High Voltage Circuit Breaker and Power Transformer Failure Modes and Their Detection

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

High Voltage Circuit Breaker and Power

Transformer Failure Modes and Their Detection


Charbel Antoun
High Voltage Products and
Transformers, Power Grids Division
ABB Australia Pty Ltd
Moorebank NSW, Australia
charbel.antoun@au.abb.com

Abstract—This paper aims to explore the various failure detect the conditions preceding potential faults or failures
modes associated with High Voltage Circuit Breakers and within the equipment will then be identified. This analysis
Power Transformers within transmission and subtransmission also presents an opportunity for network operators to assess
electricity networks and identify the online monitoring whether existing monitoring and maintenance practices
requirements to ensure effective early detection of issues. This provide sufficient visibility and coverage to manage the
would enable system operators to act appropriately to prevent varying levels of risk surrounding high voltage circuit
unexpected failures. These requirements in the context of the breaker and power transformer faults or failure. This also
capabilities and limitations in currently available Online provides motivation for manufacturers to ensure that they are
Monitoring Technologies will also be discussed.
providing solutions capable of fulfilling the requirements of
Keywords—High Voltage Circuit Breaker, Power
the industry in doing so.
Transformer, Failure Modes, Online Monitoring, Reliability
Centered Maintenance II. FAILURE MODES
To ensure that equipment failures can be mitigated or,
I. INTRODUCTION ideally, prevented, it is imperative to understand the various
Rising electricity prices, slashed utility budgets, and ways in which the equipment can fail. Armed with such
unwavering pressure to maintain electricity supply quality knowledge, it is possible to address the root causes of these
and reliability has led to an increased focus on more modes of failure and effectively monitor the status and
intelligent and efficient monitoring and maintenance condition of the equipment for early indications that the
solutions for electrical assets and networks. This has equipment is approaching failure.
provided an opportunity for manufacturers to offer flexible CIGRE has performed reliability surveys for both high
and adaptable monitoring products, which would empower voltage circuit breakers [1] and power transformers [2],
utilities to implement targeted maintenance strategies and providing a rich statistical insight surrounding asset failure.
ensure expenditures are optimized and value maximized. Given that the surveys provide such significant detail and
Particularly critical aspects of transmission and data extrapolation, this paper will therefore provide a brief
distribution electricity networks are high voltage switchgear discussion of some of the main findings with the intention of
and transformers, with a focus on circuit breakers and power establishing a contextual understanding for the subsequent
transformers. Ensuring the equipment is effectively discussion regarding online monitoring strategies.
monitored and maintained is therefore critical to the
reliability of the electricity network as a whole, and allows A. High Voltage Switchgear Failure Modes
for effective maintenance programs to be developed. Online The third (and most recent) CIGRE International Enquiry
monitoring technology, and the valuable information that it on the Reliability of High Voltage Equipment [1] provides a
yields, empowers network operators to transition from comprehensive look at the failure modes observed within an
schedule based maintenance practices to reliability-centered enormous global HV circuit breaker population from 83
and condition based maintenance practices. utilities across 26 countries. The Enquiry distinguishes
Key to ensuring the success of this initiative is verifying between major failure modes, which prevent circuit breakers
that one understands the failure mechanisms that the from performing their main function resulting in an
equipment is prone to, their root causes, and ultimately the immediate change in system operating conditions, and minor
parameters that need to be monitored to ensure that they are failure modes, which allow circuit breakers to perform their
identified before faults or failures occur. On this basis, the main function but with restrictions.
capabilities and limitations of online monitoring solutions in 1) Major Failure Modes
ascertaining the health and reliability of an asset can be Major failure modes are naturally high in their criticality,
established. given the potential consequences of their occurrence,
This paper aims to examine the statistics surrounding the however, some modes are more critical than others. For
root causes of the various failure modes associated with high example, a circuit breaker failing to close on command
voltage circuit breakers and power transformers in would typically yield less dire consequences than failing to
transmission and subtransmission utility network contexts. open on command, as opening the circuit may be required
With this practical understanding of the various kinds of for clearing a system fault.
issues faced in the field, the key underlying parameters and
associated online monitoring requirements to effectively

978-1-5386-4126-2/18/$31.00 ©2018 IEEE


Fig. 1. HV Circuit Breaker Major Failure Mode Distribution

As illustrated in Figure 1, roughly 50% of all major equipment was in service and an operation was requested,
failures occur as a result of uncontrolled commands. These while almost a third occurred while the equipment was in
commands are broken down into two main categories: service without an operation occurring. The contribution of
environmental factors to major failures was observed to be
 Failing to close or open on command: a command is particularly small at 11.9%, with over a third of those having
issued to the circuit breaker to perform a close observed lightning as a contributing environmental factor.
operation, but it is unactuated. Closing operations that
are unactuated account for 28.2% of all major Overall, the major failure frequency per 100 circuit
failures, while unactuated opening commands breaker years was observed to be 0.30 major failures per 100
account for 16.4% of all major failures. circuit breaker years (MaF/100CBy). Those circuit breakers
implemented for shunt reactor switching exhibited a
 Unintended opening or closing operation: the circuit substantially higher frequency of failure compared to other
breaker opens or closes unintentionally, without kinds of service – 2.46 MaF/100CBy, while capacitor bank
having been issued any command. While less switching circuit breakers were the second highest at 1.04
common than failing to actuate commands, MaF/100CBy. The major failure frequency was generally
unintentional open operations represent 5.4% of observed to increase exponentially as the rated voltage level
major failures, while unintentional close operations got higher.
represent only 0.2% of major failures.
2) Minor Failure Modes
The remaining major failure modes are comprised of four While minor failure modes don’t necessarily debilitate
main categories: the ability of a circuit breaker to fulfil its primary purpose, it
 Unintentional electrical locking in open or closed is important to ensure that they are identified and prevented
position: the inability to operate a circuit breaker due from progressing to a stage where they can develop into a
to unintended electrical blocking within the circuit major fault. As illustrated in Figure 2, the minor failure
breaker control system, for cases other than when it is modes are categorized as follows:
discovered upon trying to perform an operation (as  Fluid leaks: more than half of minor failures can be
this would be represented in the above statistic). This accounted for in fluid leaks, with small SF6 leaks
accounts for 25.1% of major failures.
 Loss of mechanical integrity: mechanical damage to
parts of the circuit breaker such as insulators or
within operating mechanisms, and reflects 8.1% of
major failures.
 Electrical breakdown in main circuit: issues
surrounding electrical conductivity or breakdown,
which represent 11.3% of major failures. This would
include failure to conduct current in the closed
position (representing 1.3% of major failures), or
some kind of electrical breakdown internally or
externally, representing 10% of major failures.
 Other causes: representing the remaining 5.2% of
major failures.
The CIGRE Enquiry presents several interesting
observations. Almost half of major failures occurred while Fig. 2. HV Circuit Breaker Minor Failure Mode Distribution
accounting for 35.8% and operating mechanism air or 0.13 MaF/100CBy and 0.11 MaF/100CBy, respectively. The
hydraulic leaks accounting for 20.4% of minor survey points out, however, that modern hydraulic
failures. Grading capacitor oil leakage, typically mechanisms have a vastly increased reliability compared to
applicable to higher voltage circuit breakers, account previous generations, and that they are comparable in
for 1% of minor failures. reliability to modern pneumatic or spring operating
mechanisms, although no further information is provided.
 Changes in functional characteristics: almost a third
of minor failures involve a change in functional Failures involving locking in the open or closed position
characteristics. represented just over half of major failures in hydraulic
operating mechanisms, while failing to open or close on
 Mechanical changes: e.g. contact travel speed during command represented roughly a quarter. The dominant
open or close operations, damping issues, etc., failure modes of pneumatic operating mechanisms were
accounting for 6.8% of minor failures. failing to close on command or open on command, each
 Electrical changes: e.g. increased contact resistance, representing about a third of all major failures, while the
presence of partial discharge, etc., accounting for major failure mode for spring operating mechanisms was
3.3% of minor failures. failing close on command, representing 60% of the major
failures encountered.
 Control or auxiliary system changes: e.g. non-critical
component damage or failures, increased charging B. Power Transformer Failure Modes
motor run times, etc.) accounting for 18.4% of minor
The Transformer Reliability Survey [2], published in
failures.
2015, spanned 964 failures across 56 utilities from 21
 Other causes: representing the remaining 14.3% of countries, with a total population of 23,884 transformers
minor failures. representing 167,459 transformer-years. The units within the
sample were manufactured as early as the 1950’s, up until
Roughly two thirds of minor failures occur or are 2009. The Survey focused only on major failures due to
identified during normal service outside of normal circuit historically poor data collection experiences of previous
breaker operations being performed, while slightly more than working groups. A major failure was defined as “any
a fifth occur during or after testing and maintenance. Minor situation which required the equipment to be removed from
failures occurring during normal switching operations was service for investigation, remedial work or replacement”.
observed to be particularly small, at 3.7%. Environmental
factors were observed to be contribute minimally with 5.1% The failure modes identified within the Survey were
of failures having been indicated to involve environmental aggregated at a relatively high level and, as such, the
factors. information presented was particularly scarce with regards to
detail surrounding the failures themselves. While the
3) Operating Mechanisms distribution of failure modes was relatively consistent, the
Given that operating mechanisms constitute half of the Survey differentiated between substation transformers and
components responsible for major failures and over a third of generator step-up transformers. The failure mode distribution
components responsible for minor failures, as can be seen in for the two transformer types as well as the aggregate is
Figure 3, there is value in looking at the failure frequencies shown in Figure 4. The failure modes listed are:
and failure modes of the different types of operating
mechanisms.  Electrical: Open circuit, short circuit and poor joint
or contact failures, comprising 16% of failures.
Hydraulic operating mechanisms have the highest failure
frequency at 0.19 MaF/100CBy, while pneumatic and spring  Chemical: Contamination (moisture, particles, gas)
operating mechanisms presented lower failure frequencies at

Fig. 3. HV Circuit Breaker Distribution of Components Responsible Fig. 4. Power Transformer Failure Mode Distribution by Percentage
for Failure
and corrosion failures, comprising only 3% of
failures.
 Thermal: General overheating and localized hotspot
failures, comprising 11% of failures.
 Dielectric: Partial discharge, tracking and flashover
failures, comprising 37% of failures, the largest
individual failure mode.
 Mechanical: Bending, breaking, displacement,
loosening and vibration failures, comprising 20% of
failures.
 Mode of Failure: 13% of failures were unable to be
attributed to any specific mode of failure.
The overall failure rate, across all voltage classes and
transformer types, was observed to be 0.57%. When
differentiating between substation transformers and generator Fig. 5. Power Transformer Failure Location Distribution
step-up transformers, the failure rates were observed to be
0.53% and 0.95%, respectively.
The failure locations within the failed transformers was
outlined in the Survey, and provides some valuable further
context regarding the manner in which the failures occur. As
Figure 5 shows, more than half of all failures occurred within
the windings, followed by more than a fifth of failures
occurring within the bushings.

III. ROOT CAUSE IDENTIFICATION


With an understanding of the failure modes that the
equipment being discussed is prone to, identification of their
root causes of those failure and the components responsible
will ultimately enable an effective online monitoring strategy
to be developed.

A. High Voltage Circuit Breakers Failure Root Causes


As can be seen in Figure 6, The leading root cause of
both major and minor failures is Wear/Ageing at 42.3% and
55.9%, respectively. The next highest root causes of failures
were those introduced before putting the equipment into
service, in particular during design or manufacturing,
representing 19.9% of major failure root causes and 13.6%
of minor failure root causes.
The remaining root causes of major failures are relatively
well distributed between incorrect maintenance at 3.8%,
stresses in excess of ratings (in particular environmental,
mechanical or lightning) at 4.8%, corrosion at 4.4% and
other causes (in particular abnormal service conditions,
incorrect operation or monitoring, external damage, or
human error). Corrosion was the main remaining root cause
for minor failures at 8.8%, with the remaining causes
representing 4.1%.
It is worth noting that for a considerable number of both
major and minor failures, the root cause was unknown, at
16.5% and 14.1%, respectively.
More specifically with regards to operating mechanisms,
each type has a different dominant component which tends to
fail more commonly relative to the rest of their construction:
energy storage systems for hydraulic operating mechanisms,
mechanical transmission systems for spring operating
mechanisms and charging mechanisms (compressors,
motors, pumps, etc.) for pneumatic operating mechanisms.
Fig. 6. Distribution of Major (top) and Minor (bottom) Failure Causes
These conclusions are intuitive, given the application of increased likelihood of failure, the aggregated probability of
technology within each type of operating mechanism and the failure naturally increases. In practice, a probability of failure
parts of the system which are under mechanical duress. provides a greater qualitative view on the health of the asset
than a health index approach, due to the more refined
B. Power Transformer Failure Root Causes approach with regards to the impact on the health and
Of particular note when reviewing the power transformer reliability of the asset.
failure root causes for the failures that were analysed is that Traditionally, offline monitoring has been emphasized
roughly two thirds were due to external or unknown factors. due to the technological limitations and shortfalls of online
With regards to external factors in particular, failures monitoring technologies, however, with the advancement in
attributable to design and manufacturing comprise roughly a measurement, analytical and communications technologies,
fifth of failures, while external short circuits account for online monitoring products and strategies have become more
11.63% of failures. The root cause of 29.08% of failures was reliable and accessible. While offline monitoring activities
unknown. remain important, the scope of this discussion will be
confined to online monitoring, and its capabilities and
Aging was evidently the most influential internal root shortfalls in the context of high voltage circuit breakers and
cause of failure compared to others, however, having been power transformers.
attributed as the cause for only 12.35% of all the failures
analysed, a holistic view must still be taken to ensure that an A. Online Monitoring Visibility
effective monitoring strategy is developed to minimize the The primary objective behind online monitoring, which
risk of failure. should underpin any asset management strategy, is to
monitor assets with a view towards identifying conditions
IV. EFFECTIVE MONITORING TO IDENTIFY ISSUES that would indicate incipient failures. To do so, there are a
Understanding the asset failure modes and their root range of parameters that can be monitored, and a range of
causes allows the development of an effective asset devices that are capable of monitoring those parameters.
monitoring strategy. On this basis, it is possible to ascertain In discussing this topic, it is important to distinguish
the health of an asset based upon analysis of signals provided between monitoring to identify a fault and monitoring to
by its local control and monitoring system, as well as offline identify incipient faults – while both are important,
inspections and measurements. identifying incipient faults can enable the asset owner to
The health of an asset is typically expressed as either a avoid a situation where the fault eventuates, potentially
health index or a probability of failure. A health index reducing or eliminating downtime, mitigating the extent of
comprises several parameters which constitute the condition financial ramifications and maximizing personnel safety.
of an asset, each of which are weighted, and ultimately To ascertain the extent to which failure modes and their
combined to produce a single value. A probability of failure, causes are encompassed by an online monitoring strategy,
on the other hand, is an aggregation of the various they must be correlated to the various parameters which can
likelihoods of failure associated with the parameters being be monitored online which would be indicative of those
monitored. As those parameters deteriorate in terms of an

Fig. 7. Power Transformer Failure Root Cause Distribution


Fig. 8. Correlation Charts, mapping correlations between failure modes and online monitoring solutions for Power Transformers (left) and High
Voltage Circuit Breakers (right).

failures developing. Once a correlation has been established, power transformers indicating mechanical displacements or
the risk of failure can be managed more effectively as degradations within the transformer.
addressing a failure mode by incorporating the correct type
of online monitoring allows the reduction of anticipated risk Beyond this, there will always be the risk of external and
of the failure mode occurring. unknown events that cannot be addressed within the strict
context of online asset-level monitoring.
To that end, the Correlation Charts of Figure 8 have been
developed. The failure modes listed down the vertical axes V. CONCLUSIONS
are those of the CIGRE surveys, and the risks of failure
associated with each of those failure modes are incorporated Online monitoring offers real-time visibility on the health
as per the findings of the surveys. Along the horizontal axes, of assets which comprise critical electrical infrastructure.
currently available online monitoring solutions are listed. This new asset management paradigm enables network
Within the chart area, an ‘X’ is placed to indicate that the operators to act more rapidly and precisely in scenarios
particular failure mode can be addressed to some extent by a where asset health is deteriorating. This is the result of
particular monitoring solution. increased access to valuable condition data, which allows
more powerful trend analysis and monitoring, as well as
B. Online Monitoring White Spots automated diagnostics and maintenance planning.
By applying the complete regime of online monitoring Ultimately, online monitoring enables a targeted, data-
capabilities indicated across the horizontal axes of the driven approach in transitioning from schedule based
Correlation Charts of Figure 8, the maximum risk of failure maintenance to condition based maintenance, enabling the
mitigation can be achieved. However, it must be noted that allocation of resources more efficiently, avoidance of the
doing so does not completely neutralize the risks, nor does it costs associated with an increased risk of failure [3] and
cover all foreseeable root causes of failure. ensuring that the management of the asset risk of failure is as
comprehensive as possible.
The format of the Correlation Charts not only indicates
what failure modes can be addressed using existing solutions,
it also facilitates analysis of any areas lacking either partial ACKNOWLEDGMENT
or full visibility. The most obvious example is the The author gratefully acknowledges A. Poeltl, ABB Inc.,
monitoring for grading capacitor oil leaks – there are and B. Myburgh, ABB Australia Pty Ltd, for their support
currently no standard mechanisms to monitor for this beyond while writing this paper.
offline inspections.
All other failure modes, as outlined by the CIGRE REFERENCES
Sureys, are covered to some extent or another. An in-depth [1] CIGRE Working Group A3.06, “Final report of 2004-2007
analysis can be performed to identify all the root causes international enquiry on reliability of high voltage equipment, Part 2 -
associated with each failure mode and to quantify the reliability of high voltage circuit breakers,” CIGRE TB 510, Oct.
2012.
reduction in the risk of failure as a result of addressing each
[2] CIGRE Working Group A2.37, “TRANSFORMER RELIABILITY
item. SURVEY,” CIGRE TB 642, Dec. 2015.
In general though, it is clear that online monitoring [3] Economics of Transformer Management, CIGRE WG A2.20 TB 248,
capabilities still require further development to cover the 2004.
spectrum of diagnostics that are available via offline [4] B. Desai, M. Walther and J. Haufler, "If It Ain't Broke...," in IEEE
Power and Energy Magazine, vol. 8, no. 6, pp. 48-52, Nov.-Dec.
methods, such as dynamic contact resistance tests for high 2010.
voltage circuit breakers indicating poor contacts or
[5] IEEE Guide for the Selection of Monitoring for Circuit Breakers,
connections, and sweep frequency response analyses for IEEE Std C37.10.1, 2000.

You might also like