Professional Documents
Culture Documents
Project: Contract Ref: Project No: Location: Drawing Ref: Rfi No: Descrption: VRF System Installation Inspection Checklist
Project: Contract Ref: Project No: Location: Drawing Ref: Rfi No: Descrption: VRF System Installation Inspection Checklist
CONTRACT REF:
PROJECT NO:
LOCATION:
RFI NO:
DRAWING REF :
1 Unit received at site is in good condition and no any physical damage found
4 Units are kept in secure indoor unit location until it is ready for installation
12 Power supply connection to outdoor units are done and checked for terminal tightness
14 Suction and liquid line shut off valves checked and found to be fully closed before vacuuming
the pipe line.
15 Suction and liquid line shut off valve fully opened after completing the vacuuming
REMARKS:-
Signature : Signature :
Date : Date :
RFI NO LOCATION
REPORT NO. DATE
DRAWING NO.
DESCRIPTION
INSPECTION RESULT
ITEMS TO CHECK
Accepted Rejected
UNDERGROUN DUCTS
Check that clearance is maintained between ducts and are coordinated from other services.
4
5 Check the sealing of ducts and joints to prevent ingress of concrete during pouring.
2 Check cable size & type shall be as per approved cable schedule.
3 Check cables are new and undamaged.
4 Inspect the containment and ensure there are no sharp edges and burrs.
5 Check the installation/routing of containment as per approved drawings prior to laying of cables
9 Cable glanding, termination and grounding completed as per approved drawings and details.
10 Check all terminals and connectors are completed and tightened as required.
11 Identification and ferruling completed as per approved details.
Check the installation of cable tiles, warning tapes, fittings & accessories is as per specification,
12 material submittal & latest approved shop drawings.
REMARKS:-