Construction of Toilet Facilities at River State University, Port Harcourt, Rivers State

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

Construction of Toilet Facilities at River

State University, Port Harcourt,


Rivers State.
(A Corporate Social Responsibility Project)

BETAGOD INVESTMENT LIMITED

PROGRESS REPORT: WEEK 2

ACTION NAME POSITION SIGNATURE DATE


Prepared By OKPE, Cletus PROJECT MANAGER 06/05/2021

Approved By OLIGBI Joseph MANAGING 06/05/2021


DIRECTOR
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 1 of 9 PROGRESS REPORT Date: 06/05/2021

1.0 Project Milestones Completed:

1.1 Project Documentations /Approvals and Kickoff meeting: 7th April 2021.

1.2 Full Mobilization to Project Site completed.

1.3 Project Commencement and Groundbreaking Ceremony: 21/ 04 / 2021.

1.4 Sub-structure works completed.

1.5 Commenced and Completed Superstructure blockworks and concrete works.

2.0 Breakdown of Progress of Work in Phases:

Breakdown of the progress of each phase of the project


Activity
Activity Name/Phase/Milestone
% Remarks
Complete
DETAILED WORKING DRAWINGS AND CONCLUSION OF THE CALL FOR TENDER PROCESS

Detailed Drawings 100% Submitted/Approved. Also, Consultant Validation &


Evaluation Certification has been Submitted for this
Phase/Activities
Soil Test 100% Submitted and Approved
Topographical Survey 100% Submitted and Approved
CVs of Key Project Personnel 100% Submitted and Approved
Project Organization Chart 100% Submitted and Approved
Method Statement 100% Submitted and Approved
Project Quality Plan 100% Submitted and Approved
List of Contractors 100% Submitted and Approved
Project HSE Risk Assessment 100% Submitted and Approved
Materials & Equipment specifications Submitted and Approved
100%
FULL MOBILIZATION TO PROJECT SITE

Equipment Submitted/Approved. Also Consultant Evaluation


100%
Certification has been Submitted for this
Labor 100% Phase/Activities
Materials 100%
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 2 of 9 PROGRESS REPORT Date: 06/05/2021

Site Office, Store and Demarcation Submitted/Approved


100%
Borehole Drilling and Reticulation Completed in conformity to specifications & Standard.
100%
SUB-STRUCTURE WORKS
Excavation 100% .
Excavation of Trenches 100% Completed in conformity to specifications & Standard.
Column Bases 100% Completed in conformity to specifications & Standard.
Re-enforcement for footinqs 100% Completed in conformity to specifications & Standard.
Re-enforcement for columns
100% Completed in conformity to specifications & Standard.
(Starters)
Blinding of Column bases trenches 100% Completed in conformity to specifications & Standard.

Entrance steps 100% Completed in conformity to specifications & Standard.

Ramps 100% Completed in conformity to specifications & Standard.

Sub-structure piping 100% Completed in conformity to specifications & Standard.

Block works 100% Completed in conformity to specifications & Standard.


Back fillings 100% Completed in conformity to specifications & Standard.
Compaction 100% Completed in conformity to specifications & Standard.
Application of Ant-termite 100% Completed in conformity to specifications & Standard.

BRC Fabric Mesh Re-enforcement 100% Completed in conformity to specifications & Standard.

Sawn formwork to vertical side of


100% Completed in conformity to specifications & Standard.
Column
Sawn formwork to sides of steps &
100% Completed in conformity to specifications & Standard.
ramps
Sawn formwork to edges of bed,
100% Completed in conformity to specifications & Standard.
beam
Spreading of Damp Proof 100% Completed in conformity to specifications & Standard.
Casting of DPC 100% Completed in conformity to specifications & Standard.
SUPER-STRUCTURE WORKS (Blocks works, including associated Concrete, Conduiting, Wiring and
Piping Works)
Forming of Blocks 100% Completed in conformity to specifications & Standard.
Extension of pipes 100% Completed in conformity to specifications & Standard.
External & Internal Block Works 100% Completed in conformity to specifications & Standard.
Extension of re-enforcement 100% Completed in conformity to specifications & Standard.
100% Completed in conformity to specifications & Standard.
Sawn form work on column & lintels

Re-enforcement in lintels 100% Completed in conformity to specifications & Standard.


Castinq of columns, lintels 100% Completed in conformity to specifications & Standard.
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 3 of 9 PROGRESS REPORT Date: 06/05/2021

Sawn form work on roof beam & 100% Completed in conformity to specifications & Standard.
parapets'
Casting 100% Completed in conformity to specifications & Standard.
FINISHES (Completion of roofing, windows and doors Installations)
Roof Carcass 0%
Installation of Aluminum Zinc 0%
Installation of Doors 0%
Installation of Windows 0%
INTERNAL & EXTERNAL WORKS (Completion of the walls, floors and Ceiling Finishing Including all
Electrical and Mechanical fittings and Fixtures including external works (where applicable).
Internal & External plasters 0%
Internal & External Tilling 0%
Installation of Ceiling 0%
Internal & External paintings and
0%
Decorations
Electrical Installation & Fittings 0%

Mechanical Installation & Fittings 0%

Soak Away 60% Ongoing in conformity to specifications & Standard.


Car Park & Landscaping 0%

Construction of Drainage & Slab 0%

EQUIPMENT AND FURNITURE INSTALLATION (Delivery to Site and Installation of all equipments
St Furniture).
Delivery of Generators &
0%
Accessories/Installation
Delivery of Medical
0%
Equipment/Installation
Delivery of Office
0%
Equipment/Installation

WORK ACCEPTANCE (As Built Drawings/Demobilization)

Testing of all equipment 0°/o

Correction of all snags 0%

Commissioning of site 0%
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 4 of 9 PROGRESS REPORT Date: 06/05/2021

3.0 WEEK 3 LOOK AHEAD.

3.10 Commence and Complete:


1. FINISHES (Completion of roofing, windows and doors Installations)
2. Complete Soak away

4.0 MAJOR/MINOR DELAYS.

4.1 No delays

5.0 Project Finish date:

5.10 Planned work completion and Commence demobilization. Wednesday 16th of

June 2021.

5.20 Project commencement and Groundbreaking Ceremony, Wednesday 21st April

2021.

5.30 Total Planned duration 8 weeks.


WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 5 of 9 PROGRESS REPORT Date: 06/05/2021

6.0 Site Progress Photos:

Block ready at Site DPC completed

Blockwork on going.
Blockwork on going.
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 6 of 9 PROGRESS REPORT Date: 06/05/2021

Blockwork on going Blockwork on going.

Lintel Formwork on going Lintel completed


WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 7 of 9 PROGRESS REPORT Date: 06/05/2021

Completion blockwork on going Completion blockwork on going

Completion blockwork completed.


Completion blockwork completed.
WEEK 2 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/002/21048
LIMITED
Construction of Toilet Facilities
at River State University, Port
Harcourt

Page 8 of 9 PROGRESS REPORT Date: 06/05/2021