I.

Graveleux Latéritique

1/20
𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

I. GRAVELEUX LATERITIQUE
Section : Début : PK 01+591 Fin : PK 01+750 Qtte : 730.390 m³

ODOMETA PK 12+600 PK 01+750 PK 01+591

{█( @87
@ Km
@ @ @ @ @ @ @10.85
@@@ Km
@ @ @ @ @ )┤ 0.0795 Km 0.0795 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 97.85 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.08 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 87.9295 Km

PVTr = 730.39 m³ x 87.9295 Km

𝑃𝑉𝑇𝑟= 64,223 m³.Km ⇒ Montant= 11,238,995 f cfa

I. GRAVELEUX LATERITIQUE
Section : Début : PK 01+750 Fin : PK 03+050 Qtte : 9880.000 m³

ODOMETA PK 12+600 PK 03+050 PK 01+750

{█( @87
@ Km
@ @ @ @ @ @ @ 9.55
@ @ Km
@ @ @ @ @ @ )┤ 0.65 Km 0.65 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 96.55 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.65 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 87.2000 Km

PVTr = 9880 m³ x 87.2 Km

𝑃𝑉𝑇𝑟= 861,536 m³.Km ⇒ Montant= 150,768,800 f cfa

I. GRAVELEUX LATERITIQUE
Section : Début : PK 03+050 Fin : PK 03+300 Qtte : 2156.120 m³

ODOMETA PK 12+600 PK 03+300 PK 03+050

{█( @87
@ Km 9.3@Km
@@@@@@@@ @ @ @ @ @ @ )┤ 0.125 Km 0.125 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 96.30 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.13 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 86.4250 Km

PVTr = 2156.12 m³ x 86.425 Km

2/20
𝑃𝑉𝑇𝑟= 186,343 m³.Km ⇒ Montant= 32,609,967 f cfa
𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

I. GRAVELEUX LATERITIQUE
Section : Début : PK 03+300 Fin : PK 04+350 Qtte : 5516.800 m³

ODOMETA PK 12+600 PK 04+350 PK 03+300

{█( @87
@ Km
@ @ @ @ @ @ @ 8.25
@ @ Km
@ @ @ @ @ @ )┤ 0.525 Km 0.525 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 95.25 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.53 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 85.7750 Km

PVTr = 5516.8 m³ x 85.775 Km

𝑃𝑉𝑇𝑟= 473,204 m³.Km ⇒ Montant= 82,810,616 f cfa

I. GRAVELEUX LATERITIQUE
Section : Début : PK 04+350 Fin : PK 04+525 Qtte : 1388.630 m³

ODOMETA PK 12+600 PK 04+525 PK 04+350

{█( @87
@ Km
@ @ @ @ @ @ @8.075
@@@ Km
@ @ @ @ @ )┤ 0.0875 Km 0.0875 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 95.08 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.09 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 85.1625 Km

PVTr = 1388.63 m³ x 85.1625 Km

𝑃𝑉𝑇𝑟= 118,259 m³.Km ⇒ Montant= 20,695,360 f cfa

I. GRAVELEUX LATERITIQUE
Section : Début : PK 04+525 Fin : PK 05+600 Qtte : 7485.800 m³

ODOMETA PK 12+600 PK 05+600 PK 04+525

{█( @87
@ Km
@ @ @ @ @ @ @ @7@
Km@ @ @ @ @ @ )┤ 0.5375 Km 0.5375 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 94.00 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.54 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 84.5375 Km

3/20
PVTr = 7485.8 m³ x 84.5375 Km

𝑃𝑉𝑇𝑟= 632,831 m³.Km ⇒ Montant= 110,745,393 f cfa


𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

I. GRAVELEUX LATERITIQUE
Section : Début : PK 05+600 Fin : PK 05+725 Qtte : 831.500 m³

ODOMETA PK 12+600 PK 05+725 PK 05+600

{█( @87
@ Km
@ @ @ @ @ @ @6.875
@@@ Km
@ @ @ @ @ )┤ 0.0625 Km 0.0625 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 93.88 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.06 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 83.9375 Km

PVTr = 831.5 m³ x 83.9375 Km

𝑃𝑉𝑇𝑟= 69,794 m³.Km ⇒ Montant= 12,213,955 f cfa

I. GRAVELEUX LATERITIQUE
Section : Début : PK 05+725 Fin : PK 06+250 Qtte : 3529.400 m³

ODOMETA PK 12+600 PK 06+250 PK 05+725

{█( @87
@ Km
@ @ @ @ @ @ @ 6.35
@ @ Km
@ @ @ @ @ @ )┤ 0.2625 Km 0.2625 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 93.35 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.26 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 83.6125 Km

PVTr = 3529.4 m³ x 83.6125 Km

𝑃𝑉𝑇𝑟= 295,102 m³.Km ⇒ Montant= 51,642,843 f cfa

I. GRAVELEUX LATERITIQUE
Section : Début : PK 06+250 Fin : PK 06+425 Qtte : 1765.070 m³

ODOMETA PK 12+600 PK 06+425 PK 06+250

{█( @87
@ Km
@ @ @ @ @ @ @6.175
@@@ Km
@ @ @ @ @ )┤ 0.0875 Km 0.0875 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 93.18 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.09 Km

4/20
𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 83.2625 Km

PVTr = 1765.07 m³ x 83.2625 Km

𝑃𝑉𝑇𝑟= 146,964 m³.Km ⇒ Montant= 25,718,725 f cfa


𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

I. GRAVELEUX LATERITIQUE
Section : Début : PK 06+425 Fin : PK 10+600 Qtte : 24621.900 m³

ODOMETA PK 12+600 PK 10+600 PK 06+425

{█( @87
@ Km
@ @ @ @ @ @ @ @2@
Km@ @ @ @ @ @ )┤ 2.0875 Km 2.0875 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 89.00 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 02.09 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 81.0875 Km

PVTr = 24621.9 m³ x 81.0875 Km

𝑃𝑉𝑇𝑟= 1,996,528 m³.Km ⇒ Montant= 349,392,455 f cfa

I. GRAVELEUX LATERITIQUE
Section : Début : PK 10+600 Fin : PK 11+000 Qtte : 3967.630 m³

ODOMETA PK 12+600 PK 11+000 PK 10+600

{█( @87
@ Km 1.6@Km
@@@@@@@@ @ @ @ @ @ @ )┤ 0.2 Km 0.2 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 88.60 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.20 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 78.8000 Km

PVTr = 3967.63 m³ x 78.8 Km

𝑃𝑉𝑇𝑟= 312,649 m³.Km ⇒ Montant= 54,713,618 f cfa

I. GRAVELEUX LATERITIQUE
Section : Début : PK 11+000 Fin : PK 12+500 Qtte : 8914.900 m³

ODOMETA PK 12+600 PK 12+500 PK 11+000

{█( @87
@ Km 0.1@Km
@@@@@@@@ @ @ @ @ @ @ )┤ 0.75 Km 0.75 Km

5/20
{█( @ @ @ @ @ @ @ @ @ @ @ @ @ @ @ @ @ )┤
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 87.10 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.75 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 77.8500 Km

PVTr = 8914.9 m³ x 77.85 Km

𝑃𝑉𝑇𝑟= 694,025 m³.Km ⇒ Montant= 121,454,369 f cfa


I. GRAVELEUX LATERITIQUE
Section : Début : PK 12+500 Fin : PK 12+600 Qtte : 1223.391 m³

ODOMETA PK 12+600 PK 12+600 PK 12+500

{█( @87
@ Km
@ @ @ @ @ @ @ @0@
Km@ @ @ @ @ @ )┤ 0.05 Km 0.05 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 87.00 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.05 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 77.0500 Km

PVTr = 1223.391 m³ x 77.05 Km

𝑃𝑉𝑇𝑟= 94,262 m³.Km ⇒ Montant= 16,495,898 f cfa

I. GRAVELEUX LATERITIQUE
Section : Début : PK 03+560 Fin : PK 03+560 Qtte : 300.410 m³

ODOMETA PK 12+600 PK 03+560 PK 03+560

{█( @87
@ Km
@ @ @ @ @ @ @ 9.04
@ @ Km
@ @ @ @ @ @ )┤ 0 Km 0 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 96.04 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.00 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 86.0400 Km

PVTr = 300.41 m³ x 86.04 Km

𝑃𝑉𝑇𝑟= 25,847 m³.Km ⇒ Montant= 4,523,273 f cfa

PVTr Total = 5,971,567.246 m³.Km

Montant Total = 1,045,024,268 f cfa

6/20
72311.941

7/20
Ii. Grave concassee 0/31.5

8/20
𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 01+591 Fin : PK 01+750 Qtte : 456.700 m³

TAN PK 12+600 PK 01+750 PK 01+591

{█( @142
@@ Km
@ @ @ @ @ @10.85
@@@ Km
@ @ @ @ @ )┤ 0.0795 Km 0.0795 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 152.85 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.08 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 142.9295 Km

PVTr = 456.7 m³ x 142.9295 Km

𝑃𝑉𝑇𝑟= 65,276 m³.Km ⇒ Montant= 11,423,283 f cfa

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 01+750 Fin : PK 03+050 Qtte : 4073.100 m³

TAN PK 12+600 PK 03+050 PK 01+750

{█( @142
@@ Km
@ @ @ @ @ @ 9.55
@ @ Km
@ @ @ @ @ @ )┤ 0.65 Km 0.65 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 151.55 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.65 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 142.2000 Km

PVTr = 4073.1 m³ x 142.2 Km

𝑃𝑉𝑇𝑟= 579,195 m³.Km ⇒ Montant= 101,359,094 f cfa

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 03+050 Fin : PK 03+300 Qtte : 967.800 m³

TAN PK 12+600 PK 03+300 PK 03+050

{█( @142
@@ Km 9.3@Km
@@@@@@@ @ @ @ @ @ @ )┤ 0.125 Km 0.125 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 151.30 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.13 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 141.4250 Km

9/20
PVTr = 967.8 m³ x 141.425 Km

𝑃𝑉𝑇𝑟= 136,871 m³.Km ⇒ Montant= 23,952,445 f cfa


𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 03+300 Fin : PK 04+350 Qtte : 2503.000 m³

TAN PK 12+600 PK 04+350 PK 03+300

{█( @142
@@ Km
@ @ @ @ @ @ 8.25
@ @ Km
@ @ @ @ @ @ )┤ 0.525 Km 0.525 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 150.25 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.53 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 140.7750 Km

PVTr = 2503 m³ x 140.775 Km

𝑃𝑉𝑇𝑟= 352,360 m³.Km ⇒ Montant= 61,662,969 f cfa

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 04+350 Fin : PK 04+525 Qtte : 625.000 m³

TAN PK 12+600 PK 04+525 PK 04+350

{█( @142
@@ Km
@ @ @ @ @ @8.075
@@@ Km
@ @ @ @ @ )┤ 0.0875 Km 0.0875 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 150.08 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.09 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 140.1625 Km

PVTr = 625 m³ x 140.1625 Km

𝑃𝑉𝑇𝑟= 87,602 m³.Km ⇒ Montant= 15,330,273 f cfa

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 04+525 Fin : PK 05+600 Qtte : 3374.400 m³

TAN PK 12+600 PK 05+600 PK 04+525

{█( @142
@@ Km
@ @ @ @ @ @ @7@
Km@ @ @ @ @ @ )┤ 0.5375 Km 0.5375 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 149.00 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.54 Km

10/20
𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 139.5375 Km

PVTr = 3374.4 m³ x 139.5375 Km

𝑃𝑉𝑇𝑟= 470,855 m³.Km ⇒ Montant= 82,399,685 f cfa


𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 05+600 Fin : PK 05+725 Qtte : 616.900 m³

TAN PK 12+600 PK 05+725 PK 05+600

{█( @142
@@ Km
@ @ @ @ @ @6.875
@@@ Km
@ @ @ @ @ )┤ 0.0625 Km 0.0625 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 148.88 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.06 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 138.9375 Km

PVTr = 616.9 m³ x 138.9375 Km

𝑃𝑉𝑇𝑟= 85,711 m³.Km ⇒ Montant= 14,999,345 f cfa

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 05+725 Fin : PK 06+250 Qtte : 1613.900 m³

TAN PK 12+600 PK 06+250 PK 05+725

{█( @142
@@ Km
@ @ @ @ @ @ 6.35
@ @ Km
@ @ @ @ @ @ )┤ 0.2625 Km 0.2625 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 148.35 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.26 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 138.6125 Km

PVTr = 1613.9 m³ x 138.6125 Km

𝑃𝑉𝑇𝑟= 223,707 m³.Km ⇒ Montant= 39,148,675 f cfa

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 06+250 Fin : PK 06+425 Qtte : 1080.700 m³

TAN PK 12+600 PK 06+425 PK 06+250

11/20
{█( @142
@@ Km
@ @ @ @ @ @6.175
@@@ Km
@ @ @ @ @ )┤ 0.0875 Km 0.0875 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 148.18 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.09 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 138.2625 Km

PVTr = 1080.7 m³ x 138.2625 Km

𝑃𝑉𝑇𝑟= 149,420 m³.Km ⇒ Montant= 26,148,550 f cfa


𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 06+425 Fin : PK 10+600 Qtte : 13008.700 m³

TAN PK 12+600 PK 10+600 PK 06+425

{█( @142
@@ Km
@ @ @ @ @ @ @2@
Km@ @ @ @ @ @ )┤ 2.0875 Km 2.0875 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 144.00 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 02.09 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 136.0875 Km

PVTr = 13008.7 m³ x 136.0875 Km

𝑃𝑉𝑇𝑟= 1,770,321 m³.Km ⇒ Montant= 309,806,256 f cfa

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 10+600 Fin : PK 11+000 Qtte : 1921.500 m³

TAN PK 12+600 PK 11+000 PK 10+600

{█( @142
@@ Km 1.6@Km
@@@@@@@ @ @ @ @ @ @ )┤ 0.2 Km 0.2 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 143.60 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.20 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 133.8000 Km

PVTr = 1921.5 m³ x 133.8 Km

𝑃𝑉𝑇𝑟= 257,097 m³.Km ⇒ Montant= 44,991,923 f cfa

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 11+000 Fin : PK 12+500 Qtte : 4696.900 m³

12/20
TAN PK 12+600 PK 12+500 PK 11+000

{█( @142
@@ Km 0.1@Km
@@@@@@@ @ @ @ @ @ @ )┤ 0.75 Km 0.75 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 142.10 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.75 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 132.8500 Km

PVTr = 4696.9 m³ x 132.85 Km

𝑃𝑉𝑇𝑟= 623,983 m³.Km ⇒ Montant= 109,197,054 f cfa


II. GRAVE CONCASSEE 0/31.5
Section : Début : PK 12+500 Fin : PK 12+600 Qtte : 643.890 m³

TAN PK 12+600 PK 12+600 PK 12+500

{█( @142
@@ Km
@ @ @ @ @ @ @0@
Km@ @ @ @ @ @ )┤ 0.05 Km 0.05 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 142.00 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.05 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 132.0500 Km

PVTr = 643.89 m³ x 132.05 Km

𝑃𝑉𝑇𝑟= 85,026 m³.Km ⇒ Montant= 14,879,493 f cfa

II. GRAVE CONCASSEE 0/31.5


Section : Début : PK 03+560 Fin : PK 03+560 Qtte : 137.500 m³

TAN PK 12+600 PK 03+560 PK 03+560

{█( @142
@@ Km
@ @ @ @ @ @ 9.04
@ @ Km
@ @ @ @ @ @ )┤ 0 Km 0 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 151.04 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.00 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 141.0400 Km

PVTr = 137.5 m³ x 141.04 Km

𝑃𝑉𝑇𝑟= 19,393 m³.Km ⇒ Montant= 3,393,775 f cfa

PVTr Total = 4,906,816.107 m³.Km

Montant Total = 858,692,819 f cfa

13/20
Iii. Grave bitume

14/20
𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

III. GRAVE BITUME


Section : Début : PK 01+591 Fin : PK 01+750 Qtte : 223.500 m³

TAN PK 12+600 PK 01+750 PK 01+591

{█( @142
@@ Km
@ @ @ @ @ @10.85
@@@ Km
@ @ @ @ @ )┤ 0.0795 Km 0.0795 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 152.85 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.08 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 142.9295 Km

PVTr = 223.5 m³ x 142.9295 Km

𝑃𝑉𝑇𝑟= 31,945 m³.Km ⇒ Montant= 5,590,330 f cfa

III. GRAVE BITUME


Section : Début : PK 01+750 Fin : PK 03+050 Qtte : 1976.000 m³

TAN PK 12+600 PK 03+050 PK 01+750

{█( @142
@@ Km
@ @ @ @ @ @ 9.55
@ @ Km
@ @ @ @ @ @ )┤ 0.65 Km 0.65 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 151.55 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.65 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 142.2000 Km

PVTr = 1976 m³ x 142.2 Km

𝑃𝑉𝑇𝑟= 280,987 m³.Km ⇒ Montant= 49,172,760 f cfa

III. GRAVE BITUME


Section : Début : PK 03+050 Fin : PK 03+300 Qtte : 468.000 m³

TAN PK 12+600 PK 03+300 PK 03+050

{█( @142
@@ Km 9.3@Km
@@@@@@@ @ @ @ @ @ @ )┤ 0.125 Km 0.125 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 151.30 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.13 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 141.4250 Km

PVTr = 468 m³ x 141.425 Km

15/20
𝑃𝑉𝑇𝑟= 66,187 m³.Km ⇒ Montant= 11,582,708 f cfa
𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

III. GRAVE BITUME


Section : Début : PK 03+300 Fin : PK 04+350 Qtte : 1176.000 m³

TAN PK 12+600 PK 04+350 PK 03+300

{█( @142
@@ Km
@ @ @ @ @ @ 8.25
@ @ Km
@ @ @ @ @ @ )┤ 0.525 Km 0.525 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 150.25 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.53 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 140.7750 Km

PVTr = 1176 m³ x 140.775 Km

𝑃𝑉𝑇𝑟= 165,551 m³.Km ⇒ Montant= 28,971,495 f cfa

III. GRAVE BITUME


Section : Début : PK 04+350 Fin : PK 04+525 Qtte : 301.100 m³

TAN PK 12+600 PK 04+525 PK 04+350

{█( @142
@@ Km
@ @ @ @ @ @8.075
@@@ Km
@ @ @ @ @ )┤ 0.0875 Km 0.0875 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 150.08 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.09 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 140.1625 Km

PVTr = 301.1 m³ x 140.1625 Km

𝑃𝑉𝑇𝑟= 42,203 m³.Km ⇒ Montant= 7,385,513 f cfa

III. GRAVE BITUME


Section : Début : PK 04+525 Fin : PK 05+600 Qtte : 1634.000 m³

TAN PK 12+600 PK 05+600 PK 04+525

{█( @142
@@ Km
@ @ @ @ @ @ @7@
Km@ @ @ @ @ @ )┤ 0.5375 Km 0.5375 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 149.00 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.54 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 139.5375 Km

16/20
PVTr = 1634 m³ x 139.5375 Km

𝑃𝑉𝑇𝑟= 228,004 m³.Km ⇒ Montant= 39,900,748 f cfa


𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

III. GRAVE BITUME


Section : Début : PK 05+600 Fin : PK 05+725 Qtte : 318.100 m³

TAN PK 12+600 PK 05+725 PK 05+600

{█( @142
@@ Km
@ @ @ @ @ @6.875
@@@ Km
@ @ @ @ @ )┤ 0.0625 Km 0.0625 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 148.88 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.06 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 138.9375 Km

PVTr = 318.1 m³ x 138.9375 Km

𝑃𝑉𝑇𝑟= 44,196 m³.Km ⇒ Montant= 7,734,303 f cfa

III. GRAVE BITUME


Section : Début : PK 05+725 Fin : PK 06+250 Qtte : 800.600 m³

TAN PK 12+600 PK 06+250 PK 05+725

{█( @142
@@ Km
@ @ @ @ @ @ 6.35
@ @ Km
@ @ @ @ @ @ )┤ 0.2625 Km 0.2625 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 148.35 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.26 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 138.6125 Km

PVTr = 800.6 m³ x 138.6125 Km

𝑃𝑉𝑇𝑟= 110,973 m³.Km ⇒ Montant= 19,420,304 f cfa

III. GRAVE BITUME


Section : Début : PK 06+250 Fin : PK 06+425 Qtte : 498.100 m³

TAN PK 12+600 PK 06+425 PK 06+250

{█( @142
@@ Km
@ @ @ @ @ @6.175
@@@ Km
@ @ @ @ @ )┤ 0.0875 Km 0.0875 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 148.18 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.09 Km

17/20
𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 138.2625 Km

PVTr = 498.1 m³ x 138.2625 Km

𝑃𝑉𝑇𝑟= 68,869 m³.Km ⇒ Montant= 12,051,996 f cfa


𝑃𝑉𝑇𝑟=𝑄𝑡𝑡𝑒×𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡=𝐷_𝑚𝑜𝑟𝑡𝑒+𝐷_𝑚𝑜𝑦𝑒𝑛𝑛𝑒−10 𝐾𝑚

III. GRAVE BITUME


Section : Début : PK 06+425 Fin : PK 10+600 Qtte : 6384.000 m³

TAN PK 12+600 PK 10+600 PK 06+425

{█( @142
@@ Km
@ @ @ @ @ @ @2@
Km@ @ @ @ @ @ )┤ 2.0875 Km 2.0875 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 144.00 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 02.09 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 136.0875 Km

PVTr = 6384 m³ x 136.0875 Km

𝑃𝑉𝑇𝑟= 868,783 m³.Km ⇒ Montant= 152,036,955 f cfa

III. GRAVE BITUME


Section : Début : PK 10+600 Fin : PK 11+000 Qtte : 935.900 m³

TAN PK 12+600 PK 11+000 PK 10+600

{█( @142
@@ Km 1.6@Km
@@@@@@@ @ @ @ @ @ @ )┤ 0.2 Km 0.2 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 143.60 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.20 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 133.8000 Km

PVTr = 935.9 m³ x 133.8 Km

𝑃𝑉𝑇𝑟= 125,223 m³.Km ⇒ Montant= 21,914,099 f cfa

III. GRAVE BITUME


Section : Début : PK 11+000 Fin : PK 12+500 Qtte : 2318.000 m³

TAN PK 12+600 PK 12+500 PK 11+000

{█( @142
@@ Km 0.1@Km
@@@@@@@ @ @ @ @ @ @ )┤ 0.75 Km 0.75 Km

18/20
{█( @ @ @ @ @ @ @ @ @ @ @ @ @ @ @ @ @ )┤
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 142.10 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.75 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 132.8500 Km

PVTr = 2318 m³ x 132.85 Km

𝑃𝑉𝑇𝑟= 307,946 m³.Km ⇒ Montant= 53,890,603 f cfa


III. GRAVE BITUME
Section : Début : PK 12+500 Fin : PK 12+600 Qtte : 321.940 m³

TAN PK 12+600 PK 12+600 PK 12+500

{█( @142
@@ Km
@ @ @ @ @ @ @0@
Km@ @ @ @ @ @ )┤ 0.05 Km 0.05 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 142.00 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.05 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 132.0500 Km

PVTr = 321.94 m³ x 132.05 Km

𝑃𝑉𝑇𝑟= 42,512 m³.Km ⇒ Montant= 7,439,631 f cfa

III. GRAVE BITUME


Section : Début : PK 03+560 Fin : PK 03+560 Qtte : 65.000 m³

TAN PK 12+600 PK 03+560 PK 03+560

{█( @142
@@ Km
@ @ @ @ @ @ 9.04
@ @ Km
@ @ @ @ @ @ )┤ 0 Km 0 Km
{█( @ @ @ @ @ @ @ )┤
𝐷𝑚𝑜𝑟𝑡𝑒 = 151.04 Km 𝐷𝑚𝑜𝑦𝑒𝑛𝑛𝑒 = 00.00 Km

𝐷_𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 = 141.0400 Km

PVTr = 65 m³ x 141.04 Km

𝑃𝑉𝑇𝑟= 09,168 m³.Km ⇒ Montant= 1,604,330 f cfa

PVTr Total = 2,392,547.282 m³.Km

Montant Total = 418,695,774 f cfa

19/20
Prix 175
Coef Fois G 1.4
Coef Fois GC 1.3