Professional Documents
Culture Documents
Ministry of Housing: Buqayq Project
Ministry of Housing: Buqayq Project
Ministry of Housing: Buqayq Project
Ministry of Housing
BUQAYQ PROJECT
ASPHALT WORK
Revision Record
Al Jaber Contracting-ajc
Document No:MS-C-05
Method Statement for Construction
Rev: 00
of
Date: 05/11/2017
Asphalt Work
Page 2 of 12
This cover page is a record for all the revisions of the document identified above by
number and title. All previous cover pages are hereby superseded and are to be destroyed
Name
00 Designation
Signature
COMMENTS
INDEX
Al Jaber Contracting-ajc
Document No:MS-C-05
Method Statement for Construction
Rev: 00
of
Date: 05/11/2017
Asphalt Work
Page 3 of 12
1.0 Purpose
2.0 Scope
3.0 Legislation and Code of Practice
4.0 References
5.0 Definitions and Abbreviations
6.0 Resources
6.1 Materials and Their Approval
6.2 Subcontractor Approval
6.3 Shop Drawings Approval
6.4 Equipment
6.5 Human Resources
7.0 Detailed Construction Sequence ( Methodology )
1.0 PURPOSE
Al Jaber Contracting-ajc
Document No:MS-C-05
Method Statement for Construction
Rev: 00
of
Date: 05/11/2017
Asphalt Work
Page 4 of 12
The purpose of this method statement defines the procedure for the construction of
asphaltic works in the whole area Buqayq project.
2.0 SCOPE
This method statement is applicable for the construction of asphaltic works to execute and
test as per project specifications, Contract Documents, Shop drawings For Buqayq project.
All the works related to construction of Asphaltic works shall comply with:
Technical specification of project volune 2 section (02510).
All execution activity shall comply with legislation and guidelines under;
Technical specification of project volune 2 section (02510).
4.0 REFERENCES
Al Jaber Contracting-ajc
Document No:MS-C-05
Method Statement for Construction
Rev: 00
of
Date: 05/11/2017
Asphalt Work
Page 5 of 12
5.1 ABBRIVIATIONS
5.2 DEFINITIONS
Accepted
Accepted in writing by the Engineer (or by the Employer where appropriate) as meeting the
requirements of the Contract Documents and of any authorized variations thereto. "Acceptance"
means accepted in writing as aforesaid. "Acceptable" means acceptable to the Engineer as aforesaid.
Addendum/notice
Amendment of or revision to any of the Contract Documents issued to tenderers, and which is
deemed to form part of the Contract Documents.
Backfill
Al Jaber Contracting-ajc
Document No:MS-C-05
Method Statement for Construction
Rev: 00
of
Date: 05/11/2017
Asphalt Work
Page 6 of 12
The constructed works around structures, like bridges, culverts, retaining walls and around
and above different utilities.
Change Order
A written order addressed to the Contractor and approved by the Ministry about important
and influence change in some items and works in the project or the written instruction
ordered to the Contractor issued by the Engineer and approved by the Ministry, to require
a construction of additional works according to the items of the contract.
Equipment
All machines and tools required for their operation and maintenance, devices and systems
required for the construction of contract works in a technically acceptable method and to
perform them properly within contract period.
Pre-construction meeting
A meeting between the Engineer and the Contractor and his representatives, to discuss
work plan, progress and contract requirements prior start of the work.
Site
Lands and places handed on which the works shall be executed either above or below or in
it, or any lands offered by the Ministry as areas for project construction specified in the
contract.
Specification Limits
Lower and upper limits which should be achieved on the constructed works using the best
available materials and construction methods.
Work Drawings
A set of drawings and figures for work construction that includes plans of temporary and
permanent structures , profiles, cross sections, typical models, detailed sections together
with supplementary and any additional plans showing work site, type, dimensions and
details, submitted by the Ministry/Engineer or prepared by to the Contractor and approved
by the Ministry or its Engineer.
6.0 RESOURCES:
Al Jaber Contracting-ajc
Document No:MS-C-05
Method Statement for Construction
Rev: 00
of
Date: 05/11/2017
Asphalt Work
Page 7 of 12
Approved material in accordance with relevant submittals shall be ordered well in advance
in order to ensure delivery prior start of work.
Asphalt Materials:
Prime coat and tack coat used for Asphalt works, (Technical specification of project volune
2 section (02510) part 2 (5-3).
1. No sub-contractor for this activity, AJC shall execute all asphalt works.
All the related design and shop drawings are already submitted to the client and approved.
6.4 EQUIPMENT
AJC shall make assure that all the machine and equipment’s required for Asphalt Works are
available in excellent working condition .The equipment shall be but not limited to
Mixing Plants
Asphalt Paving Machine
Steel and Tyre Rollers
dump trucks
Asphalt tankers
Al Jaber Contracting-ajc
Document No:MS-C-05
Method Statement for Construction
Rev: 00
of
Date: 05/11/2017
Asphalt Work
Page 8 of 12
Hand tools include rakes, shovels, hand compactors, leveling and smoothing tools, cleaning tools
and all other tools that may be needed by the Contractor to complete the work.
Overall Operation crew for construction and Inspection works of asphalt works shall be formed as
follows:
project Manager
Material Engineer
Steel Roller Operator
Tire Roller Operator
Mechanic
Tank Driver
Foremen
Technicians
Quality Engineer
HSE Officers
Surveyors
Survey Helpers
Flagmen / Banks men
Common Laborers
The number of personnel will be determined according to the work progress and
conditions on site.
Al Jaber Contracting-ajc
Document No:MS-C-05
Method Statement for Construction
Rev: 00
of
Date: 05/11/2017
Asphalt Work
Page 9 of 12
Al Jaber Contracting-ajc
Document No:MS-C-05
Method Statement for Construction
Rev: 00
of
Date: 05/11/2017
Asphalt Work
Page 10 of 12
Consideration:
The feed trucks shall be organized in such a way as to ensure a continuous
supply of mix.
The feed trucks shall maneuver in such a way not to damage the road base
layer.
The paver hopper shall be all time third full and the wings shall be open all time
while paving.
The paver speed should be as constant as possible without frequent stops.
As soon as the haul truck arrives at the job site, the QC inspector shall check
that the asphalt delivered shall be in a satisfactory condition (free from cold
lumps).
The mix temperature should be checked in the truck before hauling asphalt into
the paver.
Route to be paved is defined and a steering guide should help the operator to
follow the route.
The paver should be positioned properly on to the road. It should maintain speed
as to obtain as constant supply of the mix from the feed trucks as possible.
Spreading shall not be performed during unsuitable weather conditions.
b) Handwork
In situations where the paver cannot place it adequately and/or in areas not accessible to the roller,
the mixture shall be placed by a bobcat and leveled with handles rakes and shovels then thoroughly
compacted using a small steel roller followed by a Pneumatic Tired Roller where accessible.
The compaction shall start as soon as possible. The QC inspector has to ensure that the placement
Al Jaber Contracting-ajc
Document No:MS-C-05
Method Statement for Construction
Rev: 00
of
Date: 05/11/2017
Asphalt Work
Page 11 of 12
occurs within the specified temperature range (not less than 135 d c). All rolling shall be completed
before the temperature of the mixture drops below ninety (90) degrees Celsius. The breakdown
rolling shall be carried out using vibratory steel-wheel rollers operating in vibratory mode
intermediate rolling shall follow the breakdown rolling as closely as possible and shall be carried
out using pneumatic tire rollers (PTRs). Finish rolling shall be carried out while the material is still
warm enough for the removal of roller marks. It shall be carried out using steel-wheel rollers in
static mode.
The weigth of steel roller shall be 9 tonnes and Pnematic Tire Roller shall be 14 tonnes and
minimum of 4 passes shall be done.
Roller shall be started and reversed gently and slowly but at uniform speed to achieve the best
result. Commenced with a steel wheel roller along the lower edge of the area to be rolled and be
continued until the edge is thoroughly compacted, after which the roller shall be gradually
advanced to the crown point, both sides being rolled in a like manner. Near retaining walls, curbs,
gullies or manholes asphalt shall be placed manually ensuring a smooth texture then compacted
with a small steel roller and a PTR. Sufficient compaction equipment shall be provided and
compaction shall continue until each lot of asphaltic concrete pavement is compacted to an in-place
density within ninety one to ninety-five (91-95) percent of the theoretical maximum density
determined from AASHTO T-209 for all layers calculated based on three to five (3-5) percent air
voids, and the compaction level of ninety-six (96) percent of Marshall density. At calculation the
quality index required for statistical evaluation, this range shall be widened by one (±1) percent in
both sides. Near retaining walls, curbs , gullies or manholes asphalt shall be placed manually
ensuring a smooth texture then compacted with a small steel roller and a PTR.
7.7 Joints:
Whenever it is possible, longitudinal and transverse joints shall be held to the minimum practical
number. However, when these joints are used, following requirements shall be fulfilled:
All the construction joints shall be staggered and not overlapping.
All cutting works for asphalt shall be made by saw cut.
1. Longitudinal joints for each course shall be offset thirty (30) centimeters from the joint
in the immediate underlying course. Transverse joints shall be offset a Minimum of sixty
(60) Centimeters from the joint of the immediate underlying course.
2. Longitudinal joints shall be located within fifteen (15) centimeters of the Centerline
of the roadway or within fifteen (15) centimeters of the centerline of a lane.
3. The new asphaltic concrete layer shall overlap with the adjacent layers by the maximum
of five (5) centimeters or one-half (1/2) the layer thickness.
4. Transverse joints shall be formed by cutting back the first layer placed to the full depth of
Al Jaber Contracting-ajc
Document No:MS-C-05
Method Statement for Construction
Rev: 00
of
Date: 05/11/2017
Asphalt Work
Page 12 of 12
the layer, removing and wasting the material, spreading new asphaltic material in sufficient
quantity to create a compacted thickness equal to the thickness of the first layer. The joint shall be
cross-rolled with one coverage and the joint checked with a straight-edge not less than four (4)
meters in length. High points shall be removed and sags filled with additional asphaltic material
and the joint rolled a second time .The joint shall again be checked with a straight edge, humps and
sags adjusted if necessary, and rolled until the joint is complete and compacted as specified.
5. Contact surfaces, where asphaltic concrete mixtures are placed against concrete or curb stone
and gutter, bridge abutments, retaining walls, drainage facilities, a cold pavement joint or metal
surface, shall be tack coated
Al Jaber Contracting-ajc