Professional Documents
Culture Documents
New1 MR Gonse
New1 MR Gonse
New1 MR Gonse
INSTITUTE OF TECHNOLOGY
Aug. 2016
Acronyms
T = return period
S = standard deviation
A = catchments area
C = runoff coefficient
I = intensity of rainfall
D = rainfall duration
Tc = time of concentration
AMC = Antecedent Moisture Content
S = runoff gradient for direct runoff
Q = discharge
V = velocity R = hydraulic
radius n = Manning‟s
coefficient P = wetted
perimeter
By GONSE AMALO i
Page
Table of Contents
1. Watershed delineation ........................................................................................................... 1
2. Area of the catchment ......................................................................................................... 13
2.1 longest flow path
length ...................................................................................................... 13
2.2 Watershed
slope .................................................................................................................. 14
2.3 Time of
concentration.......................................................................................................... 14
2.4 Location of delineated
watershed ......................................................................................... 14
3.1 Design rainfall and Design flood estimation ..................................................................... 17
3.2 Data Consistency Test ......................................................................................................... 17
3.2 Tests for Outliers .................................................................................................................
20
3.3 Daily heaviest rainfall frequency analysis ............................................................................ 21
3.4 Design rain fall computation ............................................................................................... 21
3.4.1 Normal distribution method ...................................................................................... 21
3.4.2 Log-Normal distribution method ............................................................................... 23
3.4.3 Gumbel's distribution methods .................................................................................. 26
3.4.4 Log-Pearson Type III Distribution Method............................................................. 28
3.4.5 Pearson Type III Distribution Method. .................................................................... 30
3.4.6 Extreme value type-I ................................................................................................. 30
3.4.7 Extreme value type-II ................................................................................................. 32
4.Unit hydrograph .................................................................................................................. 40
4.1 Triangular hydrograph ..................................................................................................... 40
4.2 Developing Composite Hydrograph ..................................................................................... 44
5 POWER DETERMINATION............................................................................................. 45
5.1 Selection for Type of turbine ............................................................................................... 47 6
DESIGN OF HEAD WORK ................................................................................................ 47
By GONSE AMALO ii
6.4 Uplift pressure at key points using Khosla‟s theory .............................................................. 53
6.5 Stability Analysis ……………………………………………………………………...……..57
7 Retaining Wall Design……………………………………………………………………….…59
7.1 Stability Analysis of Retaining Walls………………………………………………..……….61
Page
List of Figures
Fig.1 Ethio_ DEM containing our interest area…………………………………………...1
Fig.2 Extracted DEM from Ethio_DEM containing our interest area…………………….2
Fig.3 Flow direction of unprocessed Extracted DEM……………………………………..2
Fig.4 Sink of flow direction……………………………………………………………….3
Fig. 5 The Fill sinks of Extracted DEM…………………………………………………...3
Fig.6. Fill Flow Direction of Extracted DEM………………………………………….….4
Fig.7 Flow Accumulation of Extracted DEM……………………………………………..4
Fig.8. Added Outlet………………………………………………………………………..5
Fig.9. Snap to Pour………………………………………………………………………..5
Fig.10. Delineated watershed……………………………………………………………...6
Fig11: Delineated watershed from Ethio- DEM…………………………………………..6
Fig12: Masked watershed from Ethio- DEM……………………………………………...7
Fig.13 Flow direction of unprocessed Masked-DEM……………………………………..7
Fig.14 Sink of flow direction ……………………………………………………………..8
Fig. 15 The Fill sinks of Masked DEM…………………………………………………...8
Fig.16 Fill Flow Direction of Masked-DEM……………………………………………...9
Fig.17 Flow Accumulation of Extracted DEM……………………………………………9
Fig.18 Converted Masked watershed…………………………………………………….10
Fig.19 Con of Masked DEM……………………………………………………………..10
Fig.20 Flow Length ……………………………………………………………………...11
Fig.21. Stream Link of Masked DEM……………………………………………………11
Fig.22 Stream Order of Masked DEM…………………………………………………...12
Fig.23 Stream to feature of Masked DEM……………………………………………….12
Fig.24 Basin of Masked DEM …………………………………………………………..13
Fig.25.Daily FDC………………………………………………………………………..15
Fig.26.Monthly FDC………………………………………………………………..........15
Fig.27.Annual FDC……………………………………………………………………....16
Page
Fig.39 Weir profile……………………………………………………………………….50
Fig 40 location of hydraulic jump………………………………………………………..51
Fig 41 Cut off piles…………………………………………………………53
Fig 42 Sub surface hydraulic gradient……………………………………...57
Fig.43 All forces act up on the weir body………………………………………………..57
Fig. 44 Profile of over flow section……………………………………………………...58
Fig.45 U/S Retaining Wall………………………………………………………………60
Fig .46 D/S Retaining Wall……………………………………………………………...60
Tables
Table 1 Rainfall data and rainfall depth………………………………………………….18
Table 2 Data consistency test for annual rainfall………………………………………...18
Table 3.Tests criteria for outliers………………………………………………………...20
Table 4.Calculated statically parameters………………………………………………...20
Table 5 Normal distribution……………………………………………………………...21
Table 6 For the different return periods the maximum probable point rainfall is calculated
as follows………………………………………………………….……………………..23
Table 7.Log-Normal distribution………………………………………………………...24
Table 8 For the different return periods the maximum probable point rainfall is calculated
as follows………………………………………………………………………………..26
Table 9 Gumbel's methods………………………………………………………………26
By GONSE AMALO iv
Table10. For the different return periods the maximum probable point rainfall is
calculated as follows……………………………………………………………………..28
Table 11.LOG-PEARSON TYPE III…………………………………………………….28
Table12. For the different return periods the maximum probable point rainfall is
calculated as follows……………………………………………………………………..29
Table13. For the different return periods the maximum probable point rainfall is
calculated as follows……………………………………………………………………..30
Table 14 Extreme value type I…………………………………………………………...31
Table 15.For the different return periods the maximum probable point rainfall is
calculated as follows……………………………………………………………………..32
Table 16.Extreme value type II…………………………………………………………..33
Table17. For the different return periods the maximum probable point rainfall is
calculated as follows……………………………………………………………………..34
Table18. Peak rainfall estimates using different statistical distributions ………………..34
Table 19. A summarized Gumble- powell‟s table……………………………………….35
Table 20 Area to point Ratio ……………………….........................................................37
Page
By GONSE AMALO v
Table 21 Composite Hydrograph………………………………………………………...44
Table 22.Rain fall converted to run off………………………………………………..…46
Table 23 Ratio of P/Hd and Cd………………………………………………………...…48
Table 24 Values of constant K and N……………………...............................................49
Table 25 Self-weight and earth pressure forces acting on the wall …………………......61
Table 26 Self-weight and earth pressure forces acting on the wall ……………………..62
Table 27 Specification and quantity surveying.…………………………………...…..…63
Table 28 Summary for Each Activity………………………………...………………….65
1. Watershed delineation
To delineate a catchment from digital elevation map (DEM) of Ethiopia by using Arc GIS
tools or Arc swat based on the given outlet coordinate points.
Since the DEM is larger than our interest area/catchment, I can clip out our area of interest
from the Ethio DEM by using “Arc Tool box/Spatial Analyst
Produce flow direction raster using the unprocessed Extracted- DEM “Arc Tool
box/Spatial Analyst Tool/ hydrology/flow direction: then inserting Extracted DEM in
Input raster. The result was as follows:
This can be done in Conversion tools/From Raster/ Raster to Polygon: the input was masked
watershed.
This can be done in Spatial analysis tool/ Conditional/ Con From Raster/ Raster to Polygon: The
input was flow accumulation, VALUE >= 1000, and 1
This can be done in Arc Tool box/Spatial Analyst Tool/ hydrology/Flow Length :the input was
flow direction.
This can be done in Arc Tool box/Spatial Analyst Tool/ hydrology/Stream Feature: the input
was Con and flow direction.
This can be done in Arc Tool box/Spatial Analyst Tool/ hydrology/Basin: the input flow direction.
The data given in Excel (Flow 4) contains 48 years data from 1959 to 2006 with a lot of
missed data. For the computation I have selected the data from year 1985 to 2004 a data of
20 years. I have filled the missed data found in this interval by using correlation using
Excel with criteria of R2>= 0.6, and average of the certain representatives of the data.
Daily duration curve was plotted for each days of years from 1985 to 2004 verses
percentage of exceedence (P). P = (m/n+1)*100 Where: m is flow rank and n is the
total number of days (i.e. n = 7305 for 20 Years) .Then daily FDC can be plotted as
follows:
100.000
80.000
Daily FDC
60.000
40.000
20.000
0.000
-20.000 0 20 40 60 80 100 120
Percentage of Exceedence
Fig.25.Daily FDC
This flow duration curve can be developed from average flow of each month for each and
its percentage of exceedence. Repeating the above procedure monthly obtained as
follows:
Monthly FDC
140
120
100
Flow (M3/se)
80
60
Monthly FDC
40
20
0
-20 0 20 40 60 80 100 120
Percentage of exceedence (%)
Fig.26.Monthly FDC
This flow duration curve can be developed from average flow of each and its percentage
of exceedence. Repeating the above procedure monthly obtain
ed as follows:
Annual FDC
25
20
Flow M3/sec
15
10
Annual FDC
5
0
0 20 40 60 80 100 120
Percentage exceedence (%)
Fig.27.Annual FDC
To do this average of monthly flow for each month in the range of selected year was
computed and plotted with its corresponding month as follows:
50
40
Flow
30
20
10
0
Jan Feb Mar Apr May Jun July Aug Sep Oct Nov Dec
Fig.28.Long term mean monthly stream flow
To do this first average value was calculated from average annual flow of each Year from
1985 to 2004 variance was calculated for each year to have variation of the flow from the
mean and it can be done as follows:
Inter-annual variability
8
7
6
5
Variance
4
3 the inter-annual variability
2
1
0
1980 1985 1990 1995 2000 2005
-1
Year
Before proceeding to the other analysis, the adequacy of rainfall data series should be
checked and it should be realized. The data series could be considered and adequate if
relative standard error, e10%, where e is the relative standard error.
,
Standard error 3.236% < 10% ok! Therefore the data is reliable and adequate.
3.2 Tests for Outliers
Outliers are data points that depart from the trend of the remaining data.
The detention or retention of these outliers can significantly affect the
magnitude. As shown from the above calculation the station Skew is Less
than -0.4, so based on the following principle the Cs value falls In the 1 st
case therefore it needs checking for lower outliers.
Therefore, the data series has no outlier and all the data series will be used for the frequency
analysis.
The 35 years data is obtained as representative for the analysis after checking the
consistency of the data for higher and lower outlier. The estimated probability of
occurrence of maximum probable rainfall of the project is computed by using different
The one with maximum output is taken for design purpose. The design has adopted 50 years of
design periods.
N - 1 = 34
2 2
Sample Variance S = ∑(X i - X mean) /(N-1) = 173.755378
2 1/2
Sample Standard Deviation S= [∑(X i - X mean) /(N-1)] = 13.1816303
……………… (1)
W = intermediate Variable
T= return period
SY = Standard deviation
Table 6. For the different return periods the maximum probable point rainfall is
calculated as follows
T Pr= Pr^2 1/Pr^2 ln(1/Pr^2) W= KT XT
0.5
1/T (ln(1/Pr^2))
2 0.5 0.25 4 1.38629436 1.177410023 0.213421 57.3989
34 2003 53.8 1.730782276 1.724895513 0.005886763 3.4654E-05 2.04E-07 35 2004 46.4 1.666517981
………………...………………………… (2)
=2.384,
XT=101.9703=93.399mm
Table 8. For the different return periods the maximum probable point rainfall is
calculated as follows
T Pr= Pr^2 1/Pr^2 ln(1/Pr^2) W= KT YT XT
0.5
1/T (ln(1/Pr^2))
2 0.5 0.25 4 1.386294361 1.177410023 0.21342051 1.74720 55.8730
5 2 5
5 0.2 0.04 25 3.218875825 1.794122578 1.1052423 1.84041 69.2494
7 6 4
25 0.04 0.0016 625 6.43775165 2.537272482 2.04115985 1.93823 86.7439
4 9 1
50 0.02 0.0004 2500 7.824046011 2.797149623 2.34834603 1.97034 93.3998
……………..………………………. (3)
Where:-
Yn= Reduced mean in Gumble‟s extreme value distribution for N sample size
Sn= Reduced standard deviation in Gumble‟s extreme value distribution for N sample size
YT (ln (ln (
The maximum probable point rainfall of 50 years return period is 93.88 mm.
…………….………………………... (2.8)
XT=101.9395=87.01238mm
The maximum probable point rainfall of 50 years return period is 87.0124 mm.
Table 12. For the different return periods the maximum probable point rainfall is
calculated as follows.
Kz ZT =Zmean + Kz* XT = 10^ZT
T=2 0 1.724895513 53.07567337
T=5 0.481 1.775169978 59.58953244
T=25 1.751 1.907911289 80.89306461
T=50 2.054 1.939581066 87.01238368
T=100 2.326 1.968010701 92.89892774
T=200 2.576 1.994140881 98.65994764
3.4.5 Pearson Type III Distribution Method.
For the Pearson type III, the same procedure applies like log Pearson type III except that if
Y is the log series it have to be changed in to X variables, and their mean and standard
deviation
XT= Xm + KT = mm
The maximum probable point rainfall for 50 years return period is 84.956mm
KT XT= Xm + KT
T=2 -0.0806 53.52327488
T=5 0.8091 65.25097139
T=25 1.9058 79.70726537
T=50 2.304 84.95619057
T=100 2.676 89.85975705
T=200 3.0281 94.50100909
3.4.6 EXTREME VALUE TYPE-I
The study of extreme hydrologic events involves the selection of a sequence of the large
stores smallest to observations from sets of data. For example, the study of peak flows
uses just the largest flow recorded each year at gauging station out of them any thousands
of values recorded. In fact, water level is usually recorded every 15 minutes, so there are
XT=U+α*YT=48.65+10.2828*3.9.19=48.65+40.123=88.77mm
Where: U=is the mode of the distribution (point of maximum probability density)
α = the parameter to get U S = Standard deviation
The maximum probable point rainfall for 50 years return period is 88.77mm
Table 14 Extreme value type I
S.no. X Xmean Xi - Xmean (Xi - Xmean)2
Time
1 1970 51.8 54.585714 -2.785714286 7.7602041
2 1971 39.8 54.585714 -14.78571429 218.61735
3 1972 50.7 54.585714 -3.885714286 15.098776
4 1973 61.5 54.585714 6.914285714 47.807347
5 1974 52.7 54.585714 -1.885714286 3.5559184
6 1975 61.6 54.585714 7.014285714 49.200204
2
∑(X i - X mean) = 5907.6829
N= 35
N - 1= 34
Sample Variance S2 = ∑(Xi - Xmean)2/(N-1) = 173.75538
Sample Standard Deviation S = [∑(Xi - Xmean)2/(N-1) ]1/2= 13.18163
Table 15.For the different return periods the maximum probable point rainfall is
calculated as follows.
XT=101.9959 = 93.37 mm
The maximum probable point rainfall for 50 years return period is 93.37mm
N-1 34
2 2
Sample Variance S = ∑(Y i - Y mean) /(N-1) = 0.01092458
2 1/2
Sample Standard Deviation S= [∑(Yi - Ymean) /(N-1) ] = 0.104520717
PEARSON
NORMAL
NORMAL
GUMBEL
TYPE II
TYPE II
LOG -
LOG -
EVII
EVI
85.54 93.399 93.85 87.012 84.95619 88.7736295 93.371543
The rain fall obtained by GUMBEL distribution is greater than that of others distribution
so to be safer take GUMBEL distribution, in addition GUMBEL is the most common
used method of distribution. Hence peak daily point rainfall of 50 years return period is
93.85 mm.
3 H1 m 4113
Level of head of main water course at
upper end
4 Level of head of main water course at H2 m 1800
lower end
Qp=0.21*QA/Tp ,Qp=1mm(assumed)
11 12 13 14 15 16
Duratio Daily point Rain Fall Rainfall Area to Point Areal
n Rainfall of Return Profile Profile (from Rainfall Ratio Rainfall
period Of 50 year (from table Appendix A)
below)
34 35 36 37 38
Duration Cumulative Incremental Peak Runoff Time of Time to Time to
beginning peak end
Hr mm mm M3/s Hr Hr Hr
0-1.0 0.663 0.663 4.873 0.000 5.714 15.256
1.0-2.0 0.227 -0.436 -3.203 1.000 6.714 16.256
2.0-3.0 0.015 -0.213 -1.563 2.000 7.714 17.256
3.0-4.0 0.561 0.546 4.014 3.000 8.714 18.256
4.0-5.0 1.765 1.204 8.853 4.000 9.714 19.256
5.0-6.0 5.162 3.397 24.972 5.000 10.714 20.256
6.0-7.0 10.023 4.861 35.729 6.000 11.714 21.256
7.0-8.0 20.035 10.012 73.596 7.000 12.714 22.256
8.0-8.7 41.215 21.180 155.688 8.000 13.714 23.256
For time from 3 to 18.25 Hr.the triangular hydrograph can be done as follows:
For time from 7 to 22.25 Hr. the triangular hydrograph can be done as follows:
2
WeightedCN= 1,591,180/ 20268= 78.5 and CNIII = 90.25, S = 27.44 and for Athe
= 200 Km
For the design of firm power firm discharge can be taken at 95 percentage of exceedencei.e 53.76 m3/se.
P = w Qgh = 0.8*1000*53.76*9.81*15 = 6328.6 KW
The following parameters were used as the starting variables for the hydraulic and structural design of
the weir.
The Computed design flood over the weir section for 50 years return period is =300 m 3/sec
The lowest river bed level 1480 m a.s.l but in our case outlet point is 1800. There for it can
The H.F.L before the construction of the weir taken as 1803 ma.s.l
= 1804.94 –1803.0=1.94 m
Head loss (static case) = crest level – bed level
= 1802.5 – 1800.0 = 2.5m
These are called standard “WES standard spillway shapes”
Table 24 Values of constant K and N
Shape
of U/S K N
face
Vertical 2 1.85
3V: 1H 1.936 1.836
3V: 2 1.939 1.81
H
3V: 3H 1.873 1.776
Bottom width
Bottom width of the weir obtained from its geometry i.e.;
For the U/s portion of the weir
A=Vertical* slope
A = 2.5*1=2.5m
For the vertical portion or first part of the weir.
B= 0.282Hd
B = 0.282*2.44m where Hd =2.44em
B = 0.69m
X 1.776
For the curved portion with equations, Y =
3.74
X =1.55m and y = 0.58m.C=X=1.55m
For the straight sloping surface with slope 1(V):1.5(H) D = Vertical * slope = 1.92* 1.5 = 2.88
m.
Applying Bernoulli‟s equation, h +Hd + ha = y1 + v2/2g, where v1 = q/y1 and q-is discharge
intensity at the weir crest. q= Q/L = 275/30 = 9.2 m3/s/m
For the tail water elevation of given Q = 275 m3/s the corresponding value of tail water depth Y3 is
equal to Y2, y2≈ y3 therefore, tail water elevation is to be considered for the selection of energy
dissipater i.e. provision of apron.
Fi
g 40
Irrigation structures should be designed against scour which occurs due to surface flow.
According to Lacey, the normal depth of scour „R‟ in alluvial soils is given by:
Hence, U/S cutoff depth =River bed level – Bottom level of U/S cutoff
Downstream High flood level =High flood level before construction of the weir
=1803.0 masl
Hence, D/S cutoff depth =River bed level – Bottom level of D/S cutoff
Conclusion: Provide 4m and 5m masonry cutoff having each 50cm thickness at the upstream and
Down stream of the weir respectively with additional of intermediate cutoff 4 m.
P = height of weir
D/S
Total length of d/S protection work = the total length of d/s impervious floor and the d/s pervious floor
and is given by the following formula for weir with crest shutter.
1/ 2 1/ 2
Hs 2
∗q ∗1.91
Lt = 13 = 18*12* 13 = 13.52m = 14m
18 C∗[ ] [ ]
75 75
Length concrete block +launching apron (Length downstream protection) = Lt – Ld = 14m – 11m = 3m
The protection work provided for D/S are D/S concrete block and D/S launching apron.
floor
By taking –ve for front water flow direction oriented key points & +ve for backside oriented key points.
Corrected values
U/S pile
PC = 57.51+1.7+7.6 = 66.81% PD = 71.12%, PE= 2.5 m
D/S pile
PE = 46.69-1.5-9.33 = 35.86 % PD = 31.56 %, PC=0
Intermediate pile
Where,
MR/Mo = 1135.05/497.76 = 2.28, since MR/Mo> 1.5 the weir is stable against overturning.
= 1079.3KN.m
= 1409 KN.m
The wall height is taken as the difference between elevation of high flood level and the riverbed level
Take a foundation depth of 1m Top width = H/7 = 4.5/7 = 0.64 m say 0.7 m Bottom
Pa = ½* KaH2s Ph = ½*H2s
2 Retaining wall
Earth work and Rock
2.1 excavation
2.1.1 Site clearing m2
2.1.2 Earth excavation m3
3 Protection works
Earth work and Rock
3.1 excavation
3.1.1 Site clearing m2
3.1.2 Rock Excavation m3
3.1.3 Earth work Excavation m3
3.2 Concrete m3
3.2.3 C-25 m3
4 Power Canal
4.1 Earth Work Excavation m3
4.2 Concrete m3
4.2.1 C-25 m3
6 Power House
Earth Work Excavation and
6.1 Rock Excavation
6.1.1 Site clearing m2
6.1.2 Earth work excavation m3
6.1.3 Rock excavation m3
6.3 Electromechanical
6.3.1 Turbine (Francis) #
6.3.2 Generator #