Weekly Progress Report
Weekly Progress Report
Page 1|8
Dodoma Silos| Weekly Progress Report No 93, March 2020
1. CONTRACT INFORMATION
Date of Site Possession: 20th March 2018
NFRA Site Handover: 28th May 2018
Mobilization Period: 14 Days
Start Date: 12th June 2018
Completion Date: 11th December 2019
Contract period: 18months
Proposed extension: 6 months
Granted extension: 6 months – 30th June 2020
Time elapsed: 92 weeks
Delays 4 weeks
Insurance:
General progress: 99% (Silo Complex Foundations)
70% (Steel structure assembly and installation)
50% (Other Buildings)
21 Telehandler/Loadall 1 Good
22 Excavator 1 Good
23 Tipper Trucks 2 Good, in need of new tyres
24 Bucket for Telehandler 1 Worn out had to be reinforced
25 Fork attachments for telehandler 1 Good
26 Bucket for excavator with teeth 1 Good
27 Bucket for excavator w/o teeth 1 Good
28 Telehandler Attachment for lifting 1 Good
people
29 Reversible plate compactors 3 Good
30 Wheel Loader (sub-contractor) 1 Good
31 Concrete mixer (sub-contractor) 1 Good
3. MATERIALS ON SITE
Silo Assembly parts – various
Reinforcing steel: 3T-6mm, 3.8T-25mm, 18T-12mm,
Sand 40m3
Cement 1T
Gravel 20m3
Aggregate 5m3
4. LABOUR ON SITE
Item Title Quantity
1 Site Manager 1
2 Site Engineer 1
3 Civil Technician 1
4 Welder 0
5 Silo Assembly Supervisors 0
6 Silo assembly 0
Labourers/Technicians
7 Storekeeper 2
8 Safety Officer 1
9 Operators/Drivers 3
10 Steel Fixers 0
11 Mason 8
12 Carpenter 0
13 Surveyor 0
14 Labourers 5
15 Mechanic 1
13 Electrician 1
5. STATUTORY AUTHORITIES
NIL
Page 3|8
Dodoma Silos| Weekly Progress Report No 93, March 2020
Page 4|8
Dodoma Silos| Weekly Progress Report No 93, March 2020
7. CONTAINER DELIVERY
No Date Container Status Remarks
.
1 24.01.2018 T761 CTN/T124 Offloaded Excavator
DJK
2 23.01.2018 T904 BWR/T331 Offloaded Front loader (Telehandler/loadall)
BVP
3 06.03.2018 GESU 4488942 Offloaded Container at site containing site
building equipment
4 06.03.2018 TCNU 9218827 Offloaded Container at site, mobile batching
plant
5 06.03.2018 CAXU 9135443 Offloaded Container at site containing site
building equipment
6 18.03.2018 Offloaded 2 Tippers
7 22.03.2018 MIEU 0027371 Offloaded Assembly parts for silos
8 25.03.2018 CMAU 4282782 Offloaded Assembly parts for silos
9 26.03.2018 CMAU 5071249 Offloaded Assembly parts for silos
10 28.03.2018 MRKU 6308653 Offloaded Assembly parts for silos
11 29.03.2018 MRKU 3693330 Offloaded Assembly parts for silos
12 02.04.2018 GESU 5024817 Offloaded 3 compactors, partitions and steel.
Container at site
13 03.04.2018 TRLU 6639336 Offloaded Steel and partitions. Container at site
14 03.04.2018 CAXU 9164098 Offloaded Conveyor, steel and partitions.
Container at site
15 12.04.2018 MRKU 2027302 Offloaded Assembly parts for silos
16 12.04.2018 MSKU 0234540 Offloaded Assembly parts for silos
17 14.04.2018 TGHU 8602697 Offloaded Assembly parts for silos
18 15.04.2018 TGHU 6314578 Offloaded Assembly parts for silos
Page 6|8
Dodoma Silos| Weekly Progress Report No 93, March 2020
7. INSTRUCTION ISSUED
NIL
NIL
9. CHALLENGES/CONSTRAINTS ENCOUNTERED
There have been site accessibility issues due to damaged road a direct result of the ongoing rains.
We have been experiencing heavy rains which hinder ongoing works.
The weather station appears to be damaged and registering false information. We have had heavy
rains for the past couple of days, but this is not reflected in the readings.
Page 8|8