FOR APPROVAL

0 22.03.2018 AG KS JKS FIRST ISSUE


Rev Date Prepared Checked Approved Details of Revision
Owner
JAWAHARPUR VIDYUT UTPADAN NIGAM LIMITED
(A UP Government Undertaking)

Owner’s Engineer
DESEIN PRIVATE LIMITED,
Consulting Engineers

Contractor

DOOSAN POWER SYSTEMS INDIA PVT. LTD

Supplier
C & S ELECTRIC LTD, HARIDWAR
Project

JAWAHARPUR SUPER THERMAL POWER STATION (2x660 MW)


Project Code
Date
Name Title
(DD.MM.YYYY)
DP16003
UAS Code
Prepared 22.03.2018 AG
QA00
Unit Code
Checked 22.03.2018 KS
MQP FOR 3.3 Kv & 11 Kv P0
Approved 22.03.2018 JKS SEGREGATED PHASE BUS DUCT KKS Code
ZEN
Digitally signed Reg. No.
Package /
3.3Kv. & 11 Kv SEGREGATED Signature Not Verified
by AMIT GUPTA
Equipment Date: 2018.04.03
Name PHASE BUS DUCT 15:12:16 IST 040068
Reason: CAT I Rev.
Location:
Owner’s Consultant Document No : 9876-101-QVE-Q-027 NTPCEOC 0
9876-101-QVE-Q-001

Contractor’s Document No.


DP16003-QA00-P0ZEN-040068
Supplier’s Document No. Page-No.
0000-999-QV-P-214 Rev01 Dt 28.08.2008 01 of 06
ENDORSEMENT SHEET FOR QP
REFERENCE / STANDARD / FIELD QUALITY PLAN (RQP / SQP/RFQP/SFQP)
TO BE FILLED IN BY SUPPLIER AT TIME OF SUBMISSION To be filled in by NTPC
PROJECT NAME 2X660 MW JAWAHRPUR THERMAL POWER PLANT REVIEW & ENDORSEMENT BY NTPC PROJECT
CONTRACT NO.: PPMM/SE-II/2017/JAWAHARPUR/02 SPECIFIC QP NUMBER ALLOTTED
MAIN SUPPLIER DOOSAN POWER SYSTEM INDIA PVT. LTD. QP NO.: 9876-101-QVE-Q-001
MANUFACTURER WORKS & ADDRESS M/s. C&S Electric Ltd., Plot No. 1C Sector 8C Industrial State Ranipur
Haridwar REV. NO.: 00 DATE: 22.03.2018
ITEM /EQUIPMENT / SYSTEM/ ** The RQP/SQP/RFQP/SFQP once endorsed for a particular
SUB-SYSTEM DETAILS i.e. MODEL TYPE / Segregated Phase Bus ducts (3.3 Kv & 11 Kv) contract shall remain valid even though the original QP may
have expired or revised, unless / otherwise mutually agreed with
SIZE /RATING etc.
the supplier. 
APPROVED QP NO.: RQP/SQP/RFQP/SFQP 0000-999-QV-P-214 REV. NO.: 0 1 DATED**: 28.08.2008
Confirmation by Main Supplier (TICK WHICHEVER APPLICABLE) (TICK APPLICABLE)
I. That the item/ component is identical to that considered for QP approval. OR. The QP is endorsed for this project without any
II. That there are minor changes in the item/ component with respect to that considered for QP approval, however the same do change
not affect the contents of QP. OR
III. That there are minor changes in the item/ component with respect to that considered for QP approval, however the same The QP is endorsed for this project with changes as
affect the QP slightly, as indicated below / in attached sheet. indicated.

DISTRIBUTION OF ENDORSEMENT OF
A) RQP/SQP:
1. MAIN SUPPLIER (WITH A COPY OF QP)
2. MANUFACTURER
3. RIO
4. CQA-SPL
5. CQA-O/C
B) RFQP/SFQP:
1. MAIN SUPPLIER (with a copy of QP)
2. MANUFACTURER
3. NTPC FQA (with a copy of QP)
4. NTPC Erection (with a copy of QP)
5. CQA-SPL
6. CQA-O/C

NTPC (Reviewed /Approved by/ Date & Seal)


SIGN.: (Main Supplier) DATE: 21.03.2018 SIGN.: (Manufacturer) DATE:21.03.2018

FORMAT NO.: QS-01-QAI-P-10/ F5-R1 1/1 ENGG. DIV./ QA&I