PROJECT NAM BAN-1 HPP

CONTROL PHILOSPHY
PROJECT CODE 1415-05 FOR COOLING WATER
EQUIP. SPEC. No. FC1415-05M0702 SYSTEM

CONTROL PHILOSPHY
FOR
COOLING WATER SYSTEM

NAM BAN-1 HPP (3 x 3.15MW)

DOCUMENT NO.
FC1415-05M0702

CUSTOMER
HUNG HUI CONST. & TRADING JSC-
VIETNAM

A 21/04/2016 DS /AG 3rd UNITS ADDED.


INDEX DATE NAME PARTICULAR
REVISION

Prepared By Date Checked By Date Approved By Date


DS 01.05.2015 OPB 01.05.2015 AG 01.05.2015
Page 1 of 4
PROJECT NAM BAN-1 HPP
CONTROL PHILOSPHY
PROJECT CODE 1415-05 FOR COOLING WATER
EQUIP. SPEC. No. FC1415-05M0702 SYSTEM

SR. No. CONTENTS PAGE NO.


1 Introduction 03
2 Description 03
3 Control System 04

Prepared By Date Checked By Date Approved By Date


DS 01.05.2015 OPB 01.05.2015 AG 01.05.2015
Page 2 of 4
PROJECT NAM BAN-1 HPP
CONTROL PHILOSPHY
PROJECT CODE 1415-05 FOR COOLING WATER
EQUIP. SPEC. No. FC1415-05M0702 SYSTEM

A common Cooling water system is provided to meet cooling water requirement of generator
bearing lub. oil system & shaft seal as pressure requirement of the cooling water system can
be made with available penstock pressure, it is proposed to use the water directly from
penstock. Application, description & scheme are given below. This description is to be read
with drawing No.F3C1415-05M0601

1.0 APPLICATION
Cooling water is required for following purpose.
1.1 Heat Exchanger of Generator Bearing lub. oil system.
1.2 Shaft Seal.

2.0 DESCRIPTION
For applications stated above, pressurized cooling water is required. Water for this purpose is
tapped from penstock of upstream of MIV. A ball valve is provided at the takeoff point of the
penstock and a common header shall be made.

A Globe valves is provided in common header line, which shall be used for regulating the
flow. A pressure gauge shall be provided in common header line for local indication.

1 No. Duplex coarse basket filter (500 micron) is provided in common header line for coarse
filtration of the water. Normally one element of duplex coarse basket filter remains in circuit
and other shall be standby. After duplex coarse basket filter Pressure reducing valves (1
main+1 standby) are provided in the common header line to reduce the inlet pressure
(penstock pressure) to 3.0 - 4.0 bar (system pressure). Isolation valves (Gate type) shall be
provided before and after Pressure reducing valve for isolation purpose during maintenance.
A Pressure relief valve is also provided for the safety of the system in the event of
malfunctioning of pressure reducing valve. A pressure gauge is provided after pressure
reducing valve to indicate the reduced system pressure.

1 No. Duplex fine basket filter (100 micron) is provided for supplying water to Shaft Seal &
Generator Bearing lube oil heat exchange. Normally one element of duplex fine basket filter
remains in circuit and other shall be standby. Duplex filter are basket type & manually change
over, back flashing also can be done by manually operating the back flash valve. A pressure
gauge is provided in line for local indication after fine filter to indicate the system pressure.

Prepared By Date Checked By Date Approved By Date


DS 01.05.2015 OPB 01.05.2015 AG 01.05.2015
Page 3 of 4
PROJECT NAM BAN-1 HPP
CONTROL PHILOSPHY
PROJECT CODE 1415-05 FOR COOLING WATER
EQUIP. SPEC. No. FC1415-05M0702 SYSTEM

After bifurcation line, a Globe valve is provided for regulating the flow each unit. A pressure
gauge and a switch is provided in line for local indication to indicate the unit system pressure
and give low switching contact to control panel in case of low pressure.

1.1 Generator bearing lubrication heat exchanger


The cooling water to generator bearing oil cooler shall be supplied for the cooling of
Lubrication oil. A flow indicator in the outlet line of heat exchanger is provided for the local
indication of flow. Globe valves is provided, which is used for regulating the flow to heat
exchanger. A pressure gauge is also providing to indicate the pressure in the line. The
discharge from the generator-bearing cooler is conveyed to the tailrace.

1.2 Shaft seal


To prevent the entry of operating water in to shaft seal area, filtered water supplied to shaft
sealing arrangement. During normal operational no cooling water is supply to shaft seal
however before starting unit after a long shutdown period; cooling water shall be supplied to
shaft seal for flushing. Globe valve is provided for regulating the flow to shaft seal. A pressure
gauge is provide to indicate the line pressure & pressure switch is provide to give signal in
case of low pressure .A flow indicator with switch is provide for local indication of flow & low
flow signal in the panel. Supplied water shall be partly mixed to operating water and get
drained through shaft seal draining pipe which leads to drainage sump.

3.0 Control System

A suitable control system shall be provided in LT distribution panel which is located in


Control room.
Inlet piping (elbow, tee & valve etc.) of stainless steel (valve casing of carbon steel) outlet
piping shall be of galvanized pipe.

-------------

Prepared By Date Checked By Date Approved By Date


DS 01.05.2015 OPB 01.05.2015 AG 01.05.2015
Page 4 of 4