have increased the operational
cost.
North Shore Hospital (NZ)
Client: Waitemata District Health Board
On behalf of Waitemata District Health Board, the
information model was used to streamline the design
process.
Multiple 3D Models were created and co-ordinated at
an early design stage to improve the workflow
between teams and to avoid issues at key junctions
such as with MEP systems and fire protection.
The model was also used for client engagement using
3D room data sheets.
The Benefit:
By developing an early design stage model, critical
junctions were highlighted which benefitted the
documentation stage, saving weeks in project time.
Client engagement was a key part of this scheme,
utilising 3D room data sheets to ensure that the right
equipment and fittings were provided and spaced
correctly. Good hospital design can limit cross-
contamination, improve staff efficiency and ultimately
save lives.
Due to the complexity of the systems proposed MEP
systems could not be approved due to the technical
level of their information by the client, a team was
then commissioned to produce this information into
3D which was then conveyed to the client and
approved.
WDHB CEO Dale Bramley anticipated that, based on
this model, operations would cost approximately 20%
less than average through improved facility design,
consultation, surgery and recovery times, and by
ensuring that most patients would need only visit the
hospital once prior to surgery.
It can be difficult for clients and non-construction
professionals to read technical drawings, as such
having good visualisation data, such as there room
data sheets allow decisions to be made by the client
and end users without having to navigate the language
of construction drawings.