Professional Documents
Culture Documents
Eyob
Eyob
ACKNOWLEDGEMENTS ............................................................................................................................ iv
Abbreviation.................................................................................................................................................... vi
CHAPTER-1 .................................................................................................................................................... 1
INTRODUCTION............................................................................................................................................ 1
Energizing Ethiopia’s sustainable gross and enabling it to be power hub of Africa. ................................... 1
CHAPTER-2 .................................................................................................................................................... 4
2.1 Over all system component and operation over view ............................................................................ 4
i
2.7.1 Hydraulic turbine............................................................................................................................. 9
CHAPTER -3 ................................................................................................................................................. 25
A. In maintenance .................................................................................................................................. 25
3.1 The procedures we have been using while performing our work tasks ............................................... 25
3.2 Challenges that we have been facing during performing our task ....................................................... 26
CHAPTER-4 .................................................................................................................................................. 27
ii
4. Problems assigned ...................................................................................................................................... 27
Abstract .......................................................................................................................................................... 27
Introduction .................................................................................................................................................... 27
Objectives ....................................................................................................................................................... 28
CHAPTER-5 .................................................................................................................................................. 31
5.1 Conclusion............................................................................................................................................ 31
Reference........................................................................................................................................................ 32
iii
ACKNOWLEDGEMENTS
First of all we would like to great thanks for MIZAN-TEPI University, for Electrical and
computer Engineering Department head (Miss MESERET) and for University industry linkage
office (DR. SHEGAW) for giving this opportunity of being parts of the internship program.
We want to say special thanks for the following persons and organizations that contributes great
role in our four month internship program.we would like to thank our company supervisor Miss
ADEY and Miss ABEBA who helped us a lot in gathering different information and about giving
data and guides from time to time in making internship program and also we want to say special
thanks to all Belles Hydropower plant workers.
iv
List of figure
Figure 1 generation operation organizational structure of EEP ....................................................................... 3
Figure 2 the general overview of Beles hydropower plant .............................................................................. 4
Figure 3: Principal operation of hydropower ................................................................................................... 5
Figure 4 components of intake ......................................................................................................................... 6
Figure 5 hydrualic turbine ................................................................................................................................ 9
Figure 6 over all MIV system ........................................................................................................................ 12
Figure 7 generator circuit breaker .................................................................................................................. 15
Figure 8 over all water cooling system ......................................................................................................... 18
Figure 9 Fire Fighting System ........................................................................................................................ 19
Figure 10 general over view of switchyard .................................................................................................... 21
Figure 11 general flow chart for diesel generator .......................................................................................... 28
List of tale
v
Abbreviation
EEPCO……………………………………….Ethiopian Electric Power Corporation
DC……………………………………………Direct current
AC……………………………………………Alternating Current
KV……………………………………………..Kilo Volt
mA……………………………………………..mili Amper
MW……………………………………………Mega Watt
CW…………………………………………….Clock Wise
vi
ABSTRACT
This report document includes Tana Belles generating station overview and back ground of the
company.The importance of the internship program is obviously known in education. Because it
gives the student a chance to link his/her theoretical background to the real world applications. It
also helps the student to develop different personal skills. This company is responsible for
generating an electrical energy. During our intern we know general idea about hydro power plant
and basic components of this generation like intake, power house, distribution board, out let and
switch yard and also how the control system analysis, measurement, Inspections, Maintenance and
using different equipment to maintain temporary as well as permanent faults. Over all about
internship, benefits obtained in internship, principal operation of hydro power plant and their
components, recommendations and reference.
vii
i
i
CHAPTER-1
INTRODUCTION
1.2 Vision
1.3 Mission
To be A world class utility and contribute do days nation building by insuring delivery of coast,
effective ,safe, and high quality power and to enable inter connection across Africa contents for
exporting surplus power. EEU shall strict towards achieving international standards for customer
1
care through subtend capacity building, operational and financial excellence, state-of-the-art
technology while insuring higher standards of corporate governance and ethics”.
2
Figure 1 generation operation organizational structure of EEP
3
CHAPTER-2
In The Beles multipurpose project water from Lake Tana is taken via the intake structures. These
structures are the main gats for the water to enter the whole system. Hence we have tried to explain
the flow of water form this intake structures to the outlet where the water is finally combined with
the Jehana River after finishing its journey through the tunnel and goes to give yet another use for
irrigation in the surrounding area.
4
The mechanical energy produced by the turbine is converted into electrical energy using a
turbine and generator shaft. Inside the generator, the shaft of the turbine spins a magnet
inside coils of copper wire. It is a fact of nature that moving a magnet near a conductor
causes an electric current.
2.4 Intake
It is the inlet structure of the plant which provides water to the turbine through head race tunnel
and penstock. It has about 12km long from the power house and the water flows underground.
5
E- Wheel gates
A. Approach channel
The approach channel draws the water from the Lake Tana and conveys it to the headrace tunnel.
It subdivided in two sections, upstream and downstream of the channel inlet structure. Upstream
section is a channel structure which provides water from Lake Tana to stop logs. Downstream side
covers from stop logs to track rash machine.
The inlet structure is provided with five sluices and 15 (fifteen) Stop logs elements. To isolate the
Lake from power intake and to do inspection and maintenance activities on its downstream Side
During the plant working, these sluices are open and the stop logs are stored on the top of the inlet
structure by means of proper supports.
6
C.Intake trash rack machine
The machine is used to clean the trash rack screen panels by removing floating debris, that is
coming with water and to facilitate the passage of water to the tunnel.
To isolate the Power intake from downstream tunnel & to allow inspection and maintenance of the
intake wheel gates and head race Tunnel.
Installed downstream side of Trash Rack Panels. It is also used balance water pressure by using
by-pass flow of water. It is operated under balanced condition only.
E. Wheel/hydraulic gates
To allow maintenance and inspection of the power tunnel. Installed downstream of the Bulkhead
gate.
F. Control room
Inside the control room of the intake step down transformer, standby diesel generator for
emergency (100KVA) 110V DC batteries, etc are present.
Length-11.823Km
Excavated Diameter-8.1m
Finished diameter-7.2m
H. Surge shaft
A structure found right before the pen stalk shaft. Its main purpose is to provide space for the
water to reside whenever the main inlet valve is closed and hence preventing back flow of the
Water. It Is 91 m high.
7
2.6 Power house
Depending up on the topography and the geology of the surface the power house can be located
on the surface, underground or semi underground. Fully underground and Excavated with Drill
and Blast Technology In which many electromechanical equipment, Control buildings, Offices,
medium store, Power Transformer and so on Work shop are situated .It has the 97m length, 18m
wide and 40m height. Inside the power house there are four floors, those are
Machine floor
Generator floor
Turbine floor and
Spiral casing and
MIV floor.
8
2.7.1 Hydraulic turbine
Turbines transfer energy from working fluid to rotor. They act as prime movers. In hydro turbines
the fluid is water. Potential/kinetic energy of water is converted to mechanical rotational energy by
turbine. Flowing water is directed on to the blades of a turbine runner, creating a force on the
blades.Since the runner is spinning, the force acts through a distance (force acting through a
distance is the definition of work). In this way, energy is transferred from the water flow to the
turbine. Water turbines are divided into two groups; reaction turbines and impulse turbines
Francis
Reaction
Kaplan and
Turbine
propeller
Impulse Pelton
The BELES hydroelectric power plant consists of four vertical shaft Francis turbines. The Francis
turbine is coupled to a Generator and the runner Blade quantity is 17. Sense of rotation c.w. Its
Rated power 115 MW and the Runner consists of blades welded to the hub and crown. It is
coupled to the shaft by means of 8 bolts, pre-stressed with hydraulic jacks, and 8 calibrated pins.
The rotor labyrinths are integrated in the runner. The turbine is generally operated under automatic
control, but can be operated under Manual control during maintenance and commissioning. Under
manual control can be operated from the governor panel, while under automatic control shall be
monitored from the Remote Automatic Control located in the control room.
9
Runner: It is the structure of the turbine which rotates due to the water pressure applied and
connected to the turbine shaft. Sense of rotation c.w.
Spiral case: It constitutes the turbine supporting structure and the water supply system.
Draft tube: Manufactured of welded plate and shaped in sectors according to the ideal hydraulic
Turbine shaft: The turbine shaft is forged steel, flanged at its ends to the coupling of the runner
2.7.2 Governor
an attachment to a machine for automatic control or limitation of speed /power/dam water
level/flow of water. A Governor is a device which controls the energy source (Water) to a prime
mover to generate power for a specific purpose. Governor senses Speed, Position, water level and
flow of water to a prime mover and adjust the energy source to maintain the desired level
frequency & power. These need to be regulated properly for stable and accurate output for good
performance.
A. Turbine governor, what for?
By regulating the flow of water passing through the turbine, the governor adjusts the power output
bring sent to the grid.
This is done by:
Opening/closing the wicket gates for Francis/ Pump turbine.
Opening/closing the wicket gates and runner blades for Kaplan/Bulb turbine.
10
Opening/closing the injectors /deflectors for Peloton Turbine
.
Wicket Gate: is key component in hydroelectric turbines that control the flow of water from the
input pipes (Penstock) to the turbine Propellers/blades inside the house of the turbine.
11
It has their oil tank, pump, heat exchanger, filter, accumulator and air compressor for hydraulic
purpose.
Electrical equipments
2.8.1 Generator
Mechanical rotational energy is converted to electrical energy by generator. There are two types of
generators: hydro generator (driven by water turbine) and turbo alternator (driven by steam
turbine)
12
Rated out put 133MVA
The BHPP has 16 pole synchronous generator and 115MW power produced. Let as illustrate how
it came from the fundamental energy formula.
Q_ discharge water=40m3/sec
G _ gravity =9.81m/sec2
H _ head =315m
ρ _ Density of water=1000kg/m3
P =1000kg/m3*9.81m/sec2*40m3/sec*315m*0.98
P=121.6MW
From the turbine manufacturer we are given a speed of 375 rpm. Using this value we can get the
no. of poles using the formula:
P=120f/ns where f= 50 Hz
Ns-synchronous speed =375rpm
P= (120 * 50 Hz)/375rpm
P=16 poles
13
We can deduce that we need flow of liquid and height through which the liquid is accelerated to
produce power. In BMPP the liquid (H2O) is obtained from a natural reservoir, Lake Tana.The
water is drawn from the lake by the intake structure and via 11.8Km tunnel and it gives to the
penstock. This part provides the head needed. The flow (discharge) is divided in to 4(hence the
power will be multiplied by 4 to get the total output power of the power plant)
Stator core: It Provides House for stator windings. Used to achieve radial air ducts, the stator core
is divided into axial packets of laminations.
14
Figure7 generator circuit breaker
4 Step-Up Transformers:
Power 133 MVA
Voltage 15 / 400 kV
Cooling OFWF
15
The power can be transmitted over a long distance with minimum I2R losses.
Is an offline tap changer because a constant output of 400KV is needed.
Has a Y delta connection.
Switchgear: it is a control panel used to receive 15kv from each unit through auxiliary
transformer. Then it gives 15kv to the switchyard then outlet, intake, housing compounds. Also
15kv from switchgear tapped to the station service transformers. Then it converts to 400v to give
supply power house AC device.
16
which comprises of the automatic voltage regulator (AVR) and the rectifying unit. The output of
the excitation system is DC value. To accomplish this rectifying unit is used. The rectifying unit is
mainly composed of thyruisters and Power diodes which are connected by bridge network.The
rectifying unit is provided for each phase and also a spare is available in case of damage. The AVR
is used to maintain the output voltage constant by varying the field excitation current. The AVR
gets its feedback by CT and VT from the terminal side of the generator. The excitation system is
also used to supply one 110V DC to the power house equipments which operate using DC current.
The raw water which is open circuit is called primary cooling system. Its main function is cooling
the secondary through heat exchanger. The other is closed circuit system which is called as
secondary cooling system. The cooling system for Beles Multipurpose Project supplies cool water
to the following users:
17
Figure 7 over all water cooling system 2 1
18
Figure 8 Fire Fighting System
Disconnected with earthling blade: Which is to open after the circuit breaker is opened and
used for grounding residual current during maintenance time.
Current transformer: It is an instrument transformer used for measuring the amount of current
passing through the system. Works on the principle of induction to measure the level of line
current its primary winding the main line and the secondary winding is coiled around the main line
which can be adjusted according to the conversion needed and also used for control and safety
purposes.
19
condition and, by interrupting continuity, to immediately discontinue electrical flow. Unlike a
fuse, which Operates once and then has to be replaced, a circuit breaker can be reset (either
manually or automatically) to resume normal operation. Circuit breakers are made in varying sizes,
from small devices that protect an individual household appliance up to large switchgear designed
to protect high voltage circuits feeding an entire city. When the circuit breaker are open and closed
arc will be produced. To quench that arc we use different medium in the circuit breaker. Those are
air, vacuum, SF6, and oil. In case of BHPP, due to high voltage in the switchyard SF6 circuit
breaker will used.
Pantograph disconnectors: It has 3 poles each poles consist of support insulator, one rotating
insulator a pantograph mechanism and a counter contact. These disconnectors are equipped with
insulators the pantograph mechanism is installed on the support insulator and transfers the
movement of the rotating insulator to the arms of the pantograph disconnectors. The main contacts
are made of copper with silver plated surface. The counter contact is a horizontal bar which is also
silver plated which has to connected to the bus bar system, the disconnectors can be motor or hand
driven. It is used to disconnect the bus bars from the system.
Bus bar: It is a hollow circular aluminum bar with diameter 12cm and 1.2cm thickness .It is used
to connect the incoming lines of each generator and each phase to the outgoing transmission lines
of the respective phase at constant voltage and it provides a steady working condition of the
switchyard.
Capacitor voltage transformer: It is another type of instrument transformer mainly used for
measuring the voltage of the bus bar and the outgoing lines for control and synchronization.
Whatever any fault occurs in the switchyard can control in the control room through different
level. These are:
Mimic control: The mimic panel control level is used only to control high voltage circuit breakers,
disconnectors and earthing switches.
Field control: method of control by giving command outside the control panel.
Bay control: the commands can be executed using the command display and the keyboard of the
20
Bay Control Unit devices installed in the protection/control panels in the switchyard control room;
SCADA control system: is the remote command level, commands are initiated from the SCADA
system/Operator Stations.
21
We improve team playing skill
We improve leadership skill
We improve interpersonal communication skill
We improve understanding of work ethics and
We improve entrepreneurship skill
When we are within team playing, anyone can raise his opinion.
During team playing, our concept may be varied. At this moment respect others idea.
Ideal disputes were solved through peaceful communication.
With our friends as a team player tried to modify and give solution for some technical
challenges that exposed in the company.
It is the position of being a person who leads a group of people in an organization. Based on the
following ways;
Self-confidence is the requirement of good leadership.
22
Good understanding of things than the others.
By open minded (optimist).
By logical, when you are tried to clarify the issue by relating with science.
23
2.10.7To improve entrepreneurship skill
The most obvious form of entrepreneurship is that starting new business. In the way of the
following;
Being motivated to solve technical problems.
Always being ready to create better world for yourself and your country as a whole
Be sure your mind is in work every time. Make yourself as much as busy as you can. We
will try to analyze what we have done on the company. Generally, be entrepreneur with
your mind not with your money.
Being risk taker is the core point in entrepreneurship skill i.e. with your money, time and
knowledge.
When you want to be an entrepreneur don’t be hopeless. Things may get to go worthy, at
that time be hopeful for the bright future.
24
CHAPTER -3
3. Task assigned
A.In the maintenance
B.Inspection system
A. In maintenance
Repair water pump
Carbon Brush replacement
Cleaned primarily filter when it is dirty
Air injection compressor cleaned and full’s the level of oil in the accumulator when the
level decreases.
B.Inspection
Governor hydraulic system operating pressure (not greater or less than 56.6 bar)
Oil linkage around in the main transformer
Oil linkage around in the Governor
the level of oil the compressor
The condition of Governor Pump by observation
Specific gravity of electro light of the 110Vdc and 48Vdc station battery (2.25)
3.1 The procedures we have been using while performing our work tasks
We have been oriented with the responsibility of our job by communicating with our company
supervisor (adviser) and company workers (staff workers). Additionally we have been fulfilled our
responsibility by accessing internet. The courses which we have been taking in campus are
essential to execute our job.
Generally, we have been oriented with the responsibilities of our job by interrelating with
company supervisor and staff workers and by organizing the knowledge which we have been got
from campus. In addition,
Find the problem during inspection
25
manuals about the machine that are failed and collecting data from it
Asking the operators, company supervisor and observing when Reading they perform
every things around them.
3.2 Challenges that we have been facing during performing our task
There is shortage of transportation.
There is a repetition of work task.
There is a shortage of pure water.
The is no enough computers in the company.
There is no clinic.
There is unsafe rood construction from Bahir dar to the work place
26
CHAPTER-4
4. Problems assigned
Abstract
Standby diesel generator is important when the blackout is occurred in the interconnected power
system (ICS) as well as self-connected system (SCS) of any power plant. But the capacity of the
diesel generator should be analyzed so, we analysis the load flow of BHPP diesel generator.
Background
Introduction
Diesel Generators play a major role in the Power Generation Industry. For HPP they not only
provide back-up power for the generating units, but in most cases also provide emergency power
to the spillway gates that are used to prevent over topping of a dam when flooding conditions exist
and threaten populated areas downstream of these facilities. There are usually two or more diesel
generators at modern dam sites due to the distances between the spillway controls and the Power
Plant.
Substations and switchyards contain the components needed to distribute and deliver electricity at
a desired voltage to the power companies customers. Circuit breakers, transformers, protective
relaying and the communication systems that control these devices, all require a backup power
source whenever power is lost to the station. It is also used for “black start” procedures by giving
supply to make ready.
27
4.1 Problem statement
Before two or three years the diesel generator was give supply for all parts power center (intake,
power house (PH), switchyard (SY) Outlet and housing compound (HC)). But now it gives supply
only for power house (PH) and switchyard (SY). So, we initiate analysis the load flow or load
capacity of the diesel generator.
Objectives
4.2Main objectives
The main objectives of this project are analysis and understand the load capacity of the generator.
This analysis is done by recording data in manual and scada system.
4.4 Methodology
We use the hard ware or flow chart to describe our project.
Diesel generator
Outlet HC GS GS GS PH
SY PH CB MCC
28
4.5 Solution
In currently the tana beles HPP the data shows in the intake, power house, switchyard, housing
coumpound and outlet the power consumption of mechanical and electrical devices is 640.472 kW
but the generator rated value is 640 kw.so the generator capacity value and operation value is
different. In these cases these operation value is greater than the generator rated value by 0.472kw.
In such case the generator is overloaded. So, we decrease the load and use it for basic and
necessary components only. So the maintenance staff must check the connection of the generator
that supplies for dc and ac components. And also to give priority for essential services and isolate
non essential services.
29
30
CHAPTER-5
5.1 Conclusion
In our intern period we got practical knowledge about the machines in the company and their
working principles, how to control, how to maintain, how to operate and how to electrical energy
produced .We also know the general characteristics and component of hydro power plant.
Our task during the internship was to observe mechanical and electrical equipment’s and
understand their methods of operation. Based on the major findings presented above its easy to
understand that internship has a great significant in up grading student’s theoretical knowledge and
improve practical skill.
31
5.4 Recommendation for department
We also recommend to the department to know the specific companies of the intern students with
short period of time and check the mentor (advisor) to get the student at that specific company with
proper time interval.
It is better to have good relation to company.
Reference
1 .Andritz Hydro,(2009) DIA TECH Monitoring & Diagnosis System Beles
2. ELC_BEL_SAL_1368 by Matousek (2010) Operation & Maintenance manual excitation
system, Modification acc. Letter.
3. EEPCo, „Facts in Brief 2007
4. Hu ZL, Chen ZH, xiaJT, etal.( 2008) Effect of positive voltage factor on the wear of
carbon brush for micrometers wear.
5. Manual
6. Qt’sh Gang’ FENGYi CHENFanyan, LIU WenHong, ZHANL, XUeBin, LIU yanFang.
7. Vatech Hydro, (2011) Calculation note.
6.Vatech Hydro, (2011) operation & maintenance manual control system.
7. Vatech Hydro, (2011) painting specification of component
32