Professional Documents
Culture Documents
ADDC Construction Questionaires
ADDC Construction Questionaires
Installation of Cables:
1. What is the main directive factor to be considered while planning underground cable installation?
3- Trail pit works to expose all the services passes and clear the cable route
4- Excavation of the complete route as per ADDC specification following the related safety rules
followed
7- Proper winch machine to be located at the end of each span to complete cable installation
8-Complete other layers (soft sand, cover tiles, backfilling, compaction, warning tape, and final
reinstate backfilling)
2. What is the minimum bending radius of MV Cables described below during installation?
3. What are the main de-rating factors to be consider while planning an underground cable
installation?
2-Soil Temperature
3-Grouping Factor
4-Depth of Cable
4. State possible causes of failure of power cables?
1-Failure of joints
2-Termination failure
ANS: (A)
ANS: (A)
c.) Nothing to do
1- Single Bonding
2-Double Bonding
3-Cross Bonding
Testing of cables:
ANS:
3- HV test = Hipot test: VLF Testing (very low frequency test : apply on each phase 3 V◦ of rms
value on a (0.1 HZ)
4- Sheath Test: DC VOLTAGE applied between the outer-most metallic layer and earth to
identify after-installation damage to the non-metallic outer sheath. The measured value should
be read after application of the voltage for 1 minute. (this test for 22 & 33 KV only)
ANS:
VLF cable testing is a technique for testing of medium voltage cables. Apply VLF to XLPE cables in
a monitored withstand approach to detect potential failures in the cable insulation The tested cable
must withstand a VLF (Very low frequency) AC voltage for a specified testing time without flashover ,
Frequency ranges used are within the range of 0.01 Hz to 0.1 Hz, where frequency selection depends on
the load of the cable. Test voltage levels are calculated using a multiple of the cable's nominal voltage (3
U0). The VLF cable testing time varies from 15 to 60 minutes
ANS:
"VLF operation reduces the power required to load cables which present a capacitive load. Test
sets typically operate at 0.1Hz. The length of cable that can be tested at a given power increases by a
factor of 500 compared to 50Hz with consequent weight and cost savings.
There are several VLF waveforms available. Sine wave testing has some advantages. Research
shows that the faster growth rate of any existing electrical tree with a sine wave waveform gives a
higher probability of finding the defect.”
Additional info: The fundamental difference between AC and DC high voltage testing is the avoidance of
space charge effects.
ANS:
"When DC high voltage is applied to a XLPE cable , the leakage current from the test set is
divided into three component;
Polarization current
Conduction current
Charging current
ANS:
The aluminum is non-magnetic. A magnetic field is produced by the current in a single core
cable. This would induce an electric current in the steel wire, which could cause overheating.
Joint & Termination:
1. What is the air clearance for 11, 22 and 33 kv cables between ph to ph, and ph to ground?
Ph to Ph Ph to Ground
11 KV 120 120
22 KV 220 250
33 KV 320 370
ANS:
ANS:
Down towards Up
Installation of SWGRs:
ANS:
Model
Manufacturer HV,MV
LV
AIS GIS
ABB UniGear series ZX series MNS series
SIEMENS NXAIR SERIES 8DA10,8DB10 , NXPLUS C SERIES SIKUS series , ALPHA series
Prior installation
1- Site visit: visit to the site location to ensure Machinery access (Crane, car crane, trailer, etc...),
workmen access
2- Marking substation as per the approved Equipment layout to ensure correct clearances for
walls/other panels
During installation
1- Lifting panels after unpacking it from the design point for lifting purpose in order to achieve
balance of each equipment
2- Rolling each panel by proper way inside the substation using proper tools (lifter, jacks, steel
rods, etc..) to its end location
3- Consider proper spacing between panels during insertion to give enough space for of bus bar
and copper joint works
4-assembly of bus bars , enclosures ,metal joints, pressure relief if any in addition to any other
related accessories (VT, Arrestors, etc..) considering leveling all the time
5-torquing of all the bolts as per IEC Table unless other mentioned by manufacturer installation
manual
All values subject to minor change according to bus bar design and copper joints type
3-continuity test: by micro ohmmeter to check proper tightening of bus bar, Droppers, bus bars
ANS: (C)
A. KW
B. kVAR
C. KVA
D. Horse power.
ANS: (C)
A. 45°
B. 90°
C. 120°
D. 180°
ANS: (B)
ANS: (C)
5. Equipment installed means equipment assembled and earthed mention how many points for body
earth should do for transformers?
ANS: (B)
A. 1
B. 2
C. 4
D. 6
6. In power transformer (conservator) located in?
ANS: (C)
A. HV bushing side
B. LV bushing side
C. top of trafo side
D. In between HV & LV Cable box
7. Silica gel is provided to suck moistures and humidity and it’s applied on
ANS: (D)
ANS: (B)
A. Off load
B. On load
C. On load and off load
D. None of the above
ANS: (B)
A. ODWF
B. OFAB
C. ONAF
D. ONAN
ANS: (A)
A. Mechanically
B. Electrically
C. All the above
ANS: (D)
A. Cables
B. Bus bars
C. CB’S
D. All the above
ANS: (C)
A. VT
B. CB
C. CB+VT
D. ES
ANS: (B)
ANS: (C)
ANS: (B)
A. Before
B. After
C. during
ANS: (A)
A. SF6
B. AIR
C. VACCUM
D. OIL
1- Conductor
• Prevents the flow of electricity from the energized conductors to the ground or an
adjacent conductor
• Withstands the electrical stresses produced by the alternating voltage
• Withstands superimposed transient voltage stress on the conductor without dielectric
failure causing a short circuit
4- Insulation screen
• Ensures that the electrical field is confined within the polymeric insulation
• Strippable type and bonded type.
5- Copper Screen
6- Filler
7- Binder Tape
• Binds the cores & filler together and separates the cores from the next layer
8- Bedding
9- Armour
You want to add one new cable to a 33KV Switchgear GIS & do the termination works?
How to check that Proper point of Isolation is made?
1- Through the Mimic Diagram (CB Off – Isolator open, CB and Earthing)
2- Built in Voltage indicator to be checked
3- Test socket at plug in termination if it is available
What are the FB types, what's the difference?
What is meaning of isolation?
o Transfer loads.
o Switch off 415V isolator or CB, Lock where possible and display a Caution Notice on the
operating handle.
o Prove that the 11kV cable spouts are dead using a high voltage indicator.
o Lock the 11kV bus bar shutters and hang a Danger Notice through the lock.
o Earth the 11kV cable using a built—in earthing switch or earthing truck. Lock the
operating pushbutton or handle wherever possible and display a Caution Notice on the
truck or switch.
o Close the 11kV cubicle door and if possible lock it. Hang a Caution Notice on the control
switch.