Professional Documents
Culture Documents
Project Title: ABC Commercial Building Location:: 4.1 Rebar
Project Title: ABC Commercial Building Location:: 4.1 Rebar
3 Excavation volume
1450 cu. m. 863.00 1,251,350.00
1201 cu. m. 718.00 862,318.00
1197 cu. m. 721.00 863,037.00
Sub-total 2,976,705.00
4 Concrete works
4.1 Rebar
4.1.1 Footing 1033 kg 128.00 132,224.00
4.1.2 Columns 1327 kg 116.50 154,601.54
4.1.3 Beam 1172 kg 138.00 161,736.00
4.1.4 Slab 1255 kg 113.00 141,815.00
4.2 Formworks (area)
4.2.1 Footing 54 sq. m. 200.00 10,800.00
4.2.2 Columns 64 sq. m. 273.00 17,472.00
4.2.3 Beam 91 sq. m. 126.00 11,466.00
4.2.4 Slab 67 sq. m. 239.00 16,013.00
4.3 Concrete (volume)
4.3.1 Footing 470 cu. m. 639.00 300,330.00
4.3.2 Columns 418 cu. m. 922.00 385,396.00
4.3.3 Beam 411 cu. m. 667.00 274,137.00
4.3.4 Slab 222 cu. m. 999.00 221,778.00
Sub-total 1,827,768.54
8 Demobilization (lot)
1 lot 516.00 516.00
1 lot 569.00 569.00
1 lot 548.00 548.00
1 lot 673.00 673.00
1 lot 949.00 949.00
Sub-total 3,255.00
B. LABOR No.
Steelman - Fabrication 1
Steelman - Installation 1
Helper 4
C. EQUIPMENT No.
Bar Bending Machine 1
% (Direct Cost)
Indirect Cost % (Direct Cost)
% (Direct Cost+OCM+Profit)
61 420 25620.00
50 229 11450.00
9 90 810.00
1 2228.5 2228.50
Subtotal 40108.50
Material Unit Cost 50.14