CM AND RODRIGO

ARCHITECTURAL DESIGN SERVICES

UNIT MATERIAL LABOR TOTAL


ITEM ITEM DESCRIPTION QTY UNIT COST COST COST COST
EARTH WORKS
A.
EXCAVATION 1.35 CU.M 550.00 P 742.5

BACKFILL 2.30 CU.M 550.00 P 1,265.00

SUB TOTAL P 2,007.5

B. CONCRETE / MASONRY
CEMENT 186 BAGS 205.00 38,130.00

SAND 4.42 CU.M 550.00 2,431.00

GRAVEL 4.48 CU.M 550.00 2,464.00

CHB 4" 250 PCS 13.50 3,375.00

SUB TOTAL 46,582.00 16,303.70 P 62,885.70

C. FORM WORKS
2"X3"X8 COCO LUMBER 20 PCS 92.00 1,840.00
2"X2"X10 COCO LUMBER 16 PCS 77.00 1,232.00

1/2 THK ORD. PLYWOOD 9 PCS 680.00 6,120.00

CWN. ASSTD. 5 BOXES 1,600.00 8,000.00


# 16 G.I TIE WIRE 2 ROLLS 2,800.00 5,600.00

SUB TOTAL 22,792.00 7,977.20 P 30,769.20

D. CEILING WORKS
1/4 THK HARDIEFLEX 8 PCS 480.00 3,840.00

FURRING CHANNEL 40 PCS 100.00 4,000.00

1/8 RIVET SCREW 4 BOX 250.00 1,000.00

W-CLIP 100 PCS 5.00 500.00

SUB TOTAL 9,340.00 3,269.00 P 12,609.00

Mrs. Dorotea Bellido CHRISTOPHER M. RODRIGO


OWNER PRINCIPAL DESIGNER/CEO
CM AND R ARCHITECTURAL
DESIGN SERVICES.

CONTACT DETAILS: 09776887677


rodrigochristopher@yahoo.com
designmanager15@yahoo.com DTI NO:2153038