DETAILED BILL OF QUANTITIES AND ESTIMATE FOR HPCL, BHUBANESWAR REGIONAL OFFICE,

2x45KL TANK INSTALLATION WORKS AT M/s. BHUSHAN STEEL LIMITED, DHENKANAL, ORISSA.

LENGTH BREADTH DEPTH


S.No. ITEM DESCRIPTION No. QTY. UNIT
IN 'M' IN 'M' IN 'M'

I SITE DEVELOPMENT WORKS :

1 Earthwork for Fencing Poles 75 0.60 0.60 0.750 20.25 Cu.M.

2 P.C.C. 1:2:4 for Grouting & Poles 75 0.45 0.45 0.900 13.67 Cu.M.

3 Structural steel for fencing Poles ISA 65x65x6 75 2.00 5.800 870.00

Structural steel for gate 3 4.50 2.00 25.000 675.00


1545.00 Kg

4 Barbed wire fencing 13 155.00 2015.00


Diagonals at every pole (75x2 = 150) 150 4.00 600.00
2615.00 Rmt

5 P.C.C. 1:3:6 for Gates foundation 6 1.35 1.35 0.100 1.09


1 8.00 0.60 0.100 0.48
1.57 Cu.M.

6 R.C.C. 1:1.5:3 for gates foundation 6 1.20 1.20 0.250 2.16


for cooler 6 0.30 0.30 2.700 1.46
3.62 Cu.M.

7 Reinforcement steel 1.00 M.T.


230Thk. Soling for Tanker Unloading platform
8 1 10.25 4.50 0.230 10.61
and approach

at HSD diesel pump 1 6.00 3.00 0.230 4.14


Approach in S - W 1 6.00 15.00 0.230 20.70
Loading bay for concrete apron 1 22.00 12.50 0.230 63.25
Before office building 1 7.00 5.00 0.230 8.05
106.75 Cu.M.

9 WBM 2 Layers 1 10.25 4.50 46.13


1 6.00 3.00 18.00
1 22.00 12.50 275.00
1 7.00 5.00 35.00
Approach out on S - W 1 15.00 6.00 90.00
464.13 Sq.M.

10 R.C.C. 1:2:4 Tank truck unloading platform 1 9.00 4.00 0.150 5.40 Cu.M.

11 230thk. Brick Masonry 1 80.00 0.23 0.750 13.80 Cu.M.

12 15Thk. Plastering 1 80.00 0.23 18.40


Gate top 6 0.38 0.38 0.84
Gate pillers 2 80.00 0.45 72.00
24 2.50 60.00
151.24 Sq.M.

13 White cement paint 151.24 Sq.M.

INSTALLATION OF 2x45KL ABOVE GROUND TANK CIVIL WORKS


Earthwork for tank supports pedestals
1
foundation

Due to loco moment impact load of loco


movement on surrounding soil to be
6 4.50 1.50 1.800 72.90
considering. depth more is considered to
minimise impact load pressure & settlements

Earthwork for dyke walls 2 21.00 1.20 1.500 75.60


2 7.70 1.20 1.500 27.72
for Pump foundations 2 2.50 1.35 0.900 6.08
182.30 Cu.M.

2 230thk. Soling for T / floor 6 4.50 1.50 0.230 9.32


Inside tanks / far 1 21.00 7.70 0.150 24.26
for Pump foundations 2 2.50 1.35 0.230 1.55
35.12 Cu.M.

3 Sand filling 6 4.50 1.50 0.150 6.08


2 7.70 1.20 0.150 2.77
2 21.00 1.20 0.150 7.56
inside dyke 1 21.00 7.70 0.100 16.17
for pump foundations 2 2.50 1.35 0.150 1.01
33.59 Cu.M.

4 P.C.C. 1:3:6
for T / Foundations 6 4.50 1.50 0.150 6.08
2 21.00 1.20 0.100 5.04
2 7.70 1.20 0.100 1.85
for pump foundations 2 2.50 1.35 0.150 1.01
inside dyke 1 21.00 7.50 0.125 19.69
33.66 Cu.M.

5 R.C.C. 1:1.5:3 T/Supporting foundations 6 4.00 1.35 0.600 19.44


Pedestals 6 4.00 0.30 2.000 14.40
Saddle portion 6 4.00 0.30 0.750 5.40
dyke wall foundation 2 21.00 0.90 0.450 17.01
2 7.50 0.90 0.450 6.08
walls 2 21.00 0.30 3.000 37.80
2 7.50 0.30 3.000 13.50
Pump foundations 2 2.00 1.50 0.750 4.50
118.13 Cu.M.

6 Reinforcement steel M.T.

7 P.C.C. 1:2:4 flooring inside dyke 1 21.00 7.50 0.125 19.69 Cu.M.

8 Plastering to R.C.C. walls 12 4.00 1.750 84.00


sides 12 0.30 1.75 6.30
Top 12 0.30 0.50 1.80
Dyke wall 4 21.00 2.500 210.00
4 7.50 2.500 75.00
2 21.00 0.30 12.60
2 7.50 0.60 9.00
398.70 Sq.M.
9 White cement paint 398.70 Sq.M.

Installation of 45Kl tank on Above ground


10 2.00 Nos
pedestal

11 Hydrotesting of tanks 2.00 Nos

Supply and applying of 2 coats of primer (red


12 2.00 Nos
oxide)

13 Supply and applying of 2 coats of enamel paint 2.00 Nos

OFFICE BUILDING
1 Earthwork in for R.C.C. Columns 6 1.50 1.50 1.800 24.30 Cu.M.

2 Soling 6 1.50 1.50 0.230 3.11


1 3.50 5.00 0.230 4.03
7.13 Cu.M.

3 Sand filling 6 1.50 1.50 0.100 1.35


1 5.00 3.50 0.100 1.75
3.10 Cu.M.

4 P.C.C. 1:3:6 6 1.50 1.50 0.100 1.35


1 5.00 3.50 0.125 2.19
3.54 Cu.M.
5 R.C.C. 1:1.5:3
for foundations 6 1.35 1.35 0.450 4.92
for columns 6 0.23 0.30 5.000 2.07
for Plinth beams 2 6.00 0.23 0.300 0.83
2 4.00 0.23 0.300 0.55
for Lintel beams 2 6.00 0.23 0.230 0.63
2 4.00 0.23 0.230 0.42
for Roof beams 2 6.00 0.23 0.300 0.83
3 4.00 0.23 0.300 0.83
for Roof slab 1 7.00 5.50 0.125 4.81
15.90 Cu.M.

6 Reinforcement steel M.T.

7 Brick masonry walls 2 5.50 0.23 3.500 8.86


2 3.96 0.23 3.500 6.38
Deductions
doors -1 1.00 0.23 2.100 -0.48
Windows -4 1.35 0.23 1.350 -1.68
Parapet wall 2 7.00 0.23 0.450 1.45
2 5.50 0.23 0.450 1.14
15.66 Cu.M.

8 Inside plastering 2 3.50 3.000 21.00


2 5.00 3.000 30.00
51.00 Sq.M.

9 Ceiling Plastering 1 7.00 5.50 38.50 Sq.M.

10 External plastering 2 5.50 3.500 38.50


2 3.96 3.500 27.72
Parapet walls 4 7.00 0.450 12.60
2 7.00 0.23 3.22
4 5.50 0.450 9.90
2 5.50 0.23 2.53
Sunshades top & bot 8 1.50 0.75 9.00
Door 2 1.20 0.900 2.16
Windows sill portion 4 1.50 0.10 0.60
8 0.55 0.10 0.44
1 1.20 0.10 0.12
2 0.90 0.10 0.18
Deductions 4 1.35 1.350 7.29
1 1.20 2.100 2.52
116.78 Sq.M.

11 White cement paint 206.28 Sq.M.

12 Colour snow cem outside 116.78 Sq.M.

13 OBD inside 51.00 Sq.M.


14 P.C.C. 1:2:4 for Flooring 1 5.00 3.50 0.100 1.75 Cu.M.

15 Hard top flooring 1 5.00 3.50 17.50


Steps 3 1.35 0.30 1.22
3 1.35 0.150 0.61
19.32 Sq.M.

16 Aluminium sliding window 4 1.35 1.350 7.29 Sq.M.

17 Partly glazed and partly panelled door 1 1.20 2.100 2.52 Sq.M.

18 4" dia rainwater pvc pipes 2 3.50 7.00 Rmt

ELECTRICAL WORKS

19 Light & Fan points 6.00 Nos


20 5A switches 3.00 Nos
21 15 Amps A.C. points 2.00 Nos
22 32 Amps MDB 1.00 Nos
23 4X2.5 Sq.m. cable 60.00 Rmt
24 48" Fan 2.00 Nos
25 2X18 Watt CFL 4.00 Nos
26 Tube lights (single tube) 2.00 Nos
27 Earth pits 10.00 Nos
28 10 SWG copper wire for earthing 200.00 Rmt
29 25X3 copper flat earth for tanks 40.00 Rmt
INSTALLATION OF PUMPS

1 Construction of pump island 3 2.50 7.50 Rmt


2 450 wide Pipe line trench 35.00 Rmt
3 50 n/b suction lines 3 35.00 105.00
3 7.50 22.50
127.50 Rmt
4 80 n/b suction header 15.00
from u/l pump to tank inlet 1 21.00 21.00
1 7.50 7.50
vents 2 4.50 9.00
tank top header 2 3.00 6.00
u/l point top 1 10.00 10.00
vent pipes 2 3.00 6.00
74.50 Rmt
5 Instalaltion of single pumps 3.00 Nos
6 Instalaltion of Dual pumps 1.00 Nos
7 3X2.5 Sq.m. cables 120.00 Rmt
8 150 dia NP2 class Humepipe for cables 40.00 Rmt
9 300 dia NP2 class hume pipes 20.00 Rmt
10 450x450 inspection chamber 3.00 Nos
11 Sgtructural steel for chamber cover plates 500.00 Kg
12 4X2.5 Sq.m copper armoured cable 150.00 Rmt

Supplying and fixing of 16Amp TPN MCB for


13 2.00 Nos
unloading pumps
Supplying and fixing of LFP push botton for
14 2.00 Nos
unloading pumps

15 TYPE - III Panel board 1.00 Nos


16 Supplying and fixing of 50n/b gate valves 3.00 Nos
17 Supplying and fixing of 50n/b NRV 3.00 Nos
18 Supplying and fixing of 80n/b gate valves 7.00 Nos
19 Supplying and fixing of 80n/b NRV 2.00 Nos

Installation of pumps, electrical connection,


20 piping connection, valves, fixing, alignment of 2.00 Nos
motor pumps, earthing connection all complete
ABSTRACT BILL OF QUANTITIES AND ESTIMATE FOR HPCL, BHUBANESWAR REGIONAL
OFFICE, 2x45KL TANK INSTALLATION WORKS AT M/s. BHUSHAN STEEL LIMITED,
DHENKANAL, ORISSA.

RATE AMOUNT
S.No. ITEM DESCRIPTION QTY. UNIT
Rs. - Ps. Rs. - Ps.

I SITE DEVELOPMENT WORKS :


1 Earthwork for Fencing Poles 25.00 Cu.M. 180.00 4500.00
2 P.C.C. 1:2:4 for Grouting & Poles 15.00 Cu.M. 2800.00 42000.00
3 Structural steel for fencing Poles & Gates 1.60 M.T. 65000.00 104000.00
4 Barbed wire fencing 2700.00 Rmt 450.00 1215000.00
5 P.C.C. 1:3:6 1.60 Cu.M. 2000.00 3200.00
6 R.C.C. 1:1.5:3 4.00 Cu.M. 4200.00 16800.00
7 Reinforcement steel 1.00 M.T. 40000.00 40000.00
8 230Thk. Soling 110.00 Cu.M. 900.00 99000.00
9 WBM 2 Layers 470.00 Sq.M. 175.00 82250.00
10 R.C.C. 1:2:4 Tank truck unloading platform 5.50 Cu.M. 3000.00 16500.00
11 230thk. Brick Masonry 15.00 Cu.M. 3200.00 48000.00
12 15Thk. Plastering 155.00 Sq.M. 180.00 27900.00
13 White cement paint 155.00 Sq.M. 40.00 6200.00

PART - 1 TOTAL AMOUNT 1705350.00

II INSTALLATION OF 2x45KL ABOVE GROUND TANK CIVIL WORKS


1 Earthwork in excavation 185.00 Cu.M. 180.00 33300.00
2 230thk. Soling 36.00 Cu.M. 900.00 32400.00
3 Sand filling 35.00 Cu.M. 1150.00 40250.00
4 P.C.C. 1:3:6 34.00 Cu.M. 2000.00 68000.00
5 R.C.C. 1:1.5:3 120.00 Cu.M. 4200.00 504000.00
6 Reinforcement steel 14.00 M.T. 40000.00 560000.00
7 P.C.C. 1:2:4 flooring inside dyke 20.00 Cu.M. 2800.00 56000.00
8 Plastering to R.C.C. walls 400.00 Sq.M. 180.00 72000.00
9 White cement paint 400.00 Sq.M. 40.00 16000.00

Installation of 45Kl tank on Above ground


10 2.00 Nos 12000.00 24000.00
pedestal

11 Hydrotesting of tanks 2.00 Nos 9000.00 18000.00

Supply and applying of 2 coats of primer (red


12 2.00 Nos 3500.00 7000.00
oxide)

Supply and applying of 2 coats of enamel


13 2.00 Nos 6500.00 13000.00
paint

PART - II TOTAL AMOUNT 1443950.00

III OFFICE BUILDING


RATE AMOUNT
S.No. ITEM DESCRIPTION QTY. UNIT
Rs. - Ps. Rs. - Ps.

1 Earthwork in for R.C.C. Columns 25.00 Cu.M. 180.00 4500.00


2 Soling 7.50 Cu.M. 900.00 6750.00
3 Sand filling 3.50 Cu.M. 950.00 3325.00
4 P.C.C. 1:3:6 3.60 Cu.M. 2000.00 7200.00
5 R.C.C. 1:1.5:3 16.00 Cu.M. 4200.00 67200.00
6 Reinforcement steel 2.00 M.T. 40000.00 80000.00
7 Brick masonry 16.00 Cu.M. 3200.00 51200.00
8 Inside plastering 51.00 Sq.M. 100.00 5100.00
9 Ceiling Plastering 40.00 Sq.M. 110.00 4400.00
10 External plastering 120.00 Sq.M. 180.00 21600.00
11 White cement paint 210.00 Sq.M. 40.00 8400.00
12 Colour snow cem outside 120.00 Sq.M. 60.00 7200.00
13 OBD inside 51.00 Sq.M. 110.00 5610.00
14 P.C.C. 1:2:4 for Flooring 2.00 Cu.M. 2800.00 5600.00
15 Hard top flooring 20.00 Sq.M. 300.00 6000.00
16 Aluminium sliding window 7.50 Sq.M. 5500.00 41250.00
17 Partly glazed and partly panelled door 2.52 Sq.M. 3500.00 8820.00
18 4" dia rainwater pvc pipes 7.00 Rmt 350.00 2450.00

PART - III TOTAL AMOUNT 336605.00

IV ELECTRICAL WORKS
19 Light & Fan points 6.00 Nos 530.00 3180.00
20 5A switches 3.00 Nos 350.00 1050.00
21 15 Amps A.C. points 2.00 Nos 2700.00 5400.00
22 32 Amps MDB 1.00 Nos 6500.00 6500.00
23 4X2.5 Sq.m. cable 60.00 Rmt 200.00 12000.00
24 48" Fan 2.00 Nos 2000.00 4000.00
25 2X18 Watt CFL 4.00 Nos 0.00
26 Tube lights (single tube) 2.00 Nos 1050.00 2100.00
27 Earth pits 10.00 Nos 5500.00 55000.00
28 10 SWG copper wire for earthing 200.00 Rmt 90.00 18000.00
29 25X3 copper flat earth for tanks 40.00 Rmt 475.00 19000.00

PART - IV TOTAL AMOUNT 126230.00

V INSTALLATION OF PUMPS
1 Construction of pump island 7.50 Rmt 5800.00 43500.00
2 450 wide Pipe line trench 35.00 Rmt 2000.00 70000.00
3 50 n/b suction lines 130.00 Rmt 750.00 97500.00
4 80 n/b suction header 75.00 Rmt 950.00 71250.00
5 Instalaltion of single pumps 3.00 Nos 1750.00 5250.00
RATE AMOUNT
S.No. ITEM DESCRIPTION QTY. UNIT
Rs. - Ps. Rs. - Ps.

6 Instalaltion of Dual pumps 1.00 Nos 1800.00 1800.00


7 3X2.5 Sq.m. cables 120.00 Rmt 250.00 30000.00
8 150 dia NP2 class Humepipe for cables 40.00 Rmt 525.00 21000.00
9 300 dia NP2 class hume pipes 20.00 Rmt 1350.00 27000.00
10 450x450 inspection chamber 3.00 Nos 5800.00 17400.00
11 Structural steel for chamber cover plates 500.00 Kg 65.00 32500.00
12 4x2.5 Sq.m copper armoured cable 150.00 Rmt 110.00 16500.00

Supplying and fixing of 16Amp TPN MCB for


13 2.00 Nos 1200.00 2400.00
unloading pumps

Supplying and fixing of LFP push botton for


14 2.00 Nos 1200.00 2400.00
unloading pumps

15 TYPE - III Panel board 1.00 Nos 55000.00 55000.00


16 Supplying and fixing of 50n/b gate valves 3.00 Nos 4000.00 12000.00
17 Supplying and fixing of 50n/b NRV 3.00 Nos 3500.00 10500.00
18 Supplying and fixing of 80n/b gate valves 7.00 Nos 9000.00 63000.00
19 Supplying and fixing of 80n/b NRV 2.00 Nos 7000.00 14000.00

Installation of pumps, electrical connection,


piping connection, valves, fixing, alignment of
20 2.00 Nos 10000.00 20000.00
motor pumps, earthing connection all
complete

PART - V TOTAL AMOUNT 613000.00

GRAND TOTAL AMOUNT 4225135.00


ABSTRACT BILL OF QUANTITIES FOR HPCL, BHUBANESWAR REGIONAL OFFICE, 2x45KL
TANK INSTALLATION WORKS AT M/s. BHUSHAN STEEL LIMITED, DHENKANAL, ORISSA.

RATE AMOUNT
S.No. ITEM DESCRIPTION QTY. UNIT
Rs. - Ps. Rs. - Ps.

I SITE DEVELOPMENT WORKS :


1 Earthwork for Fencing Poles 25.00 Cu.M.
2 P.C.C. 1:2:4 for Grouting & Poles 15.00 Cu.M.
3 Structural steel for fencing Poles & Gates 1.60 M.T.
4 Barbed wire fencing 2700.00 Rmt
5 P.C.C. 1:3:6 1.60 Cu.M.
6 R.C.C. 1:1.5:3 4.00 Cu.M.
7 Reinforcement steel 1.00 M.T.
8 230Thk. Soling 110.00 Cu.M.
9 WBM 2 Layers 470.00 Sq.M.
10 R.C.C. 1:2:4 Tank truck unloading platform 5.50 Cu.M.
11 230thk. Brick Masonry 15.00 Cu.M.
12 15Thk. Plastering 155.00 Sq.M.
13 White cement paint 155.00 Sq.M.

PART - 1 TOTAL AMOUNT

II INSTALLATION OF 2x45KL ABOVE GROUND TANK CIVIL WORKS


1 Earthwork in excavation 185.00 Cu.M.
2 230thk. Soling 36.00 Cu.M.
3 Sand filling 35.00 Cu.M.
4 P.C.C. 1:3:6 34.00 Cu.M.
5 R.C.C. 1:1.5:3 120.00 Cu.M.
6 Reinforcement steel 14.00 M.T.
7 P.C.C. 1:2:4 flooring inside dyke 20.00 Cu.M.
8 Plastering to R.C.C. walls 400.00 Sq.M.
9 White cement paint 400.00 Sq.M.

Installation of 45Kl tank on Above ground


10 2.00 Nos
pedestal

11 Hydrotesting of tanks 2.00 Nos

Supply and applying of 2 coats of primer (red


12 2.00 Nos
oxide)

13 Supply and applying of 2 coats of enamel paint 2.00 Nos

PART - II TOTAL AMOUNT

III OFFICE BUILDING


1 Earthwork in for R.C.C. Columns 25.00 Cu.M.
2 Soling 7.50 Cu.M.
3 Sand filling 3.50 Cu.M.
4 P.C.C. 1:3:6 3.60 Cu.M.
5 R.C.C. 1:1.5:3 16.00 Cu.M.
6 Reinforcement steel 2.00 M.T.
7 Brick masonry 16.00 Cu.M.
8 Inside plastering 51.00 Sq.M.
9 Ceiling Plastering 40.00 Sq.M.
10 External plastering 120.00 Sq.M.
11 White cement paint 210.00 Sq.M.
12 Colour snow cem outside 120.00 Sq.M.
13 OBD inside 51.00 Sq.M.
14 P.C.C. 1:2:4 for Flooring 2.00 Cu.M.
15 Hard top flooring 20.00 Sq.M.
16 Aluminium sliding window 7.50 Sq.M.
17 Partly glazed and partly panelled door 2.52 Sq.M.
18 4" dia rainwater pvc pipes 7.00 Rmt

PART - III TOTAL AMOUNT

IV ELECTRICAL WORKS
19 Light & Fan points 6.00 Nos
20 5A switches 3.00 Nos
21 15 Amps A.C. points 2.00 Nos
22 32 Amps MDB 1.00 Nos
23 4X2.5 Sq.m. cable 60.00 Rmt
24 48" Fan 2.00 Nos
25 2X18 Watt CFL 4.00 Nos
26 Tube lights (single tube) 2.00 Nos
27 Earth pits 10.00 Nos
28 10 SWG copper wire for earthing 200.00 Rmt
29 25X3 copper flat earth for tanks 40.00 Rmt

PART - IV TOTAL AMOUNT

V INSTALLATION OF PUMPS
1 Construction of pump island 7.50 Rmt
2 450 wide Pipe line trench 35.00 Rmt
3 50 n/b suction lines 130.00 Rmt
4 80 n/b suction header 75.00 Rmt
5 Instalaltion of single pumps 3.00 Nos
6 Instalaltion of Dual pumps 1.00 Nos
7 3X2.5 Sq.m. cables 120.00 Rmt
8 150 dia NP2 class Humepipe for cables 40.00 Rmt
9 300 dia NP2 class hume pipes 20.00 Rmt
10 450x450 inspection chamber 3.00 Nos
11 Structural steel for chamber cover plates 500.00 Kg
12 4x2.5 Sq.m copper armoured cable 150.00 Rmt

Supplying and fixing of 16Amp TPN MCB for


13 2.00 Nos
unloading pumps

Supplying and fixing of LFP push botton for


14 2.00 Nos
unloading pumps

15 TYPE - III Panel board 1.00 Nos


16 Supplying and fixing of 50n/b gate valves 3.00 Nos
17 Supplying and fixing of 50n/b NRV 3.00 Nos
18 Supplying and fixing of 80n/b gate valves 7.00 Nos
19 Supplying and fixing of 80n/b NRV 2.00 Nos

Installation of pumps, electrical connection,


20 piping connection, valves, fixing, alignment of 2.00 Nos
motor pumps, earthing connection all complete

PART - V TOTAL AMOUNT

GRAND TOTAL AMOUNT

NOTE:
* All quantities are approximate.
* Actual quantities shall be based on work done.
* Contractor shall visit the site before quoting.