The Essentials of Automation Applied To Distribution Systems Via PLCs SCADA IEDs and RTUs
The Essentials of Automation Applied To Distribution Systems Via PLCs SCADA IEDs and RTUs
The essentials of automation applied to distribution systems via PLCs, SCADA, IEDs, and RTUs (photo
credit: svitovyr.com)
1/17
The distribution systems feeding the industrial and commercial loads must be automated in
most cases. Distribution system automation helps to raise the reliability level by decreasing
the interruption duration, isolating the faulty parts, keeping the system equipment functioning,
and automating the required switching processes during system operation.
This technical article explains the basics of automation applied to electrical distribution
systems using PLCs, SCADA, IEDs, and RTUs.
Table of Contents:
It depends on the size of the network, the nature and amount of load, and the type of system
equipment. When the distribution system grows and becomes more complicated, is the
automation sufficient to achieve optimal performance and to operate satisfactorily and
securely? This is the question to be answered by the following discussion.
In a commercial office building (e.g., 40 floors), the utility feeder comes into the main circuit
breaker (CB) in the main switchboard located in the building basement. The outgoing feeders
from this switchboard go inside riser ducts to feed each floor through a distribution
switchboard (sub-switchboard). This distribution switchboard distributes the power into the
different apartments within each floor via the utility meters of each apartment.
It is required to install standby generators as a backup to the utility supply to avoid the
uncertainty in utility power reliability and damage in the event of power failure. In this
situation, an interlock between the generators’ switches (circuit breakers) and the utility
feeder CB is needed to avoid paralleling between them.
In addition, it is necessary to install transfer switches on each floor to allow the standby-
generated power to flow into each apartment directly without passing through the utility
meters (Figure 1).
2/17
Figure 1 – Schematic drawing of main lines of feeding a commercial building
1. An interlocking panel for each generator located in the control room near the main
switchboard (utility switches),
2. Transfer-switches panel located at the DP of each floor, and
3. The interconnection between the equipment and the control room.
It is clear that the space required for the control room will be large, and the number of wires
needed between panels and remote points is also increased.
3/17
The operator monitors the system operation and the equipment functionality via the control
room to know the position of each switch (open/closed/emergency), to visually diagnose the
system status during a utility outage, and to diagnose the fault. These monitoring functions,
traditionally, need a very large number of indicating lamps and warning alarms.
Imagine the difficulties and confusion that the operator is subjected to because of the large
number of interconnecting wires and indicators. Also, do not forget the difficulties and
time consumed in commissioning and testing the system. On the other hand, the load is
increasing continuously and its nature may change resulting in a probable redesign of the
distribution system by adding new equipment or making changes in the wiring system that
may be difficult to implement.
With the workstation, the operator is able to display graphically on the screen the single-line
diagram of the distribution system and any other visual display needed by utilizing user-
friendly interaction through windows.
This system with high data acquisition and reporting requirements (but with
limited control) is defined as SCADA.
The SCADA system can be easily adapted to any change in the application field as it can be
integrated with other systems, for example, the protection system. Consider a power system
involving the protection relay as shown in Figure 2.
4/17
Figure 2 – Protection mechanism
In this diagram, the current and potential transformers send samples of phase currents and
phase voltages to be used as inputs to the protection relay. In turn, if these inputs violate
prespecified values, the relay sends a tripping signal to the CB to be opened. To
guarantee a correct performance for this protection mechanism, it must be ensured that the
protection relay is working properly.
This can be verified by testing the relay using a generator as a simulator to generate the
proper input signals and measuring the output (see Figure 3). The need for a simulator
arises because the utility company cannot interrupt the main power lines with the goal of
testing the relay. This test is applied from the protection point of view, but if it is needed to
use this relay as a data source to the SCADA system, the situation becomes quite different.
It needs to do another test to verify that the data generated by the protective functions are
correctly communicated to the SCADA system. In this case, knowledge of the exact
numerical representation of the data transmitted by the communication circuit is an important
factor.
5/17
Figure 3 – Testing of the relay by using a simulator
Where,
V = voltage;
I = current;
f = frequency.
Disadvantages of the relay systems and the advantages of the SCADA systems can be
summarized as below:
6/17
4. Control relays consume more power, generating more heat;
5. Relays are used only for on/off control;
6. Any change in the control program needs rewiring of the relays; and
7. It is difficult to troubleshoot and diagnose the fault for complicated control systems.
More details about SCADA, definitions, components, communication, and others are given in
the forthcoming paragraphs.
2. A SCADA System
SCADA system stands for supervisory control and data acquisition system. It refers to
the combination of telemetry and data acquisition. It commences with measurement of the
data by specific devices in the field of application and collected via intelligent electronic
devices (IEDs), then transferring these data to a master station to implement the necessary
processing and control algorithms.
The results of processing are displayed on a number of operator monitoring screens, while
the control actions are conveyed back to the field of application in real-time. See Figure 4
below.
7/17
Figure 4 – Elements of a SCADA system
2.1 Telemetry
Telemetry is the initial step in applying SCADA by defining the technique used for
measuring the data (voltage, current, speed, etc.) from different locations in the real-time
process and transferring it to the IEDs such as remote terminal units (RTUs) or PLCs in
another location through a communication circuit.
It can also be data to control equipment such as actuators, relays, valves, and electric
motors.
8/17
3. SCADA Components
The SCADA system consists of four components as follows.
Their main function is to convert the parameters from the physical form to electrical form as
continuous (analog) or discrete (digital) signals readable by the remote station equipment
(RTUs or PLCs).
9/17
The measuring devices (first component) connected to the plant being monitored and
controlled are interfaced to the remote station. Functions of remote stations are
1. Gathering data from the different devices in the plant being monitored and controlled;
2. Holding the data gathered in its memory and waiting for a request from the master
station (master terminal unit [MTU]) to transmit the data; and
3. Receiving data and control signals from MTU and transmitting the control signals to the
plant devices.
The remote station is either RTU or PLC. The RTU is used effectively in the event of difficult
communications. Its inputs and outputs are shown in Figure 6.
The RTU has digital/analog inputs and outputs with light-emitting diode (LED) indication
(selectable per channel), optically isolated for surge protection, and also protected against
short circuits. On the other hand, the PLC is usually expected to be already available in the
plant processes, so it is of great worth to be used also in the SCADA systems.
It’s worth saying that both the RTU and PLC have been greatly improved in the last ten
years.
10/17
Figure 7 – Remote terminal unit: inputs/outputs (Siemens Simatic RTU3030C RTU)
The hardware and software design of both MTU and RTUs must guarantee that the
information is transferred correctly from the RTUs to the MTU and vice versa, and not
affected by the noise occurring randomly on the communication channel.
11/17
The configuration of the communication system depends on:
3.3.1 Modulation
To convey information from one point (sending end [SE]) to another point (receiving end
[RE]) through a communication channel, it must be modulated at the SE and demodulated at
RE. This means that it is necessary to transmit a signal with a change from SE to RE where
it is detected. This change can be carried out by either a change in signal amplitude or
change of signal frequency or change of signal phase.
The demodulator at RE detects the change in the signal and outputs the transmitted
information.
12/17
If the information transmission is only in one direction, it is called “simplex channel”, and if it
is in the two directions but not simultaneously, it is called “half duplex”. Finally, if the
transmission is in the two directions and simultaneous, it is called “full duplex”.
3.3.2 Multiplexing
In the SCADA system structure, it is needed to transmit information from different locations to
one point, that is, multi-transmitter to one receiver. Economically, the best method is to use a
single communication channel for many pieces of information.
This is known as “multiplexing” and can be carried out by one of two basic techniques: (1)
frequency division multiplexing (FDM) and (2) time-division multiplexing (TDM).
13/17
Figure 8 – Frequency division multiplexing
In the FDM technique, each piece of information is transmitted over a dedicated part of the
available communication channel spectrum (Figure 8). For the TDM technique, each piece of
information is transmitted as part of a serial digital message over a separate span of time
and demultiplexed by the receiver into the individual pieces of information (Figure 9).
14/17
Watch Video At: https://youtu.be/fIZhDl35_XY
The transmission of information in both directions between the MTU and RTUs using TDM
techniques requires the use of serial digital messages. All messages are divided into three
basic parts:
Message Establishment – Which provides the signals to synchronize the receiver and
transmitter and the unique RTU address;
Information – Which provides the data in a coded form to allow the receiver to decode the
information and properly utilize it; and
Message Termination – This provides the message security checks and a means of denoting
the end of the message. Message security checks consist of logical operations on the data,
which result in a predefined number of check bits transmitted with the message. At the
receiver, the same operations are performed on the data and compared with the received
check bits.
The message is accepted if they are identical, otherwise, a retransmission of the original
message is required.
15/17
3.3.4 Information Transfer
As it is clear in the preceding sections, the information in SCADA systems is transmitted from
the RTUs to the MTU and also from the MTU to the RTUs. Therefore, it is not sufficient to
just transmit the information correctly, but it must also be done securely.