20% Component of The Ira Utilization: City of Calapan, Or. Mindoro
20% Component of The Ira Utilization: City of Calapan, Or. Mindoro
Other Services
Loan Amortization/Debt Servicing Land Bank of the Philippines 36,219,289.98 January 36%
Social Services
Completion of San Vicente West Multi-Purpose Building Brgy. San Vicente West 1,000,000.00
Completion of Bayanan 2 Elementary School Multi-Purpose Building Bayanan 2 Elem. School 2,000,000.00
Construction of Sta. Maria Village Multi-Purpose Building Brgy. Sta. Maria Village 3,700,000.00
Environmental Services
Construction of Perimeter Fence in Category 2 Sanitary Landfill, Phase 3 Brgy. Batino 1,000,000.00 January
(i.e. soil covering, landfill cell & other facilities) Brgy. Batino 2,000,000.00
Installation/Rehabilitation of Streetlights
Economic Services
Agricultural Devt. Program
Purchase/Acquisition of Pre & Post Harvest Facilities & Equipment Rural Barangays 3,000,000.00
Construction of Solar & Flat Bed Dryers Rural Barangays 1,000,000.00
Const./Install. of Communal Irrigation Systems & Shallow Tube Wells Rural Barangays 3,000,000.00
Installation/Rehabilitation of Water System in Different Barangays Different Barangays 2,000,000.00
Concreting/Rehabilitation of Roads in Different Barangays
Rehab. of Road with Const. of Drainage Canal in M H del Pilar St., Phase 2 M.H. del Pilar St. 4,000,000.00
Rehab. of Road with Const. of Drainage Canal in Pachoca Brgy. Pachoca 5,000,000.00
Rehabilitation of Road in Juan Luna St., Phase 3 Juan Luna St. 2,000,000.00
FDP Form 7 - 20% Component of the IRA Utilization
Rehabilitation of Tibag-Pachoca Provincial Road with Drainage Const., Phas Tibag-Pachoca 4,000,000.00
Rehabilitation of Biga-Comunal Provincial Road, Phase 3 Biga-Comunal 3,000,000.00
Rehabilitation of Road in Brgy. Sta. Cruz Brgy. Sta. Cruz 1,000,000.00
Rehabilitation of Road in Brgy. Personas Brgy. Personas 1,000,000.00
Rehabilitation of Road in Brgy. Malamig Brgy. Malamig 1,000,000.00
Rehabilitation of Road in Brgy. Balingayan Brgy. Balingayan 1,000,000.00
Rehabilitation of Sitio Bagong Silang Road, Baruyan Sitio Bagong Silang, Baruyan 1,000,000.00
Concreting of Road in Sitio Bagong Silang, Baruyan Sitio Bagong Silang, Baruyan 1,000,000.00
Rehabilitation of Sapul-Bayanan 2 Road Sapul-Bayanan 2 3,000,000.00
Rehabilitation of Bondoc Road Bondoc 1,000,000.00
Concreting of Sitio Amuguis Road in Sta. Rita Sitio Amuguis, Sta. Rita 1,000,000.00
Concreting of Lalud-Pachoca, NIA Road, Phase 2 Lalud-Pachoca, NIA Road 5,000,000.00
Concreting of Sitio Tahik Road, Managpi Sitio Tahik, Managpi 1,000,000.00
Concreting of Sapul-Puting Tubig-Gulod Road Sapul-Puting Tubig-Gulod 1,000,000.00
Concreting of Sapul Road (access road to BJMP Bldg.) Sapul Road 2,000,000.00
Concreting of Road in Brgy. San Rafael Brgy. San Rafael 1,000,000.00
Concreting of Road in Brgy. Lalud Brgy. Lalud 1,000,000.00
Concreting of San Jose Pamayanan Road, Balite Brgy. Balite 1,000,000.00
Concreting of Road in Sitio Sto. Niño, Nag-iba 2 Sitio Sto. Niño, Nag-iba 2 1,000,000.00
Concreting of Guinobatan Road (road going to City Housing Site & Regl. Ev Brgy. Guinobatan 2,000,000.00
- Concreting of Lalud-Pachoca NIA Road, Lalud NIA Road Extension Lalud-Pachoca, NIA Road
Other Services
Loan Amortization/Debt Servicing Land Bank of he Philippines 34,000,000.00 January 2020 December 2020 100%
Social Services
Other Social Services Program
Construction/Rabilitation of Multi-Purpose Building
Construction of City Multi-Purpose Bldg. (Old ABC Hall/Cueto Bldg.) Old ABC Hall/Cueto Bldg. 10,000,000.00
Construction/Completion of Rural Health Unit (RHU-Guinobatan) RHU-Guinobatan 8,000,000.00 June 2020 March 6, 2021 100%
Construction of Libis Multi-Purpose Building Brgy. Libis 2,500,000.00 June 2020 August 2020 100%
Construction of Biga Multi-Purpose Building Brgy. Biga 3,700,000.00
Construction of Canubing I Multi-Purpose Building Brgy. Canubing I 900,000.00 June 2020 August 2020 100%
Construction of Sta. Isabel Multi-Purpose Building Brgy. Sta. Isabel 1,900,000.00 June 2020 August 2020 100%
Construction of Bondoc Multi-Purpose Building Brgy. Bondoc 3,700,000.00 Oct. 2020 35%
Construction of Bulusan Multi-Purpose Building Brgy. Bulusan 3,000,000.00 June 2020 August 2020 100%
Construction of Camilmil Multi-Purpose Building Brgy. Camilmil 3,700,000.00 June 2020 Jan. 2021 100%
Construction of Ibaba West Multi-Purpose Building Brgy. Ibaba West 3,700,000.00 Oct. 2020 March 2021 100%
Construction of Malamig Multi-Purpose Building Brgy. Malamig 3,700,000.00 Dec. 2020 2%
Construction of Managpi Multi-Purpose Building (Phase 2) Brgy. Managpi 1,000,000.00 June 2020 August 2020 100%
Construction of Nag-iba II Multi-Purpose Building Brgy. Nag-iba II 3,700,000.00 June 2020 March 2021 100%
Construction of San Vicente West Multi-Purpose Building (Phase 2) Brgy. San Vicente West 1,500,000.00 Nov. 2020 March 2021 100%
Construction of Silonay Multi-Purpose Building, Bleachers and Wall Brgy. Silonay 1,000,000.00 Sept. 2020 Nov. 2020 100%
Rehabilitation of Mahal na Pangalan Multi-Purpose Building Brgy. Mahal na Pangalan 1,000,000.00 Oct. 2020 Jan. 2021 100%
Rehabilitation of Sta. Isabel Health Center Brgy. Sta. Isabel (1,000,000.00)
Construction/Completion of Child Development. Centers in Different Baranga Different Brgys. 1,000,000.00
- Construction/Completion of Child Devt. Center, N. Aboboto MS, Sapul Brgy. Sapul July 2020 Sept. 2020 100%
- Construction/Completion of Child Devt. Center, Brgy. Lalud Brgy. Lalud Sept. 2020 Sept. 2020 100%
- Construction/Completion of Child Devt. Center, Brgy. Sta. Maria Village Brgy. Sta. Maria Village Aug. 2020 Sept. 2020 100%
Housing & Urban Settlements Services
Development of Relocation/Resettlement/CMP & Other Housing Projects Balite, Maidlang 5,000,000.00 Aug. 2020 Dec. 2020 100%
(682,134.60)
4,317,865.40
Environmental Services
(i.e. soil covering, landfill cell & other facilities) Brgy. Batino 2,000,000.00 July 2020 Dec. 2020 100%
Installation/Rehabilitation of Streetlights
Installation of Streetlights in Balite-Wawa Provincial Road (Phase 3) Balite-Wawa 1,500,000.00 June 2020 Dec. 2020 100%
Installation of Streetlights in Mabini St., Ilaya Mabini St., Ilaya 620,000.00 June 2020 Dec. 2020 100%
Installation of Streetlights in San Antonio-Suqui Provincial Road San Antonio-Suqui 500,000.00 June 2020 Dec. 2020 100%
Installation of Streetlights in Lazareto Provincial Road Brgy. Lazareto 1,500,000.00 June 2020 Dec. 2020 100%
Rehabilitation of Streetlights in Lumangbayan-Guinobatan Provincial Road (R Lumangbayan-Guinobatan 800,000.00 Oct. 2020 Feb. 2021 100%
FDP Form 7 - 20% Component of the IRA Utilization
Installation/Rehabilitation of Streetlights in different barangays Different Brgys. 1,000,000.00 March 2020 Dec. 2020 100%
Economic Services
Agricultural Devt. Program
Purchase/Acquisition of Pre & Post Harvest Facilities & Equipment Rural Brgys. 3,000,000.00
Construction of Solar & Flat Bed Dryers Rural Brgys. 1,000,000.00
- Solar Dryer, Brgy. Managpi Brgy. Managpi Dec. 2020 Dec. 2020 100%
Const./Install. of Communal Irrigation Systems & Shallow Tube Wells Rural Brgys. 2,000,000.00
- Irrigation System, Brgy. Malad Brgy. Malad Sept. 2020 Sept. 2020 100%
- Irrigation System, Brgy. Nag-iba 2 Brgy. Nag-iba 2 Sept. 2020 Sept. 2020 100%
Installation/Rehabilitation of Water System in Different Barangays Different Brgys. 1,000,000.00 June 2020 Dec. 2020 74%
Concreting/Rehabilitation of Roads in Different Barangays
Rehabilitation of Road with Construction of Drainage Canal in M H del Pilar S MH del Pilar St. 4,000,000.00 43,952.00 June 2020 100%
Rehabilitation of Tibag-Pachoca Provincial Road with Drainage Construction Tibag-Pachoca 4,000,000.00 Oct. 2020 Jan. 2021 100%
Rehabilitation of Road in Bonifacio St., Ilaya (Provincial Road) Bonifacio St., Ilaya 2,000,000.00 Oct. 2020 Dec. 2020 100%
Rehabilitation of Road in Bulusan Provincial Road (Sitio Wireless-Sitio Colo- Bulusan (Wireless-Colo-colo) 2,000,000.00 Oct. 2020 Feb. 2021 100%
Rehabilitation of Sta. Cruz Road Brgy. Sta. Cruz 1,000,000.00 Sept. 2020 Dec. 2020 100%
Concreting of Sitio Upperville Road, San Rafael, Phase 3 Upperville, San Rafael 1,000,000.00 Oct. 2020 Nov. 2020 100%
Concreting of Sitio San Gabriel/Manuro Road Malamig San Gabriel/Manuro, Malamig 1,000,000.00 Sept. 2020 Nov. 2020 100%
Concreting of Farm to Market Road in Sitio Centro-Bagong Pook, Biga Centro-Bagong Pook, Biga 1,000,000.00 Oct. 2020 Nov. 2020 100%
Concreting of Farm to Market Road in Sitio Pajo-Sitio Lagonlong, Canubing I Pajo-Lagonlong, Canubing I 1,000,000.00 Oct. 2020 Nov. 2020 100%
Concreting of Farm to Market Road, Sitio Binarilan, Canubing I Binarilan, Canubing I 1,000,000.00 Oct. 2020 Nov. 2020 100%
Concreting of Farm to Market Road, Sitio Aglicawan, Nag-Iba II Aglicawan, Nag-iba II 1,000,000.00 Oct. 2020 Nov. 2020 100%
Concreting of Sitio San Isidro Road, Balingayan San Isidro Road, Balingayan 1,000,000.00 Nov. 2020 Jan. 2020 100%
Concreting of Road in Personas (access road to senior high school) Personas 1,000,000.00 Oct. 2020 Nov. 2020 100%
Concreting of Road in Tawagan (access road going to elementary school) Tawagan 1,000,000.00 Oct. 2020 Nov. 2020 100%
Concreting of Road in Sitio Tahik-Sitio Centro, Camansihan Sitio Tahik Centro, Camansihan 1,000,000.00 Oct. 2020 Dec. 2020 100%
Concreting/Rehabilitation of Road in Sitio Amuguis, Sta. Rita Amuguis, Sta. Rita 1,000,000.00 Oct. 2020 Dec. 2020 100%
Open/Concreting of Road in Sitio Ilang-Ilang, Pachoca Ilang-ilang, Pachoca 1,000,000.00 Oct. 2020 Nov. 2020 100%
Concreting of Lalud-Pachoca, NIA Road Lalud-Pachoca NIA road 4,000,000.00 Oct. 2020 Jan. 2021 100%
Concreting of Road in Sitio Buhuan, Comunal Sitio Buhuan, Comunal 1,000,000.00 Oct. 2020 Nov. 2020 100%
Concreting of Road in Maidlang Resettlement Area, Maidlang Maidlang 1,000,000.00 Oct. 2020 Nov. 2020 100%
Concreting of Road in Sitio Ilaya-Cuenca, Managpi Sitio Ilaya-Cuenca, Managpi 1,000,000.00 Sept. 2020 100%
- Rehabilitation of Road (Phase 2) Juan Luna St., San Vicente North Brgy. San Vicente North June 2020 July 2020 100%
- Concreting of Road Lalud-Pachoca Road Lalud-Pachoca Road June 2020 July 2020 100%
- Concreting of Road, Sitio Ibaba, Brgy. Baruyan Sitio Ibaba, Brgy. Baruyan Oct. 2020 Dec. 2020 100%
- Rehabilitation of Road, Sta. Maria Village Brgy. Sta. Maria Village Nov. 2020 Dec. 2020 100%
- Construction Matrials, Brgy. San Rafael Brgy. San Rafael June 2020 July 2020 100%
- Concreting of Road, Sitio Mahabang Parang, Brgy. Parang Brgy. Parang Nov. 2020 Dec. 2020 100%
- Concreting of Road, Sitio Ibaba, Brgy. Baruyan Brgy. Baruyan Oct. 2020 Dec. 2020 100%
- Concreting of Road, Brgy. Tawagan Brgy. Tawagan Nov. 2020 Nov. 2020 100%
- Rehabilitation of Road with Drainage Construction, Brgy. Masipit (AO No Brgy. Masipit 1,000,000.00 Dec. 2020 Feb. 2021 100%
- Concreting of Chico St. with Drainage Construction, Brgy. Lalud (AO No. Chico St., Brgy. Lalud 1,000,000.00 Nov. 2020 March 2021 100%
Social Services
Other Social Services Program
Construction/Rabilitation of Multi-Purpose Building
Construction of Canubing I Multi-Purpose Building Brgy. Canubing I 3,000,000.00 Sept. 2019 March 2020 100%
Construction of Bayanan II Multi-Purpose Building Brgy. Bayanan II 3,000,000.00 Sept. 2019 20%
Construction of Gulod Multi-Purpose Building Brgy. Gulod 3,700,000.00 March 2019 Oct. 2019 100%
Construction of Balingayan Multi-Purpose Building Brgy. Balingayan 3,700,000.00 March 2019 Nov. 2019 100%
Construction/Rehabilitation of Multi-Purpose Buildings Various Brgys. 1,000,000.00
Economic Services
Other Economic Development Program
Concreting/Rehabilitation of Roads in Different Barangays
Concreting of Sitio Kili-kilo Road, Palhi Brgy. Palhi 1,000,000.00 2020
Concreting of Puting Tubig-Batino Road Puting Tubig-Batino 1,000,000.00
Rehabilitation of City Roads in Poblacion Area Poblacion Area 6,000,000.00
- Rehabilitation of Road, J. Luna St.,San Vicente Central Dec. 2019 100%
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
998,694.77 On-going
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation/with Program of Works - P2,993,294.57
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation/with Program of Works-P2,997,931.00
For Implementation.
For Implementation.
For Implementation/with Program of Works-P5,000,000.00
For Implementation.
For Implementation.
For Implementation/with Program of Works-P1,994,770.77
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
For Implementation.
On-going.
439,260.00 On-going.
For implementation
On-going.
104,662.50 Project Completed.
992,607.46 On-going
For Implementation
ARNAN C. PANALIGAN
City Mayor