Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

Construction of Toilet Facilities at River

State University, Port Harcourt,


Rivers State.
(A Corporate Social Responsibility Project)

BETAGOD INVESTMENT LIMITED

PROGRESS REPORT: WEEK 2

ACTION NAME POSITION SIGNATURE DATE


Prepared By OKPE, Cletus PROJECT MANAGER 06/05/2021

Approved By OLIGBI Joseph MANAGING 06/05/2021


DIRECTOR
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 1 of 9 PROGRESS REPORT Date: 06/05/2021

1.0 Project Milestones Completed:

1.1 Project Documentations /Approvals and Kickoff meeting: 7th April 2021.

1.2 Full Mobilization to Project Site completed.

1.3 Project Commencement and Groundbreaking Ceremony: 21/ 04 / 2021.

1.4 Sub-structure works completed.

1.5 Commenced and Completed Superstructure blockworks and concrete works.

2.0 Breakdown of Progress of Work in Phases:

Breakdown of the progress of each phase of the project


Activity
Activity Name/Phase/Milestone
% Remarks
Complete
DETAILED WORKING DRAWINGS AND CONCLUSION OF THE CALL FOR TENDER PROCESS

Detailed Drawings 100% Submitted/Approved. Also, Consultant Validation &


Evaluation Certification has been Submitted for this
Phase/Activities
Soil Test 100% Submitted and Approved
Topographical Survey 100% Submitted and Approved
CVs of Key Project Personnel 100% Submitted and Approved
Project Organization Chart 100% Submitted and Approved
Method Statement 100% Submitted and Approved
Project Quality Plan 100% Submitted and Approved
List of Contractors 100% Submitted and Approved
Project HSE Risk Assessment 100% Submitted and Approved
Materials & Equipment specifications Submitted and Approved
100%
FULL MOBILIZATION TO PROJECT SITE

Equipment Submitted/Approved. Also Consultant Evaluation


100%
Certification has been Submitted for this
Labor 100% Phase/Activities
Materials 100%
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 2 of 9 PROGRESS REPORT Date: 06/05/2021

Site Office, Store and Demarcation Submitted/Approved


100%
Borehole Drilling and Reticulation Completed in conformity to specifications & Standard.
100%
SUB-STRUCTURE WORKS
Excavation 100% .
Excavation of Trenches 100% Completed in conformity to specifications & Standard.
Column Bases 100% Completed in conformity to specifications & Standard.
Re-enforcement for footinqs 100% Completed in conformity to specifications & Standard.
Re-enforcement for columns
100% Completed in conformity to specifications & Standard.
(Starters)
Blinding of Column bases trenches 100% Completed in conformity to specifications & Standard.

Entrance steps 100% Completed in conformity to specifications & Standard.

Ramps 100% Completed in conformity to specifications & Standard.

Sub-structure piping 100% Completed in conformity to specifications & Standard.

Block works 100% Completed in conformity to specifications & Standard.


Back fillings 100% Completed in conformity to specifications & Standard.
Compaction 100% Completed in conformity to specifications & Standard.
Application of Ant-termite 100% Completed in conformity to specifications & Standard.

BRC Fabric Mesh Re-enforcement 100% Completed in conformity to specifications & Standard.

Sawn formwork to vertical side of


100% Completed in conformity to specifications & Standard.
Column
Sawn formwork to sides of steps &
100% Completed in conformity to specifications & Standard.
ramps
Sawn formwork to edges of bed,
100% Completed in conformity to specifications & Standard.
beam
Spreading of Damp Proof 100% Completed in conformity to specifications & Standard.
Casting of DPC 100% Completed in conformity to specifications & Standard.
SUPER-STRUCTURE WORKS (Blocks works, including associated Concrete, Conduiting, Wiring and
Piping Works)
Forming of Blocks 100% Completed in conformity to specifications & Standard.
Extension of pipes 100% Completed in conformity to specifications & Standard.
External & Internal Block Works 100% Completed in conformity to specifications & Standard.
Extension of re-enforcement 100% Completed in conformity to specifications & Standard.
100% Completed in conformity to specifications & Standard.
Sawn form work on column & lintels

Re-enforcement in lintels 100% Completed in conformity to specifications & Standard.


Castinq of columns, lintels 100% Completed in conformity to specifications & Standard.
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 3 of 9 PROGRESS REPORT Date: 06/05/2021

Sawn form work on roof beam & 100% Completed in conformity to specifications & Standard.
parapets'
Casting 100% Completed in conformity to specifications & Standard.
FINISHES (Completion of roofing, windows and doors Installations)
Roof Carcass 0%
Installation of Aluminum Zinc 0%
Installation of Doors 0%
Installation of Windows 0%
INTERNAL & EXTERNAL WORKS (Completion of the walls, floors and Ceiling Finishing Including all
Electrical and Mechanical fittings and Fixtures including external works (where applicable).
Internal & External plasters 0%
Internal & External Tilling 0%
Installation of Ceiling 0%
Internal & External paintings and
0%
Decorations
Electrical Installation & Fittings 0%

Mechanical Installation & Fittings 0%

Soak Away 60% Ongoing in conformity to specifications & Standard.


Car Park & Landscaping 0%

Construction of Drainage & Slab 0%

EQUIPMENT AND FURNITURE INSTALLATION (Delivery to Site and Installation of all equipments
St Furniture).
Delivery of Generators &
0%
Accessories/Installation
Delivery of Medical
0%
Equipment/Installation
Delivery of Office
0%
Equipment/Installation

WORK ACCEPTANCE (As Built Drawings/Demobilization)

Testing of all equipment 0°/o

Correction of all snags 0%

Commissioning of site 0%
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 4 of 9 PROGRESS REPORT Date: 06/05/2021

3.0 WEEK 3 LOOK AHEAD.

3.10 Commence and Complete:


1. FINISHES (Completion of roofing, windows and doors Installations)
2. Complete Soak away

4.0 MAJOR/MINOR DELAYS.

4.1 No delays

5.0 Project Finish date:

5.10 Planned work completion and Commence demobilization. Wednesday 16th of

June 2021.

5.20 Project commencement and Groundbreaking Ceremony, Wednesday 21st April

2021.

5.30 Total Planned duration 8 weeks.


WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 5 of 9 PROGRESS REPORT Date: 06/05/2021

6.0 Site Progress Photos:

Block ready at Site DPC completed

Blockwork on going.
Blockwork on going.
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 6 of 9 PROGRESS REPORT Date: 06/05/2021

Blockwork on going Blockwork on going.

Lintel Formwork on going Lintel completed


WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 7 of 9 PROGRESS REPORT Date: 06/05/2021

Completion blockwork on going Completion blockwork on going

Completion blockwork completed.


Completion blockwork completed.
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 8 of 9 PROGRESS REPORT Date: 06/05/2021

You might also like