مواد٦

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 85

Production Activity Control

Chapter 6
“The time comes when plans must
be put into action”
Production Activity Control
◼ Responsible for executing the:
◼ Master Production Schedule (MPS)
◼ Materials Requirements Plan (MRP)
◼ At the same time:
◼ Make good use of labor, machines and
materials
◼ Minimize work-in-process inventory
◼ Maintain customer service

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Production Activity Control
◼ The material requirements plan authorizes PAC:
◼ Release work orders

◼ Control work orders to complete on time

◼ Control the flow of work

◼ Through manufacturing

◼ Carrying out the plan to completion

◼ Manage day-to-day activity and provide support

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Production
Planning

Master
Planning Production
Scheduling

Material
Requirements
Planning
Input/
Implement Output
and Production Control
Control Purchasing Activity
Control
Operation
Figure 6.1 Sequencing
Priority planning and production activity control
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Planning

◼ To meet delivery dates


◼ Ensure:
◼ The required materials, tooling, personnel
and information
◼ Schedule:
◼ Start and completion times for each shop
order
◼ Develop load profiles for the work centres`
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Implementation
◼ Gather information needed to make the
product
◼ Release orders to the shop floor
◼ MRP authorized

“Dispatching”

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Control
◼ The production order has been released
◼ Is corrective action necessary?
◼ Rank the orders by priority
◼ Establish a dispatch list
◼ Track performance to planned schedule
◼ Replan, reschedule, adjust capacity
◼ Monitor and control WIP, lead times, cues
◼ Report work center effciency, scrap, times
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
PRODUCTION ACTIVITY CONTROL

PLAN
Schedule
Replan

EXECUTE CONTROL
Work Compare
Authorization Decide

Dispatch Feedback

MANUFACTURING OPERATIONS
Figure 6.2 Production control system
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Manufacturing Systems
◼ Flow manufacturing
◼ Intermittent manufacturing
◼ Project manufacturing

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Flow Manufacturing
◼ High volume
◼ Standard products
◼ Repetitive /cars
◼ Continuous/gasoline

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Flow Manufacturing
◼ Routings are fixed
◼ Work centers arranged according to the
routing
◼ Dedicated to a limited range of products
◼ specifically designed equipment
◼ Use of mechanical transfer devices
◼ Low WIP and throughput times
◼ Capacity is fixed by the line
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Flow Manufacturing
◼ Production Activity Control
◼ Plans the flow of work
◼ Planned schedule of materials to the line
◼ Implementation and control are relatively
simple

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Intermittent Manufacturing
◼ In the intermittent production system,
goods are produced based on customer's
orders. These goods are produced on a
small scale.
◼ Many variations in:
◼ product design
◼ process requirements
◼ order quantities

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Intermittent Manufacturing
◼ Flow of work is varied - work flow not
balanced
◼ Machinery and workers must be flexible
◼ Usually grouped according to function
◼ Throughput times are generally long
◼ Capacity required depends on product
mix

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Intermittent Manufacturing
◼ Production Activity Control is complex:
◼ number of products made
◼ variety of routings
◼ scheduling problems
◼ PAC is a major activity
◼ Controlled through shop orders for each
batch

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Intermittent production system.

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Project Manufacturing
◼ One or a small number of units
◼ Usually in one place
◼ Close coordination between:
◼ Manufacturing, Marketing, Purchasing,
Engineering
◼ Examples:
◼ Shipbuilding
◼ House construction
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Data Requirements
◼ Need to know:
◼ What and how much to produce
◼ When parts are needed
◼ What operations and times are required
◼ Work center capacities
◼ Organized into databases:
◼ Planning or Control

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Planning Files
◼ Item master file
◼ Product structure file
◼ Routing file
◼ Work center master file

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Item Master File
◼ Part number ◼ Quantity on hand

◼ Part description ◼ Quantity available


◼ Allocated quantity
◼ Manufacturing lead
◼ already assigned to
time other work orders
◼ Lot size quantity ◼ On-order quantities

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Product Structure File
◼ Bill of material file
◼ A listing of single-level components to
make an assembly
◼ Forms a basis for a ‘pick list’

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Routing File
◼ Step-by-step instructions on how to
make the product
◼ Operations and their sequence
◼ Operation descriptions (brief)
◼ Equipment tools and accessories
◼ Operation setup times
◼ Operation run times
◼ Lead times for each operation
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Work Center Master File
◼ Details on each work center
◼ Work center number
◼ Capacity
◼ Shifts, machine hours and labor hours per
week
◼ Efficiency
◼ Utilization
◼ Average queue time
◼ Alternative work centers
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Control Files
◼ Shop order master file
◼ Summarized data on each shop order

◼ Shop order detail file


◼ Current record of each operation

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Shop Order Master File
◼ Shop order number ◼ Due date
◼ Order quantity ◼ Priority
◼ Quantity completed ◼ Balance due
◼ Quantity scrapped ◼ Cost information
◼ Quantity of material
issued to the order

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Shop Order Detail File
◼ Operation number
◼ Setup hours planned and actual
◼ Run hours planned and actual
◼ Quantity complete (at this operation)
◼ Quantity scrapped (at this operation)
◼ Lead time remaining

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Order Preparation
◼ A check for available:
◼ Tooling
◼ Materials
◼ Capacity - when it is needed

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Scheduling
◼ To meet delivery dates
◼ Make the best use of resources
◼ Need information on:
◼ Routing
◼ Capacity
◼ Competing jobs
◼ manufacturing lead times

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Manufacturing Lead Time
◼ Queue - time spent waiting before
operation
◼ Setup - time to prepare the work center
◼ Run - time to make the product
◼ Wait - time spent after the operation
◼ Move - transit time between work
centers
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Manufacturing Lead Time
Queue Setup Run Wait

Move Need a lift truck here

Queue Setup Run Wait Move

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Cycle Time
◼ “The length of time from when material
enters a production facility until it exits”
◼ APICS Dictionary 12th Edition

◼ Synonym - throughput time

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem
◼ An order for 100 of a product is processed on work
centers A and B. The setup time on A is 30 minutes,
and run time is 10 minutes per piece. The setup time
on B is 50 minutes, and the run time is 5 minutes per
piece. Wait time between the two operations is 4
hours. The move time between A and B is 10
minutes. Wait time after operation B is 4 hours, and
the move time into stores is 15 minutes. There is no
queue at either workstation. Calculate the total
manufacturing lead time for the order.

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem
Work Center A operation time = 30 + (100 x 10) = 1030 minutes
Wait time = 240 minutes
Move time from A to B = 10 minutes
Work Center B operation time = 50 + (100 x 5) = 550 minutes
Wait time = 240 minutes
Move time from B to stores = 15 minutes
Total manufacturing lead time = 2085minutes

= 34 hours, 45 minutes

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Scheduling Techniques
◼ Forward Scheduling ◼ Backward Scheduling
◼ Start when the order ◼ Uses MRP logic
is received ◼ Schedule last
◼ May finish early operation to be
◼ Used to determine complete on the due
the earliest date
completion date ◼ Schedule previous
◼ Determine promise operations back from
dates the last operation
◼ Builds inventory ◼ Reduces inventory

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Forward and Backward Scheduling:
Infinite Load
Order Received Due Date
1 2 3 4 5 6 7 8 9

Forward Scheduling
Material 1st 2nd 3rd
Ordered Operation Operation Operation

Backward Scheduling

Material 1st 2nd 3rd


Ordered Operation Operation Operation

Figure 6.4 Infinite load profile


Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Infinite loading

• The assumption is made that the


workstations on which operations
1, 2, and 3 are done have capacity
available when required. It does
not consider the existence of other
shop orders competing for capacity
at these work centers as shown in
Figure 6.5
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Infinite Load Profile
Capacity Overload

Capacity

Capacity Underload
Figure 6.5 Infinite load profile
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Finite loading

assumes there is a defined limit to


available capacity at any workstation. If
there is not enough capacity available at
a workstation because of other shop
orders, the order has to be scheduled in
a different time period. Figure 6.6
illustrates the condition.

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Finite Load Profile

Capacity

Smoothed Load

Figure 6.7 Finite load profile


Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Forward and Backward Scheduling:
Finite Load
Order Recieved Due Date
1 2 3 4 5 6 7 8 9

Forward Scheduling
Material 1st 2nd 3rd
Ordered Operation Operation Operation

Backward Scheduling

Material 1st 2nd 3rd


Ordered Operation Operation Operation

Figure 6.6 Forward and Backward scheduling: finite load


Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem
Backward Scheduling
◼ A company has an order for 50 brand X to be
delivered on day 100
◼ Only one machine is available for each operation
◼ The factory works one 8 hour shift 5 days a week
◼ The parts move in one lot of 50

Part Operation Time


X A 10 5
20 3
B 10 10
A B X Assembly 5

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem Answer

Part A
OP 10 OP 20
X
Assembly
Part B
OP 10

85 90 95 100
Working Days
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Operation Overlapping
◼ The next operation is allowed to begin
before the entire lot is completed
◼ Reduces the manufacturing lead time
◼ Order is divided into at least two
transfer lots
Operation A
SU Lot 1 Lot 2
T=Transfer Time

SU Lot 1 Lot 2
Operation B
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Operation Overlapping
◼ Costs involved:
◼ Handling costs between work centers
◼ May increase queue and wait for other
orders
◼ Idle time if the second batch doesn’t
arrive in time

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
EXAMPLE PROBLEM
◼ Refer to the data given in the example
problem in the section on manufacturing lead
time. It is decided to overlap operations A
and B by splitting the lot of 100 into two lots
of 70 and 30. Wait time between A and B and
between B and stores is eliminated. The move
times remain the same. Setup on operation B
cannot start until the first batch arrives.
Calculate the manufacturing lead time. How
much time has been saved?
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Answer

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Size of the Optimal Transfer
Batch
SUA = Set up time operation A
SUB = Set up time operation B
RTA = Run time per piece operation A
RTB = Run time per piece operation B
QT = Total order size
T1 = size of the first transfer batch

T1 = QT x RTA - SUB T2 = QT - T1
RTA + RTB

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Size of the Transfer Batch
◼ If the second operation is slower than the
first make the first transfer batch small
◼ i.e. get the slower machine started early

◼ If the second machine is faster than the first


make the first transfer batch large
◼ i.e. the second machine will be able to catch up

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem
◼ A batch of 100 whatzits is to be run
through 2 operations, A and B. Times
for the operations are as follows:

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem
Operation A
0 30 730 1,000 (Minutes)

30 70 x 10 = 700 30 x 10 = 300

T T Transfer Time
1,010

50 70 x 5 = 350 30x5 = 150

740 790 1140 1290

Operation B
Stores 1300
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Operation Splitting
◼ Reduces manufacturing lead time
◼ The order is split into at least two lots
◼ Similar machines are run simultaneously

◼ Setup time is low compared to run time


◼ Operators can run more than one
machine
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Operation Splitting
One Machine
SU Run

Two Machine Operation Splitting


SU Run
Reduction in
Lead Time

SU Run

Figure 6.9 Operation splitting


Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Load Leveling
◼ Load Report
◼ Tells PAC the current and upcoming
load on a work center
◼ Based on standard hours of operation
for each order

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Load Report
Work Center: 10 Available Time: 120 Hours per week
Description: Lathes Efficiency: 115%
Number of Machines: 3 Utilization 80%
Rated Capacity: 110 standard hours / wk

Week 18 19 20 21 22 23 Total
Released
80 30 0 0 315
Load 105 100
60 80 130 80 350
Planned Load
Total Load 105 100 140 110 130 80 665
Rated
110 110 110 110 110 110 660
Capacity
(Over) /
Under 5 10 (30) 0 (20) 30 (5)
Capacity

Figure 6.10 Work centre load report


Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Scheduling Bottlenecks
◼ Some workstations are overloaded and
some are underloaded; mainly in
intermittent manufacturing.

◼ Bottlenecks
◼ “a facility, function, department, or
resource whose capacity is equal to or less
than the demand put upon it.”
Introduction to Materials Management, 7th Edition
APICs Dictionary 12th Edition
© 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Throughput
◼ The total volume of product passing
through a facility
◼ Bottlenecks control the throughput
◼ Work centers feeding bottlenecks will build
inventory
◼ Work Centers fed by bottlenecks have their
throughput controlled by the bottleneck

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem -
Bottlenecks
◼ Wagon Wheel Assembly - 1200 sets (2) per week
◼ Handle Assembly - 450 per week

◼ Final Assembly - 550 wagons per week

a. What is the capacity of the factory?


b. What limits the throughput of the factory?
c. How many wheel assemblies should be made?
d. What is the utilization of the wheel assembly?
e. What happens if utilization is 100%

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem -
Bottlenecks

Wagon:
Body
Wheel sets (2)
Handle

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem -
Bottlenecks
a. 450 units per week
b. Throughput is limited by the handle
assembly operation
c. 900 wheel assemblies per week
d. Utilization of the wheel assemblies =
900 ÷ 1200 = 75%
e. Excess inventory of wheel assemblies
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Bottleneck Principles (7)
1. Utilization of a non-bottleneck resource is not
determined by its potential, but by another constraint
in the system.
2. Utilization of a non-bottleneck 100% of the time does
not produce 100% utilization.
3. The capacity of the system depends on the capacity
of the bottleneck.
4. Time saved at a non-bottleneck saves the system
nothing.
5. Capacity and priority must be considered together.
6. Loads can and should be split.
7. Focus should be on balancing the flow in the shop.
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Managing Bottlenecks
1. Establish a time buffer before each
bottleneck.
2. Control the rate of material feeding the
bottleneck.
3. Do everything to provide the bottleneck with
capacity.
4. Adjust loads.
5. Change the schedule.
Back schedule before the bottleneck; forward
schedule after the bottleneck.
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Theory of Constraints continued

2. Exploit the constraint. (idle time?)


3. Subordinate everything to the
constraint.
4. Elevate the constraint.
5. Once the constraint is a constraint no-
longer, find the new one and repeat the
steps.
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Drum-Buffer-Rope
◼ Drum - pace of production set by the
constraint
◼ Buffer - inventory established before
the constraint
◼ Rope - coordinated release of material

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
EXAMPLE PROBLEM
◼ Parent X requires 1 each of component Y
and Z. Both Y and Z are processed on work
center 20 which has an available capacity
of 40 hours. The setup time for component
Y is 1 hour and the run time 0.3 hour per
piece. For component Z, setup time is 2
hours and the run time is 0.20 hour per
piece. Calculate the number of Ys and Zs
that can be produced.
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem
◼ To find the constraint we set the load equal to the
capacity and solve for the number of units to produce
that amount of load.
◼ Since the Bill of Material can not change then the
number of each component can be expressed in
terms of the end item.
◼ This first example has the number of Y’s equal to the
number of X’s and the number of Z’s the same as
well.
◼ It would be wasteful to produce more than this ratio.

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
X

Example Problem Y Z

Work Center 20: Capacity = 40 hours per week


Y: Setup = 1 hour, Run Time = .3 hours per piece
Z: Setup = 2 hours, Run Time = .2 hours per piece
Calculate Ys and Zs
Let x = the number of Y’s and Z’s to produce
TimeY +TimeZ=40 H
1 + 0.3x + 2 + .2x = 40 hours
0.5x = 37 hours
x = 74 (you can produce 74 Y’s and 74 Z’s)

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
A
B C(2)

Example Problem
Item Setup (hrs) Run Time (hrs/unit)

A 2 .1
B 2 .2
C 1 .3

Work Station 1 makes A’s and B’s; Capacity = 40 hrs/week


Work Station 2 makes C’s; Capacity = 40 hrs/week

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem
The number of B’s should equal the number of
A’s produced and the load in workstation 1
can be expressed as the number of A’s
produced.
2 hrs + .1×A hrs + 2 hrs + .2×A hrs = 40 hrs
.3×A hrs = 36 hrs
A = 120
Workstation 1 has the capacity to make 120 A’s
and 120 B’s
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem
Workstation 2 (there are 2 C’s in every A)

1 hr + 2×.3×A hrs = 40 hrs


.6 A = 39
A = 65

Workstation 2 can support the number of C’s to


make 65 A’s. (130 C’s)
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Implementation
◼ Issuing shop orders to manufacturing
◼ Which have a good chance of being
completed on time
◼ Orders which have the:
◼ tooling
◼ material
◼ capacity

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Shop Order Information
◼ Order number, ◼ Material Issue
description Tickets
◼ Engineering
◼ Tool Requisitions
Drawings

◼ Bills of Material ◼ Job Tickets

◼ Route Sheets ◼ Move Tickets

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Figure 6.12 Review Order
Order Release
Process Check Tooling
and Material
Availability

No
Okay? Resolve
Yes
Check Capacity
Requirements
and Availability

No
Okay? Resolve
or
Yes Reschedule
Release
Order
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Control
◼ Control the work going into and out of a
work center: Input/output control

◼ Set the priority of orders to run at each


work center

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Input / Output Control
Input Rate
Control

Queue
(Load, WIP)

Output Rate
Control
Figure 6.13
Input/output control

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Work Center: 201
Capacity per period: 40 standard hours

Period 1 2 3 4 5 Total
Planned Input 38 32 36 40 44 190
Actual Input 34 32 32 42 40 180
Cumulative Variance -4 -4 -8 -6 -10 -10

Planned Output 40 40 40 40 40 200


Actual Output 32 36 44 44 36 192
Cumulative Variance -8 -12 -8 -4 -8 -8

Planned Backlog 32 30 22 18 18 22
Actual Backlog 32 34 30 18 16 20

Figure 6.14 Input/output report


Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Cumulative Variance
◼ The difference between the total planned for a
given period and the actual total for that period

◼ Cumulative variance
= previous cumul variance + actual - planned

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Work Center: 201
Capacity per period: 40 standard hours

Period 1 2 3 4 5 Total
Planned Input 38 32 36 40 44 190
Actual Input 34 32 32 42 40 180
Cumulative Variance -4 -4 -8 -6 -10 -10

Planned Output 40 40 40 40 40 200


Actual Output 32 36 44 44 36 192
Cumulative Variance -8 -12 -8 -4 -8 -8

Planned Backlog 32 30 22 18 18 22
Actual Backlog 32 34 30 18 16 20

Cumulative variance week 3 = -4 + 32 -36 = -8

Figure 6.14 Input/output report


Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Example Problem:
Input/Output
Week 1 2

Planned Input 45 40

Actual Input 42 46

Cumulative Variance

Planned Output 40 40

Actual Output 42 44

Cumulative Variance

Planned Backlog 30

Actual Backlog 30

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Operations Sequencing
◼ “a technique for short term planning of actual
jobs to be run in each work center based on
capacities and priorities.”
APICS Dictionary 12th Edition

◼ Priority: The sequence in which jobs should run at a


work center

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Dispatching
◼ Selecting and sequencing jobs to be run
at a work center
◼ Dispatch list
◼ Plant, department, work center
◼ Part number, shop order number, operation
number and description
◼ Standard hours
◼ Priority information
◼ Jobs coming to the work center

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Dispatching Rules
◼ FCFS - First come, first served
◼ EDD - Earliest job due date
◼ ODD - Earliest operation due date
◼ SPT - Shortest processing time
◼ CR - Critical ratio

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Critical Ratio
CR= due date - present date CR<1 Behind
lead time remaining Schedule

CR=1 On Schedule
= actual time remaining
lead time remaining CR>1 Ahead of
Schedule

CR<0 Already late

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Sequencing Rules
Process Sequencing Rule
Arrival Due Operation
Job Time
Date Date Due Date FCFS EDD ODD SPT
(days)
A 4 223 245 233 2 4 1 3
B 1 224 242 239 3 2 2 1
C 5 231 240 240 4 1 3 4
D 2 219 243 243 1 3 4 2

Figure 6.16 Application of sequencing rules

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Production Reporting
◼ Feedback of what is actually happening on
the shop floor
◼ Needed for management decisions

on-hand on-order
job status shortages
scrap material shortages

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.
Production Activity Control
Summary
◼ Converting MRP plans into action
◼ Reporting results
◼ Revising plans
◼ Need:
◼ detailed and current schedules and priorities
◼ Results:
◼ on-time deliveries, well utilized labor, and
equipment, minimum inventory levels

Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman and Clive All Rights Reserved.

You might also like