FORM 002

BANDING INSPECTION REPORT

Client : PT. PERTAMINA (PERSERO) Report No. : 10/BANDING/QC-PBAS/X/2018


Project : Pembangunan Tanki Air Kap 5000 KL Contract No. : PPJ-015/F.12400/2017-S5
Tank Name: Storage Tank
Tank No. : T15
Location : TBBM Kertapati, Palembang
Arrangement
Bending Tolerance : Max ± 13 mm
Refer to API STD 650 Para 7.5.4 (b)
Course
SKETCH JOINT NO A B C DEVIATION No. Remark

C5H53 0 0 0 0 5 to 6 ACC
A B

C5H54 0 0 0 0 5 to 6 ACC

C5H55 0 0 0 0 5 to 6 ACC
a b c
C5H56 0 0 0 0 5 to 6 ACC
C
C5H57 0 0 0 0 5 to 6 ACC

SWEEP BOARD C5H58 0 0 0 0 5 to 6 ACC

WELDING
HORIZONTAL C5H59 0 0 0 0 5 to 6 ACC

C5H60 0 0 0 0 5 to 6 ACC

C5H61 0 0 0 0 5 to 6 ACC

C5H62 0 0 0 0 5 to 6 ACC

C5H63 0 0 0 0 5 to 6 ACC

C5H64 0 0 0 0 5 to 6 ACC

C5H65 0 0 0 0 5 to 6 ACC
Comment : After Welding

Prepared By, Review / Witness By, Approved by:


PT. PBAS PT. PBAS PT. Pertamina (persero) MOR II

SEPTIMAN RUDI DARMANTO Fahmi A. Husain


Date : Date : Date :
FORM 002
FORM 002

BANDING INSPECTION REPORT

Client : PT. PERTAMINA (PERSERO) Report No. : 09/BANDING/QC-PBAS/X/2018


Project : Pembangunan Tanki Air Kap 5000 KL Contract No. : PPJ-015/F.12400/2017-S5
Tank Name: Storage Tank
Tank No. : T15
Location : TBBM Kertapati, Palembang
Arrangement
Bending Tolerance : Max ± 13 mm
Refer to API STD 650 Para 7.5.4 (b)
Course
SKETCH JOINT NO A B C DEVIATION No. Remark

C5H53 0 0 0 0 5 to 6 ACC
A B

C5H54 0 0 0 0 5 to 6 ACC

C5H55 0 0 0 0 5 to 6 ACC
a b c
C5H56 0 0 0 0 5 to 6 ACC
C
C5H57 0 0 0 0 5 to 6 ACC

SWEEP BOARD C5H58 0 0 0 0 5 to 6 ACC

WELDING
HORIZONTAL C5H59 0 0 0 0 5 to 6 ACC

C5H60 0 0 0 0 5 to 6 ACC

C5H61 0 0 0 0 5 to 6 ACC

C5H62 0 0 0 0 5 to 6 ACC

C5H63 0 0 0 0 5 to 6 ACC

C5H64 0 0 0 0 5 to 6 ACC

C5H65 0 0 0 0 5 to 6 ACC
Comment : Before Welding

Prepared By, Review / Witness By, Approved by:


PT. PBAS PT. PBAS PT. Pertamina (persero) MOR II

SEPTIMAN RUDI DARMANTO Fahmi A. Husain


Date : Date : Date :
FORM 002
FORM 002

BANDING INSPECTION REPORT

Client : PT. PERTAMINA (PERSERO) Report No. : 08/BANDING/QC-PBAS/X/2018


Project : Pembangunan Tanki Air Kap 5000 KL Contract No. : PPJ-015/F.12400/2017-S5
Tank Name: Storage Tank
Tank No. : T15
Location : TBBM Kertapati, Palembang
Arrangement
Bending Tolerance : Max ± 13 mm
Refer to API STD 650 Para 7.5.4 (b)
Course
SKETCH JOINT NO A B C DEVIATION No. Remark

C4H40 0 0 0 0 4 to 5 ACC
A B

C4H41 0 0 0 0 4 to 5 ACC

C4H42 0 0 0 0 4 to 5 ACC
a b c
C4H43 0 0 0 0 4 to 5 ACC
C
C4H44 0 0 0 0 4 to 5 ACC

SWEEP BOARD C4H45 0 0 0 0 4 to 5 ACC

WELDING
HORIZONTAL C4H46 0 0 0 0 4 to 5 ACC

C4H47 0 0 0 0 4 to 5 ACC

C4H48 0 0 0 0 4 to 5 ACC

C4H49 0 0 0 0 4 to 5 ACC

C4H50 0 0 0 0 4 to 5 ACC

C4H51 0 0 0 0 4 to 5 ACC

C4H52 0 0 0 0 4 to 5 ACC
Comment : After Welding

Prepared By, Review / Witness By, Approved by:


PT. PBAS PT. PBAS PT. Pertamina (persero) MOR II

SEPTIMAN RUDI DARMANTO Fahmi A. Husain


Date : Date : Date :
FORM 002
FORM 002

BANDING INSPECTION REPORT

Client : PT. PERTAMINA (PERSERO) Report No. : 07/BANDING/QC-PBAS/IX/2018


Project : Pembangunan Tanki Air Kap 5000 KL Contract No. : PPJ-015/F.12400/2017-S5
Tank Name: Storage Tank
Tank No. : T15
Location : TBBM Kertapati, Palembang
Arrangement
Bending Tolerance : Max ± 13 mm
Refer to API STD 650 Para 7.5.4 (b)
Course
SKETCH JOINT NO A B C DEVIATION No. Remark

C4H40 0 0 0 0 4 to 5 ACC
A B

C4H41 0 0 0 0 4 to 5 ACC

C4H42 0 0 0 0 4 to 5 ACC
a b c
C4H43 0 0 0 0 4 to 5 ACC
C
C4H44 0 0 0 0 4 to 5 ACC

SWEEP BOARD C4H45 0 0 0 0 4 to 5 ACC

WELDING
HORIZONTAL C4H46 0 0 0 0 4 to 5 ACC

C4H47 0 0 0 0 4 to 5 ACC

C4H48 0 0 0 0 4 to 5 ACC

C4H49 0 0 0 0 4 to 5 ACC

C4H50 0 0 0 0 4 to 5 ACC

C4H51 0 0 0 0 4 to 5 ACC

C4H52 0 0 0 0 4 to 5 ACC
Comment : Before Welding

Prepared By, Review / Witness By, Approved by:


PT. PBAS PT. PBAS PT. Pertamina (persero) MOR II

SEPTIMAN RUDI DARMANTO Fahmi A. Husain


Date : Date : Date :
FORM 002
FORM 002

BANDING INSPECTION REPORT

Client : PT. PERTAMINA (PERSERO) Report No. : 06/BANDING/QC-PBAS/IX/2018


Project : Pembangunan Tanki Air Kap 5000 KL Contract No. : PPJ-015/F.12400/2017-S5
Tank Name: Storage Tank
Tank No. : T15
Location : TBBM Kertapati, Palembang
Arrangement
Bending Tolerance : Max ± 13 mm
Refer to API STD 650 Para 7.5.4 (b)
Course
SKETCH JOINT NO A B C DEVIATION No. Remark

C3H27 0 0 0 0 3 to 4 ACC
A B

C3H28 0 0 0 0 3 to 4 ACC

C3H29 0 0 0 0 3 to 4 ACC
a b c
C3H30 0 0 0 0 3 to 4 ACC
C
C3H31 0 0 0 0 3 to 4 ACC

SWEEP BOARD C3H32 0 0 0 0 3 to 4 ACC

WELDING
HORIZONTAL C3H33 0 0 0 0 3 to 4 ACC

C3H34 0 0 0 0 3 to 4 ACC

C3H35 0 0 0 0 3 to 4 ACC

C3H36 0 0 0 0 3 to 4 ACC

C3H37 0 0 0 0 3 to 4 ACC

C3H38 0 0 0 0 3 to 4 ACC

C3H39 0 0 0 0 3 to 4 ACC
Comment : After Welding

Prepared By, Review / Witness By, Approved by:


PT. PBAS PT. PBAS PT. Pertamina (persero) MOR II

SEPTIMAN RUDI DARMANTO Fahmi A. Husain


Date : Date : Date :
FORM 002
FORM 002

BANDING INSPECTION REPORT

Client : PT. PERTAMINA (PERSERO) Report No. : 05/BANDING/QC-PBAS/IX/2018


Project : Pembangunan Tanki Air Kap 5000 KL Contract No. : PPJ-015/F.12400/2017-S5
Tank Name: Storage Tank
Tank No. : T15
Location : TBBM Kertapati, Palembang
Arrangement
Bending Tolerance : Max ± 13 mm
Refer to API STD 650 Para 7.5.4 (b)
Course
SKETCH JOINT NO A B C DEVIATION No. Remark

C3H27 0 0 0 0 3 to 4 ACC
A B

C3H28 0 0 0 0 3 to 4 ACC

C3H29 0 0 0 0 3 to 4 ACC
a b c
C3H30 0 0 0 0 3 to 4 ACC
C
C3H31 0 0 0 0 3 to 4 ACC

SWEEP BOARD C3H32 0 0 0 0 3 to 4 ACC

WELDING
HORIZONTAL C3H33 0 0 0 0 3 to 4 ACC

C3H34 0 0 0 0 3 to 4 ACC

C3H35 0 0 0 0 3 to 4 ACC

C3H36 0 0 0 0 3 to 4 ACC

C3H37 0 0 0 0 3 to 4 ACC

C3H38 0 0 0 0 3 to 4 ACC

C3H39 0 0 0 0 3 to 4 ACC
Comment : Before Welding

Prepared By, Review / Witness By, Approved by:


PT. PBAS PT. PBAS PT. Pertamina (persero) MOR II

SEPTIMAN RUDI DARMANTO Fahmi A. Husain


Date : Date : Date :
FORM 002
FORM 002

BANDING INSPECTION REPORT

Client : PT. PERTAMINA (PERSERO) Report No. : 04/BANDING/QC-PBAS/IX/2018


Project : Pembangunan Tanki Air Kap 5000 KL Contract No. : PPJ-015/F.12400/2017-S5
Tank Name: Storage Tank
Tank No. : T15
Location : TBBM Kertapati, Palembang
Arrangement
Bending Tolerance : Max ± 13 mm
Refer to API STD 650 Para 7.5.4 (b)
Course
SKETCH JOINT NO A B C DEVIATION No. Remark

C2H14 0 0 0 0 2 to 3 ACC
A B

C2H15 0 0 0 0 2 to 3 ACC

C2H16 0 0 0 0 2 to 3 ACC
a b c
C2H17 0 0 0 0 2 to 3 ACC
C
C2H18 0 0 0 0 2 to 3 ACC

SWEEP BOARD C2H19 0 0 0 0 2 to 3 ACC

WELDING
HORIZONTAL C2H20 0 0 0 0 2 to 3 ACC

C2H21 0 0 0 0 2 to 3 ACC

C2H22 0 0 0 0 2 to 3 ACC

C2H23 0 0 0 0 2 to 3 ACC

C2H24 0 0 0 0 2 to 3 ACC

C2H25 0 0 0 0 2 to 3 ACC

C2H26 0 0 0 0 2 to 3 ACC
Comment : After Welding

Prepared By, Review / Witness By, Approved by:


PT. PBAS PT. PBAS PT. Pertamina (persero) MOR II

SEPTIMAN RUDI DARMANTO Fahmi A. Husain


Date : Date : Date :
FORM 002
FORM 002

BANDING INSPECTION REPORT

Client : PT. PERTAMINA (PERSERO) Report No. : 03/BANDING/QC-PBAS/IX/2018


Project : Pembangunan Tanki Air Kap 5000 KL Contract No. : PPJ-015/F.12400/2017-S5
Tank Name: Storage Tank
Tank No. : T15
Location : TBBM Kertapati, Palembang
Arrangement
Bending Tolerance : Max ± 13 mm
Refer to API STD 650 Para 7.5.4 (b)
Course
SKETCH JOINT NO A B C DEVIATION No. Remark

C2H14 0 0 0 0 2 to 3 ACC
A B

C2H15 0 0 0 0 2 to 3 ACC

C2H16 0 0 0 0 2 to 3 ACC
a b c
C2H17 0 0 0 0 2 to 3 ACC
C
C2H18 0 0 0 0 2 to 3 ACC

SWEEP BOARD C2H19 0 0 0 0 2 to 3 ACC

WELDING
HORIZONTAL C2H20 0 0 0 0 2 to 3 ACC

C2H21 0 0 0 0 2 to 3 ACC

C2H22 0 0 0 0 2 to 3 ACC

C2H23 0 0 0 0 2 to 3 ACC

C2H24 0 0 0 0 2 to 3 ACC

C2H25 0 0 0 0 2 to 3 ACC

C2H26 0 0 0 0 2 to 3 ACC
Comment : Before Welding

Prepared By, Review / Witness By, Approved by:


PT. PBAS PT. PBAS PT. Pertamina (persero) MOR II

SEPTIMAN RUDI DARMANTO Fahmi A. Husain


Date : Date : Date :
FORM 002
FORM 002

BANDING INSPECTION REPORT

Client : PT. PERTAMINA (PERSERO) Report No. : 02/BANDING/QC-PBAS/VIII/2018


Project : Pembangunan Tanki Air Kap 5000 KL Contract No. : PPJ-015/F.12400/2017-S5
Tank Name: Storage Tank
Tank No. : T15
Location : TBBM Kertapati, Palembang
Arrangement
Bending Tolerance : Max ± 13 mm
Refer to API STD 650 Para 7.5.4 (b)
Course
SKETCH JOINT NO A B C DEVIATION No. Remark

C1H1 0 0 0 0 1 to 2 ACC
A B

C1H2 0 0 0 0 1 to 2 ACC

C1H3 0 0 0 0 1 to 2 ACC
a b c
C1H4 0 0 0 0 1 to 2 ACC
C
C1H5 0 0 0 0 1 to 2 ACC

SWEEP BOARD C1H6 0 0 0 0 1 to 2 ACC

WELDING
HORIZONTAL C1H7 0 0 0 0 1 to 2 ACC

C1H8 0 0 0 0 1 to 2 ACC

C1H9 0 0 0 0 1 to 2 ACC

C1H10 0 0 0 0 1 to 2 ACC

C1H11 0 0 0 0 1 to 2 ACC

C1H12 0 0 0 0 1 to 2 ACC

C1H13 0 0 0 0 1 to 2 ACC
Comment : After Welding

Prepared By, Review / Witness By, Approved by:


PT. PBAS PT. PBAS PT. Pertamina (persero) MOR II

SEPTIMAN RUDI DARMANTO Fahmi A. Husain


Date : Date : Date :
FORM 002
FORM 002

BANDING INSPECTION REPORT

Client : PT. PERTAMINA (PERSERO) Report No. : 01/BANDING/QC-PBAS/VIII/2018


Project : Pembangunan Tanki Air Kap 5000 KL Contract No. : PPJ-015/F.12400/2017-S5
Tank Name: Storage Tank
Tank No. : T15
Location : TBBM Kertapati, Palembang
Arrangement
Bending Tolerance : Max ± 13 mm
Refer to API STD 650 Para 7.5.4 (b)
Course
SKETCH JOINT NO A B C DEVIATION No. Remark

C1H1 0 0 0 0 1 to 2 ACC
A B

C1H2 0 0 0 0 1 to 2 ACC

C1H3 0 0 0 0 1 to 2 ACC
a b c
C1H4 0 0 0 0 1 to 2 ACC
C
C1H5 0 0 0 0 1 to 2 ACC

SWEEP BOARD C1H6 0 0 0 0 1 to 2 ACC

WELDING
HORIZONTAL C1H7 0 0 0 0 1 to 2 ACC

C1H8 0 0 0 0 1 to 2 ACC

C1H9 0 0 0 0 1 to 2 ACC

C1H10 0 0 0 0 1 to 2 ACC

C1H11 0 0 0 0 1 to 2 ACC

C1H12 0 0 0 0 1 to 2 ACC

C1H13 0 0 0 0 1 to 2 ACC
Comment : Before Welding

Prepared By, Review / Witness By, Approved by:


PT. PBAS PT. PBAS PT. Pertamina (persero) MOR II

SEPTIMAN RUDI DARMANTO Fahmi A. Husain


Date : Date : Date :