PRESSURISATION UNIT SCHEDULE

UNIT REFERENCE PU-4TX-26-01 PU-4TX-45-01 PU-4TX-45-02 PU-4TX-45-03 PU-4TX-70-01 PU-4TX-70-02 PU-4TX-70-03


LOCATION 4TX PLANTROOM L26 4TX PLANTROOM L45 4TX PLANTROOM L45 4TX PLANTROOM L45 4TX PLANTROOM L70 4TX PLANTROOM L70 4TX PLANTROOM L70
SERVICE CHW - NORMAL/CRITICAL LZ CHW - NORMAL MZ CHW - CRITICAL LINE 1 MZ CHW - CRITICAL LINE 2 MZ CHW - NORMAL HZ CHW - CRITICAL LINE 1 HZ CHW - CRITICAL LINE 2 HZ
CAPACITY (LITERS) 2500 300 215 215 800 215 215
MAX. ADMISSIBLE PRESSURE kPa
MIN. ADMISSIBLE PRESSURE kPa 70 70 70 70 70 70 70
MAX. ADMISSIBLE TEMPERATURE °C 35 35 35 35 35 35 35
MIN. ADMISSIBLE TEMPERATURE °C 6 6 6 6 6 6 6
MAX. ADMISSIBLE AMBIENT TEMPERATURE °C 46 46 46 46 46 46 46
ELECTRIC VOLTAGE V 400 400 400 400 400 400 400
PHASE ph 3 3 3 3 3 3 3
ELECTRIC LOAD kW 0.5 0.5 0.5 0.5 0.5 0.5 0.5

NOTES:
1. THIS SCHEDULE SHALL BE READ IN-CONJUNCTION WITH THE SPECIFICATION AND DRAWINGS
2. LOCATE UNITS WITH ADEQUATE SPACE FOR SAFE MAINTENANCE
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR CALCULATING THE FINAL SYSTEM VOLUME AND FINAL
SELECTION OF EXPANSION VESSEL BASED IN FINAL SELECTION OF EQUIPMENT AND INSTALLATION DRAWINGS
4. WIRING TO COMPLY WITH BS 7671
5. PROVIDE ALL NECESSARY INTERCONNECTING PIPEWORK
6. THE UNIT CONTROLS SHALL INCLUDE:
A.) ALTERNATING PUMP STARTING WHERE TWO OR MORE PUMPS ARE SPECIFIED
B.) PUMP START EFFICIENCY
C.) LEAK DETECTION ALARM TO INDICATE LEAK IF ABOVE MAXIMUM STATS PER HOUR
D.) HIGH/LOW PRESSURE ALARMS ARRANGED FOR MANUAL RESTART
E.) COMMON ALARM TO SHUTDOWN SYSTEM IF IT EXCEEDS PRESSURE LIMITS AND PROVIDE INDICATION OF FAULT
F.) EMERGENCY STOP BUTTON
7. PROVIDE VISUAL DISPLAY FOR HIGH/LOW FLOW; PUMP FAILURE; EXCESSIVE PUMP OPERATION; LOW WATER LEVEL.