Professional Documents
Culture Documents
Tutorial 2-5 Submitted BY:SULAV GIRI (40765)
Tutorial 2-5 Submitted BY:SULAV GIRI (40765)
BY :SULAV GIRI(40765)
Sulav Giri
SU40765
Su40765 TUTORIAL 2-5
Week 2
Draw a Project Team Organization Structure of a project team implementing a complete
infrastructure and retail customer service software implementation program for a
multinational FMCG (Fast Moving Consumer Goods) Organization. Ensure that all internal
stakeholders within the team are highlighted as well as external stakeholders including
steering committee, change approval board etc.
PROJECT SPONSOR
PROJECT MANGER
PROJECT SPECIALIST
SYSTEM ANALYST
Week 3
Scope Management You are asked to implement network and infrastructure for a FMCG (Fast
Moving Consumer Goods) organization like Woolworths as well as replace the legacy (old
software) with new software programs. To this purpose, you are asked to train all the
100,000 employees via train-the-trainer program. Some retail centres have old and new
technology devices. Identify 5 scope items, 5 out-of-scope items, 5 constraints and 5
assumptions for this program
Assumptions:
The project always doesn’t go as planned. We make lots of assumptions such as deadlines and
outcomes but in some cases different factors might affect the project and hence proving out
assumptions false. In those examples some can be opening day or stock managements for the
shop etc.
Week 4
Su40765 TUTORIAL 2-5
Time Management FMCG program’s training team has come up with the following arrow-on-
activity diagram. Identify the critical path for their team’s activities and the slack time for
activities not on critical path. A = 1 week; B = 2 weeks; C = 3 weeks; D = 4 weeks; E = 10
weeks; F = 18 weeks; G = 3 weeks; H = 2 weeks; I = 30 weeks; J = 5 weeks; K = 2 weeks; L = 3
weeks; M = 2 weeks; N = 8 weeks; O=3 weeks
A+E+L+Q+R=1+10+3+4+2=20
A+F+M+O+R=1+18+2+3+2=26
B+I+M+O+R=2+4+2+3+2=13
C+G+I+M+O+R=3+3+4+2+3+2=17
C+H+J+M+O+R=3+2+5+2+3+2=17
C+H+K+N+O+R=3+2+2+8+5+2=19
Su40765 TUTORIAL 2-5
C+H+K+P+R=3+2+2+5+2=14
D+S+T=30+4+7=41
The critical path is the longest path through the network diagram.
In the diagram path 8, D-S-T-R = 41days, so it is the critical path.
Slack time: In this diagram, L can’t be started without B and C-G completed. B need to finish 2
days and C-G need to be finish 6 days. B must be delay 4 days to start L.
M can’t be started without A-F, B-I, C-G-I, and C-H-J need to be completed. A-F need to finish19
days, B-I=6, C-G-I= 10, C-H-J= 10 days. B-I has slack of days 13, C-G-I and C-H-J has slack of 9
days.