PROJECT : COVENT GARDEN NORTH TOWER

SUBJECT : 2 WEEKS LOOKAHEAD MEPFS (SLEEVING)


DATE:MAY 5, 2021

May
Duration
Item Description Start Finish 3 4 5 6 7 8 10 11 12 13
(Days)
1 6th Floor Segment 2
Preparation/Cutting of Pipe Sleeves (5pcs G.I & 60 pcs PVC) 04-May-21 06-May-21 2
Reference Line setting out 07-May-21 07-May-21 1
Installation of Pipe sleeves 06-May-21 08-May-21 3
Inspection and Punchlisting 08-May-21 11-May-21 3
Slab and Beam Concreting 12-May-21 12-May-21 1
2 8th Floor Segment 1
Mechanical Block outs 11-May-21 12-May-21 2
Preparation/Cutting of Pipe Sleeves 13-May-21 14-May-21 2