Professional Documents
Culture Documents
Cost Variance Is
Cost Variance Is
Cost variance is *
0/1
earned value – planned value
Correct answer
earned value – actual cost
2. CPI is 1.2, SPI is 1.1. Four months later CPI is.91 and SPI is .86. The most
likely reason for this change is *
0/1
The WBS was inaccurate
As work packages were being executed, discovery on critical path activities caused estimates to
change drastically on several of the work packages
The project manager has not been keeping track of variances on the project to implement
corrections
Several key stakeholders insisted on a last-minute scope change
Correct answer
As work packages were being executed, discovery on critical path activities caused estimates to
change drastically on several of the work packages
No correct answers
4. You are three months into a six month project. Assume the budget burn rate is
constant. The budget at completion (BAC) is $120,000. AC = $65,000. The SPI
= 1.2. What is the CPI of this project? (Round to 2 decimal places) *
0/1
1.25
1.32
It cannot be determined from the information given
1.11
Correct answer
1.11
5. You are three months into a six month project. Assume the budget burn rate is
constant. The budget at completion (BAC) is $120,000. AC = $65,000. The SPI
= 1.2. What is the CPI of this project? (Round to 2 decimal places) *
0/1
1.32
Correct answer
1.11
No correct answers
7. Cost estimating techniques which estimate the cost of individual work packages
or individual schedule activities with the lowest level of detail.This detailed cost
is then summarized or “rolled up” to higher levels for reporting and tracking
purposes is called as: *
0/1
Analogous estimating
Bottom up estimating
None of the above
Parametric estimating
Correct answer
Bottom up estimating
The schedule
Clarifying the requirements collection process
Managing stakeholder expectations
Correct answer
The schedule
Correct answer
Cost overrun
Use value
Reliability
Cost
Correct answer
Use value
A pen having a cost of Rs.13 caters the utility worth Rs.15 of the customer after selling
it in the market. Calculate the value of the pen. *
0/1
.90
.91
1.11
1.15
Correct answer
1.15
Nowadays, we can observe that in online shopping we can exchange our old product
withthe new ones by a reduction in the price of the new ones and we get the new
product at lower prices.Which type of value does this show?
0/1
Use Value
Esteem Value
Cost Value
Exchange Value
No, the answer is incor
Correct answer
Exchange Value
False
Other:
Method of manufacturing
Material used
All of the above
Correct answer
All of the above
Old products
Future products
New and old products
Correct answer
New and old products
Preventive
Continuous
None of the above
Value analysis should be applied when the following symptom(s) is (are) present *
0/1
Rate of return on investment is reducing
Correct answer
All of the above
Value analysis reduces cost and increases the quality of a product first providing maximum
satisfaction to customers.
Value analysis involves an innovative exercise
Value analysis reduces the cost through research in alternative materials, simplifying the process
and effective services.
Correct answer
Value analysis involves an innovative exercise
Spiritual value
Esteem value
Exchange value
Correct answer
Spiritual value