Dodoma Silos| Weekly Progress Report No 93, March 2020

WEEKLY PROGRESS REPORT: WPR 93, 16th March 2020


For

Proposed Design, Supply, Construction, Test and Commission of


Silo Complexes, Warehouses and Rehabilitation of Existing
Facilities for National Food Reserve Agency of Tanzania – Lot 07
(Dodoma)

Client: NATIONAL FOOD RESERVE AGENCY


OF TANZANIA (NFRA)
Main Contractor: FEERUM SPOLKA AKCYJNA
Civil Sub-Contractor: WESONS TANZANIA LIMITED
Architect: SPACE CONSULT ARCHITECT (T) LTD
Structural Engineer: CLASSIC PLAN (T) LTD
Service Engineers POWER CONSULT LTD
Quantity Surveyor: CONSTRUCTION PROJECTS
CONSULTANCY LTD

Page 1|8
Dodoma Silos| Weekly Progress Report No 93, March 2020

1. CONTRACT INFORMATION
Date of Site Possession: 20th March 2018
NFRA Site Handover: 28th May 2018
Mobilization Period: 14 Days
Start Date: 12th June 2018
Completion Date: 11th December 2019
Contract period: 18months
Proposed extension: 6 months
Granted extension: 6 months – 30th June 2020
Time elapsed: 92 weeks
Delays 4 weeks
Insurance:
General progress: 99% (Silo Complex Foundations)
70% (Steel structure assembly and installation)
50% (Other Buildings)

2. EQUIPMENTS & TOOLS ON SITE


No Item Qty Condition
.
1 Bar bending machine 4 Good
2 Bar cutting machine 1 Faulty motor and in need of
repair
3 Submersible dewatering pump 2 Good
4 Dewatering motor pump 1 Good
5 Water pump 2 Both damaged and were
replaced
6 Walk behind trowel 900m with 2 Good
attachments
7 Aluminium ladder 3x14 2 Usable
8 Plate bending machine 1 Good
9 Wet screed with attaching blades 1 Good
10 Floor saw 1 Good
11 Concrete breaker hammer 1 Faulty, overheats when used.
12 Electric internal vibrator for concrete 2 Good
compaction
13 Modular internal vibrator for concrete 2 One is damaged
compaction
14 Air compressor 1 Good
15 Power generator 48kW 1 Good
16 Mobile concrete batching B1200 1 Good but with a faulty
(concrete mixer) emergency stop switch
17 Auger 1 Good
18 3m3 big bag silo 1 Good
19 Concrete transporter 1 Good
20 Conveyors 3 Two in good condition one in
need of bearing replacement
Page 2|8
Dodoma Silos| Weekly Progress Report No 93, March 2020

21 Telehandler/Loadall 1 Good
22 Excavator 1 Good
23 Tipper Trucks 2 Good, in need of new tyres
24 Bucket for Telehandler 1 Worn out had to be reinforced
25 Fork attachments for telehandler 1 Good
26 Bucket for excavator with teeth 1 Good
27 Bucket for excavator w/o teeth 1 Good
28 Telehandler Attachment for lifting 1 Good
people
29 Reversible plate compactors 3 Good
30 Wheel Loader (sub-contractor) 1 Good
31 Concrete mixer (sub-contractor) 1 Good

3. MATERIALS ON SITE
Silo Assembly parts – various
Reinforcing steel: 3T-6mm, 3.8T-25mm, 18T-12mm,
Sand 40m3
Cement 1T
Gravel 20m3
Aggregate 5m3

4. LABOUR ON SITE
Item Title Quantity
1 Site Manager 1
2 Site Engineer 1
3 Civil Technician 1
4 Welder 0
5 Silo Assembly Supervisors 0
6 Silo assembly 0
Labourers/Technicians
7 Storekeeper 2
8 Safety Officer 1
9 Operators/Drivers 3
10 Steel Fixers 0
11 Mason 8
12 Carpenter 0
13 Surveyor 0
14 Labourers 5
15 Mechanic 1
13 Electrician 1

5. STATUTORY AUTHORITIES
NIL

Page 3|8
Dodoma Silos| Weekly Progress Report No 93, March 2020

6. PROGRESS AND PROGRAM


Week start: 16th March, 2020
Week end: 22nd March, 2020

Completed Ongoing Work hasn’t started

Item Description of works Completion date as per Actual Progress


Latest Program of Works
A Mobilisation 100% 100%
B Installation of construction camp 100% 100%
1 Mobile office for Project Manager 100% 100%
2 Site Manager office 100% 100%
3 Social container for workers 100% 100%
4 Sanitary containers 100% 100%
5 Storage containers 100% 100%
6 Accommodation container 100% 100%
7 Electrical supply and plumbing 100% 100%
C Demolition and preparatory works 100% 100%
D Silos Complex – Sub & Superstructure 12.06.18 – 12.03.2020 97%
1 Silo ring 1-6 12.06.2018 – 01.07.2019 Completed
2 Silo FSW 9.6 02.07.2019 – 12.08.2019 Completed
3 Receiving bucket 22.08.19 – 05.02.20 Completed
4 Dryer 27.09.19 – 12.12.19 Completed
5 Cleaner 03.09.19 – 23.09.19 Completed
6 Silo FSW 4.8 13.08.19 – 02.09.19 Completed
7 Silo FSS 3.8 13.12.19 – 19.12.19 Completed
8 Shipping shed 20.12.19 – 12.03.20 80%
9 Control container and diesel tanks 24.09.19 – 26.09.19 0%
10 Supporting towers 01.08.19 – 30.08.19 Completed
11 Technical pits DT1 and DT2 02.07.19 – 12.08.19 Completed
12 Powerhouse Completed
13 Water tanks 40%
E Silos Complex – Steel structure 05.03.19 – 29.05.20 70%
assembly and installation
1 Silo FSP 17.1 05.03.19 – 20.04.20 90%
2 Silo 9.6 24.09.19 – 07.10.19 90%
3 Dryer 20.09.19 – 16.04.20 80%
4 Cleaner 13.03.20 – 16.04.20 0%
5 Silo 3.8 13.03.20 – 19.03.20 40%
6 Silo 4.8 03.09.19 – 23.09.19 95%
7 Shipping shed 13.03.20 – 02.04.20 0%
8 Receiving bucket 06.02.20 – 08.04.20 40%
9 Control Container 03.04.20 – 03.04.20 0%
10 Equipment and fittings 06.04.20 – 15.05.20 0%

Page 4|8
Dodoma Silos| Weekly Progress Report No 93, March 2020

11 Electrical installations 06.04.19 – 29.05.20 0%


12 IT installations 06.04.19 – 29.05.20 0%
13 Plumbing & engineering installations 06.04.19 – 29.05.20 0%
14 Commissioning of works 01.06.20 – 30.06.20 0%
F Other Buildings 02.07.2019 – 14.10.2019 40%
1 Washroom Building 03.09.19 – 03.06.20 50%
Earthworks 03.09.19 – 30.09.19 100%
Foundation works 05.11.19 – 09.12.19 100%
Water, sewage and electrical 10.12.19 – 13.12.19 10%
installations
Blockwork 12.12.19 – 15.01.20 100%
Roof work 16.01.19 – 19.02.19 5%
Installation of doors and windows 20.02.20 – 11.03.20 0%
Finishing works 09.04.20 – 20.05.20 0%
Furnishing 21.05.20 – 03.06.20 0%
2 Canteen Building 03.09.19 – 03.06.20 50%
Earthworks 03.09.19 – 30.09.19 100%
Foundation works 05.11.19 – 09.12.19 100%
Water, sewage and electrical 10.12.19 – 13.12.19 10%
installations
Blockwork 12.12.19 – 15.01.20 100%
Roof work 16.01.19 – 19.02.19 5%
Installation of doors and windows 20.02.20 – 11.03.20 0%
Finishing works 09.04.20 – 20.05.20 0%
Furnishing 21.05.20 – 03.06.20 0%
3 Chemical Store Building 03.09.19 – 10.06.20 25%
Earthworks 03.09.19 – 30.09.19 100%
Foundation works 05.11.19 – 09.12.19 100%
Water, sewage and electrical 10.12.19 – 13.12.19 10%
installations
Blockwork 12.12.19 – 15.01.20 100%
Floor finish works 14.01.20 – 03.02.20 0%
Roof work 16.01.19 – 19.02.19 0%
Installation of doors and windows 20.02.20 – 18.03.19 0%
Finishing works 16.04.20 – 27.05.20 0%
Furnishing 28.05.20 – 10.06.20 0%
4 Equipment Store Building 03.09.19 – 24.04.20 60%
Earthworks 03.09.19 – 30.09.19 100%
Foundation works 05.11.19 – 09-12.19 100%
Blockwork 12.12.19 – 15.01.20 100%
Electrical installations 10.12.19 – 13.01.20 0%
Floor finish works 14.01.20 – 03.02.20 0%
Roof work 16.01.20 – 19.02.20 0%
Installation of doors and windows 20.02.20 – 11.03.20 0%
Finishing works 09.04.20 – 24.04.20 0%
5 Qualification Building 03.09.19 – 10.06.20 25%
Page 5|8
Dodoma Silos| Weekly Progress Report No 93, March 2020

Earthworks 03.09.19 – 30.09.19 100%


Foundation works 05.11.19 – 09.12.19 100%
Water, sewage and electrical 10.12.19 – 13.12.19 0%
installations
Blockwork 12.12.19 – 15.01.20 90%
Floor finish works 14.01.20 – 03.02.20 0%
Roof work 16.01.19 – 19.02.19 0%
Installation of doors and windows 20.02.20 – 18.03.19 0%
Finishing works 16.04.20 – 27.05.20 0%
Furnishing 28.05.20 – 10.06.20 0%
6 Office Building 01.08.2019 0%

Summary of works done this week:


 Completed plastering work for equipment store building
 Ongoing plastering chemical store building, washroom and canteen building
 Placement of conduit pipes for all buildings, for electrical works

7. CONTAINER DELIVERY
No Date Container Status Remarks
.
1 24.01.2018 T761 CTN/T124 Offloaded Excavator
DJK
2 23.01.2018 T904 BWR/T331 Offloaded Front loader (Telehandler/loadall)
BVP
3 06.03.2018 GESU 4488942 Offloaded Container at site containing site
building equipment
4 06.03.2018 TCNU 9218827 Offloaded Container at site, mobile batching
plant
5 06.03.2018 CAXU 9135443 Offloaded Container at site containing site
building equipment
6 18.03.2018 Offloaded 2 Tippers
7 22.03.2018 MIEU 0027371 Offloaded Assembly parts for silos
8 25.03.2018 CMAU 4282782 Offloaded Assembly parts for silos
9 26.03.2018 CMAU 5071249 Offloaded Assembly parts for silos
10 28.03.2018 MRKU 6308653 Offloaded Assembly parts for silos
11 29.03.2018 MRKU 3693330 Offloaded Assembly parts for silos
12 02.04.2018 GESU 5024817 Offloaded 3 compactors, partitions and steel.
Container at site
13 03.04.2018 TRLU 6639336 Offloaded Steel and partitions. Container at site
14 03.04.2018 CAXU 9164098 Offloaded Conveyor, steel and partitions.
Container at site
15 12.04.2018 MRKU 2027302 Offloaded Assembly parts for silos
16 12.04.2018 MSKU 0234540 Offloaded Assembly parts for silos
17 14.04.2018 TGHU 8602697 Offloaded Assembly parts for silos
18 15.04.2018 TGHU 6314578 Offloaded Assembly parts for silos
Page 6|8
Dodoma Silos| Weekly Progress Report No 93, March 2020

19 20.04.2018 ECMU 9864515 Offloaded Assembly parts for silos


20 22.04.2018 TGHU 8418186 Offloaded Site building equipment. Container at
site
21 24.04.2018 SEGU 4625335 Offloaded Assembly parts for silos
22 02.05.2018 TGHU 6392689 Offloaded Assembly parts for silos
23 14.05.2018 UETU 5550948 Offloaded Assembly parts for silos
24 15.05.2018 GESU 5241535 Offloaded Assembly parts for silos
25 15.05.2018 BMOU 5347057 Offloaded Assembly parts for silos
26 16.05.2018 TCNU 2386747 Offloaded Assembly parts for silos
27 17.05.2018 CMAU 4420325 Offloaded Assembly parts for silos. There was an
attempted robbery on container
whilst on transit. Nothing was stolen.
28 17.05.2018 MSKU 1331375 Offloaded Assembly parts for silos
29 02.07.2018 APHU 7363154 Offloaded Silo assembly parts and site materials
30 13.07.2018 TCNU 2992549 Offloaded Shuttering plywood
31 16.07.2018 BEAU 4669964 Offloaded Site and building Materials
32 10.08.2018 FCIU 8236040 Offloaded 12mm steel
33 10.08.2018 GESU 4655757 Offloaded Reinforcing steel 12mm
34 12.08.2018 FSCU9282938 Offloaded Reinforcing steel 25mm, 16mm,
12mm
35 13.08.2018 UACU 5357831 Offloaded Corrugated tubes, 6mm steel and silo
assembly parts
36 16.08.2018 SEGU 4986744 Offloaded Silo assembly parts
37 24.08.2018 HLXU 6481250 Offloaded Steel 12mm
38 24.10.2018 CPSU 6445151 Offloaded Silo assembly parts
39 26.10.2018 HAMU 1142935 Offloaded Silo assembly parts
40 14.11.2018 T 543 CVD Offloaded CCTV equipment for 5 sites
41 18.11.2015 CMAU 5914359 Offloaded Silo assembly parts
42 07.01.2019 CAIU 8214778 Offloaded Silo assembly parts
43 24.01.2019 UACU 5829959 Offloaded Silo assembly parts
44 10.02.2019 SEGU 6217538 Offloaded Silo assembly parts
45 19.02.2019 CMAU 4961546 Offloaded Silo assembly parts
46 20.03.2019 CMAU 7839228 Offloaded Silo assembly parts
47 15.04.2019 TCNU 9182299 Offloaded Silo assembly parts
48 19.04.2019 CMAU 4711249 Offloaded Silo assembly parts
49 28.04.2019 TCNU 5572405 Offloaded Silo assembly parts
50 09.06.2019 CMAU 5525629 Offloaded Silo assembly parts
51 07.07.2019 GESU 5311000 Offloaded Silo assembly parts
52 28.10.2019 BMOU 5294527 Offloaded Silo assembly parts
53 20.01.2020 APZU 4517813 Offloaded Reinforcement

7. INSTRUCTION ISSUED
NIL

8. INFORMATION REQUIRED FROM CONSULTANTS/CLIENT


Page 7|8
Dodoma Silos| Weekly Progress Report No 93, March 2020

NIL
9. CHALLENGES/CONSTRAINTS ENCOUNTERED
There have been site accessibility issues due to damaged road a direct result of the ongoing rains.
We have been experiencing heavy rains which hinder ongoing works.

10. SAFETY POLICY


Workers will be provided with safety gear. First Aid kits are available at site. There is safe water
available at site and clean and hygienic toileting facilities. There is a health officer onsite.

11. AIDS/HIV CARE


Health seminars will be scheduled for raising awareness on HIV/AIDS. The seminars will include
preventative measures and ways to seek treatment. Additionally, there is a health officer at site all
the time.

12. MAJOR INCIDENTS ON SITE


NIL

13. WEATHER REPORT


Dat Mean High Time Low Time Rain Avg wind High Time Direction
e Temp (oC) (oC) (mm) speed
(oC) (m/s)
10 - - - - - - - - - -
11 - - - - - - - - - -
12 - - - - - - - - - -
13 - - - - - - - - - -
14 - - - - - - - - - -
15 - - - - - - - - - -
16 - - - - - - - - - -

The weather station appears to be damaged and registering false information. We have had heavy
rains for the past couple of days, but this is not reflected in the readings.

14. PROGRESS PHOTOGRAPHS


Prepare by:
Mugore Chambiri – Dodoma Site Manager
23.03.2020

Page 8|8