Professional Documents
Culture Documents
Topic 1 CE 13 Materials Estimate
Topic 1 CE 13 Materials Estimate
Materials Estimate
1. UNIT OF MEASURE
2. EARTHWORKS – volume of excavation and backfill.
Example :
A 1.2 meter x 2.4 meter and 2.0 meter deep septic tank is to be constructed. Compute the
cost of labor for excavation of the septic tank. Assuming 350 pesos per cubic meter for labor rate.
Solution :
Compute for volume of excavation = 1.2m x 2.4m x 2.0m = 5.76 m ³
Labor cost = 5.76 m³ x 350 pesos/m³ = 2016 pesos
Concrete – an artificial stone as a result of mixing cement, fine aggregates and coarse
aggregates and water.
Reinforced Concrete – concrete with reinforcement embedded in such a manner that the
two materials act together in resisting forces.
Coarse Aggregate – crushed stone, crushed gravel or natural gravel with particles retained
on a 5mm sieve.
Fine Aggregates - crushed stone, crushed gravel or natural sand with particles passing 5mm
sieve.
Note: Aggregate size must be less than 25mm in size for the concrete mix to flow around the reinforcement
ready for compaction.
LINTEL BEAM – beams that are found above every opening on CHB walls. Usually 150mm x
200mm in cross section, this member prevents cracks on doors and windows for it is
responsible for carrying loads above the opening.
FLOOR BEAM – beams that are installed on the finished floor line level, same cross section
as the lintel beam. This member prevents the lateral force brought about by the backfill on
the flooring.
Solving for concrete materials on the said members are also the same as the beams and
columns.
Solve for volume of concrete then determine the class mixture of the member, in this case
Class “A” is recommended for it is load veering member.