5/22/2021 API 570 Certification Prep API 578 Study Questions Flashcards | Quizlet

API 570 Certification Prep API 578 Study Questions


Terms in this set (29)

API 578 provides b. all alloy materials


guidelines for a quality
assurance system to
verify
a. all materials.
b. all alloy materials.
c. only non-ferrous
materials.
d. only high-alloy
materials.

Usually substituting an a. hydrogen sulfide (H2S)


alloy for carbon steel b. hydrofluoric acid (HF)
would not cause a c. sulfuric acid (H2SO4)
problem. List 3 process
services where
substituting an alloy for
carbon steel could
result in a problem.

API 570 Certification Prep API 578 Study Questions


https://quizlet.com/558312831/api-570-certification-prepapi-578-study-questions-flash-cards/ 1/6
5/22/2021 API 570 Certification Prep API 578 Study Questions Flashcards | Quizlet

An alloy material is any c. to improve either mechanical properties or


metallic material that improve corrosion resistance
contains alloying
elements that are
added:
a. only to improve
mechanical properties.
b. only to improve
corrosion resistance.
c. to improve either
mechanical properties
or improve corrosion
resistance

Alloy components . welds


include, pipe, fittings,
plate, flanges, and

An inspection lot d. all materials of the same material type from the
includes: same supplier and heat
a. all materials from
same supplier.
b. all materials included
on the same purchase
order.
c. all materials of the
same material type (i.e.
316 SS)
all materials of the same
material type from the
same supplier and heat

API 570 Certification Prep API 578 Study Questions


https://quizlet.com/558312831/api-570-certification-prepapi-578-study-questions-flash-cards/ 2/6
5/22/2021 API 570 Certification Prep API 578 Study Questions Flashcards | Quizlet

A documented material b. Owner/User


verification program
should be established
by the:
a. Authorized inspector.
b. Owner/User.
c. Repair organization.
d. Engineering
organization.

1. The material d. in existing piping systems and during


verification program construction, repairs and alterations of piping
should cover PMI systems
testing of materials:
a. during construction
of piping systems.
b. in existing piping
systems.
c. during repairs and
alterations of piping
systems.
d. in existing piping
systems and during
construction, repairs
and alterations of piping
systems.

1. Random sampling is a. low-risk systems


most appropriate for:
a. low-risk systems.
b. low alloy systems.
c. stainless steel
systems.
d. ferritic steel systems.
API 570 Certification Prep API 578 Study Questions
https://quizlet.com/558312831/api-570-certification-prepapi-578-study-questions-flash-cards/ 3/6
5/22/2021 API 570 Certification Prep API 578 Study Questions Flashcards | Quizlet

Who has the b. Owner/User


responsibility to
determine the extent of
PMI performed?
a. Authorized inspector
b. Owner/User
c. Repair organization
d. Engineering
organization.

Who has the b. Owner/User


responsibility to verify
that the material
verification program is
properly implemented?
a. Authorized inspector
b. Owner/User
c. Repair organization
d. Engineering
organization

Who has the b. Owner/User


responsibility to review
and approve the
adequacy of the PMI
program used by
fabricators and material
suppliers?
a. Authorized inspector
b. Owner/User
c. Repair organization
d. Engineering
organization

API 570 Certification Prep API 578 Study Questions


https://quizlet.com/558312831/api-570-certification-prepapi-578-study-questions-flash-cards/ 4/6
5/22/2021 API 570 Certification Prep API 578 Study Questions Flashcards | Quizlet

A mill test report: c. is an important part of the material qualify


a. eliminates the need assurance program
for further material
verification.
b. is a report showing
material discrepancies.
c. is an important part of
the material qualify
assurance program.
d. is issued by the
owner upon receipt of
materials.

The material verification a. only pressure-containing components


program specified by
API 578 covers:
a. only pressure-
containing components
b. only pipe, and fittings.
c. only pipe, fittings, and
welds.
d. pressure-containing
and non-pressure
containing components.

API 570 Certification Prep API 578 Study Questions


https://quizlet.com/558312831/api-570-certification-prepapi-578-study-questions-flash-cards/ 5/6
5/22/2021 API 570 Certification Prep API 578 Study Questions Flashcards | Quizlet

During alloy welding: c. on electrode from each lot should be sampled


a. one electrode from
each box should be
sampled.
b. two electrodes from
each box should be
sampled.
c. one electrode from
each lot should be
sampled.
d. two electrodes from
each lot should be
sampled.

If alloy element(s) are d. could be conducted on a weld button prior to


contained in the flux of production welds
a welding electrode,
PMI testing:
a. is not necessary.
b. is not necessary
provided appropriate
documentation is
provided by the
supplier.
c. could be conducted
on any of the
production welds.
d. could be conducted
on a weld button prior
to production welds.

https://quizlet.com/558312831/api-570-certification-prepapi-578-study-questions-flash-cards/ 6/6