Construction of Toilet Facilities at River State University, Port Harcourt, Rivers State
Construction of Toilet Facilities at River State University, Port Harcourt, Rivers State
1.1 Project Documentations /Approvals and Kickoff meeting: 7th April 2021.
BRC Fabric Mesh Re-enforcement 100% Completed in conformity to specifications & Standard.
Sawn form work on roof beam & 100% Completed in conformity to specifications & Standard.
parapets'
Casting 100% Completed in conformity to specifications & Standard.
FINISHES (Completion of roofing, windows and doors Installations)
Roof Carcass 0%
Installation of Aluminum Zinc 0%
Installation of Doors 0%
Installation of Windows 0%
INTERNAL & EXTERNAL WORKS (Completion of the walls, floors and Ceiling Finishing Including all
Electrical and Mechanical fittings and Fixtures including external works (where applicable).
Internal & External plasters 0%
Internal & External Tilling 0%
Installation of Ceiling 0%
Internal & External paintings and
0%
Decorations
Electrical Installation & Fittings 0%
EQUIPMENT AND FURNITURE INSTALLATION (Delivery to Site and Installation of all equipments
St Furniture).
Delivery of Generators &
0%
Accessories/Installation
Delivery of Medical
0%
Equipment/Installation
Delivery of Office
0%
Equipment/Installation
Commissioning of site 0%
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt
4.1 No delays
June 2021.
2021.
Blockwork on going.
Blockwork on going.
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt