Procurement and Contracts - March 2008
Procurement and Contracts - March 2008
Procurement and Contracts - March 2008
(D13XN Dubai)
Term 2 - 2007/08
Date: Wednesday 12 March 2008 Time: 09:30-11:30
Time: 13:30-15:30 (Dubai)
Course(s)
Attached:
Supplied:
Heriot-Watt University D13PN2 Procurement and Contracts - Term 2 - 2007/08
Section A
(b) Evaluate any problems that may be encountered when partnering and
suggest how they can be overcome.
(11 marks)
Q3 Discuss the factors that influence the selection of a suitable procurement path.
(33 marks)
Page 2 of 3
Heriot-Watt University D13PN2 Procurement and Contracts - Term 2 - 2007/08
Section B
Advise the Contractor on its contractual rights in this situation. Describe the
actions it must take to ensure it complies with the Contract when exercising
these rights.
(33 marks)
(b) A contractor and employer forming a new contract using JCT05 SBC/Q
require the right to refer disputes to arbitration to be available. Describe how
the standard JCT05 SBC/Q contract form must be edited to achieve this and
where any additional information should be inserted.
(10 marks)
(b) Describe how JCT05 SBC/Q can be used to grant rights to a third party in
accordance with The Contracts (Rights of Third Parties) Act 1999 or by using
Collateral Warranties. Identify the specific parts of the JCT05 SBC/Q contract
that are used to do this.
(20 marks)
End of Paper
Page 3 of 3