Activity Graph
Activity Graph
Activity Graph
START A G H
E
B
D F
J END
END
C
D ES EF LS LF S
START 0 0 0 0 0 0
A 7 0 7 0 7 0
B 2 0 2 5 7 5
C 15 0 15 12 27 12
D 8 17 25 17 25 0
E 10 7 17 7 17 0
F 2 25 27 25 27 0
G 5 17 23 19 24 2
H 8 23 31 24 32 1
I 2 27 29 27 29 0
J 3 29 32 29 32 0
END 0 32 32 32 32 0
TABLE #1
D ES EF LS LF S
START 0 0 0 0 0 0
A 7 0 7 0 7 0
B 2 0 2 5 7 5
C 15 0 15 12 27 12
D 8 17 25 17 25 0
E 10 7 17 7 17 0
F 2 25 27 25 27 0
G 5 17 23 19 24 2
H 8 23 31 24 32 1
I 2 27 29 27 29 0
J 3 29 32 29 32 0
END 0 32 32 32 32 0
CRITICAL PATH
CRITICAL PATH
START A G H
E
B
D F
J END
END
CRITICAL PATH: A -> E -> D -> F -> I -> J EARLIEST TIME TO FINISH: 32 MINUTES
GRAPH #2
A B E
START G
C F
I END
D ES EF LS LF S
START 0 0 0 0 0 0
A 15 0 15 0 15 0
B 40 15 55 15 55 0
C 30 55 85 55 85 0
D 25 0 25 30 55 30
E 5 85 90 85 90 0
F 10 90 100 90 100 0
H 10 85 95 105 115 20
TABLE #2
CRITICAL PATH
D ES EF LS LF S
START 0 0 0 0 0 0
A 15 0 15 0 15 0
B 40 15 55 15 55 0
C 30 55 85 55 85 0
D 25 0 25 30 55 30
E 5 85 90 85 90 0
F 10 90 100 90 100 0
H 10 85 95 105 115 20
CRITICAL PATH
A B E G
D
C F
START
END
CRITICAL PATH: A-> B -> C -> E -> F -> G -> I EARLIEST TIME TO FINISH: 130 MINUTES