Professional Documents
Culture Documents
04-Dr Yet-Managing Adverse Impact
04-Dr Yet-Managing Adverse Impact
• Unfavourable conditions
& Preferred pile types
Compliance with design &
construction requirements
(Building Control Regulation 26)
4
Performance requirement
(Fifth schedule)
• A building, including its foundation, shall be
designed and constructed, so that combined
dead, imposed, wind and other intended
load can be sustained and transmitted to
ground:
– Safely and
– Compliance with
acceptable solutions - is
deemed to comply
objective and performance
requirements of building.
6
BSEN 1997-1:2004 Eurocode 7
SECTION 7 Pile foundations
7
BSEN 1997-1:2004 Eurocode 7
SECTION 7 Pile foundations
• 7.3.2.3 Heave
(1)P In considering the effect of heave, or upward loads,
which may be generated along the pile shaft, the movement
of the ground shall generally be treated as an action.
NOTE 1 Expansion or heave of the ground can result from
unloading, excavation, frost action or driving of adjacent
piles. It can also be due to an increase of the ground-water
content resulting from the removal of trees, cessation of
abstraction from aquifers, prevention (by new construction) of
evaporation and from accidents.
NOTE 2 Heave may take place during construction, before
piles are loaded by the structure, and may cause
unacceptable uplift or structural failure of the piles. 8
BSEN 1997-1:2004 Eurocode 7
SECTION 7 Pile foundations
• 7.4.2 Design considerations
(4)P The choice of type of pile, including the quality of the pile
material and the method of installation, shall take into account:
— the effect of the method and sequence of pile installation
on piles, which have already been installed and on adjacent
structures or services;
— the effects of pile construction on neighbouring buildings.
(5) In considering the aspects listed above, the following items
should receive attention:
— displacement or vibration of adjacent structures due to pile
installation; 9
prEN 12699:2013
Execution of displacement piles
10
Regulatory requirement in a nutshell
• BC Regulation 26 • BC Regulation 27 –
– All buildings shall be – Deem to satisfy by compliance
designed and constructed to with acceptable solution
comply with objectives and • Eurocode 7
performance requirements in • Execution code EN12699
Fifth schedule
• Design & construction to
– Objective : to protect other
properties from damage consider:
– Performance requirement : – Excessive heave and excessive
without causing deformation lateral movement
which will impair stability of – Effects on existing piles and
other buildings adjacent structures
11
Statistics on usage of
Jacked piles
Piling usage in landed development
From 2002 to 2013
• Reduction in usage of driven RC piling to less than 10%
• Increase in usage of jack in piling to almost 50%
• Reflects success in persuasive measures to adopt more environmentally friendly
piling system
Usage of Driven and Jacked RC piles in
landed development
70% 65%
Perecentage of projects
60%
49%
50%
40%
30%
20%
9%
10% 4%
0%
2002 2013
Driven RC pile 65% 9%
Jacked RC pile 4% 49%
Year
Driven RC pile Jacked RC pile
Feedback Due to Different Piling Systems
for landed development
Percentage feedback for landed development
Micropile 3%
15
Classification of pile
Large-displacement pile Small-displacement pile
16
Issues of jacked-in piles
• Soil displacement problem is particularly severe, when:
Density of displacement piles is high
17
What happen when pile is pushed into soft clay ?
18
Heave & lateral movement due to pile driving
19
Possible pile displacement mechanism
Pile depth, L
Clay Clay
• Vheave = Vpile_inserted for insensitive clay; Vheave < Vpile_inserted for sand
• Influence zone is a function of pile depth & soil type.
• The longer the pile, the larger is the influence zone.
• The influence zone for clayey soil is larger as compared to sandy soil. 22
Issue of surcharge loading from self-
weight of jacked piling machine
• Heavy weight of jack-in piling machine can exert
significant pressure on ground, potentially
causing ground heave, even before piling work
commences
• Need to check adequacy of geotechnical
capacity of ground on which the jack-in machine
is resting
• Pay attention to site with soft ground and fill
layer is thin / absent, and when piling machinery
moves very near to adjacent buildings or to a
slope, like canal 23
Issue of surcharge loading from self-weight
of jacked piling machine
• Use of steel plates to
distribute self-weight
of machine, so that
bearing pressure
exerted on ground is
within limit.
• Laying a layer of
hardcore to help
distribute the weight
over a larger area
24
Case study on projects
using jacked piles
25
Jacked RC pile
• Pile diameter 175x175mm
• Pile depth 23m (38 nos)
• Soft soil upto 8m depth
• No relief well & no preboring
26
Subsoil condition
27
Sensitive adjacent buildings
28
Learning point (Case study 1)
• Despite just a small number of jacked
piles in soft clay, damage could still
occur if no protective measure were
implemented at site, and adjacent
buildings are “sensitive”.
29
Jacked RC pile
• Pile diameter 300x300mm
• Pile depth 46m (214 nos)
• Soft soil upto 30m depth
• Some relief wells, no preboring
30
Ground condition
Thick Kallang formation underlain by OA
31
Jacked-in precast RC pile
• 300mm x 300mm precast RC pile
• Penetration depth = 46m
• Total 214 piles (volume =886m3) → 1 pile ≈ 4 m3
• Relief trench
– 0.7m width x 0.8m deep around the site
• Relief wells
– 250mm diameter @10m c/c along boundary
– Depth 20m
– Total 15 nos (volume = 14.7m3) → 1 relief well ≈ 1 m3
Heave during jacked piling
34
Probable causes
• Improper execution of relief wells
– Volume of soil displaced by piles = 886 m3
– Volume of soil removed from relief wells
=14.7m3 x 4 = 59 m3 (only maintain 3-4 times)
– Net volume of soil displaced = 886m3 - 59m3 =
827m3 !!
• Ground heave of 25mm not acted upon
– It should be specified as work suspension
level on plan. 35
Learning point (Case study 2)
• Builder to take immediate remedial action
when critical instrumentation readings
exceed limits during jacked pile
installation.
• Improper execution of relief wells may not
help to reduce the soil displacement
problem.
36
Jacked prestressed spun piles
• Pile diameter 300-600mm
• Pile depth 40m to 50m
• Thick layer of marine clay
• Relief wells & preboring
37
Section through the piling site
and the adjacent structures
Adjacent
Piling structure
site
39
Additional measures taken
• Install sheetpile to reduce the migration of soil
outside the boundary
41
Protective measures taken for jacked piles
(2) Temporary (3) Permanent
(1) Preboring relief wells
well relief wells
well
Piling
Nearby
site structure
43
Jacked prestressed spun pile
• Pile diameter 400mm / 600mm
• Pile depth 23m
• Soft clay upto 15m depth
• Relief wells & preboring successfully implemented
44
Jacked prestressed spun pile
45
Installation of jacked pile
46
Preboring with steel casing
50
Perforated steel pipes
• In this project, relief wells are made up of steel
pipes of 400mm diameter - installed to depth 9m-15m,
with perforations along pipes.
51
Perforated steel pipes
Perforation size 4”x2”,
regularly spaced along pipe.
52
Prestressed spun pile jacked into ground
53
No complaint of damage
54
Learning point (Case study 4)
• With active involvement of
designers, it is possible to
mitigate effect of installation
of large-displacement piles
on adjacent buildings,
through meticulous planning
and implementation of relief
wells and preboring,
coupled with close
monitoring of the ground
movements.
55
Jacked steel H-pile
• Pile size 203x203x46 kg/m
• Pile depth 26m
• Soft soil upto 20m depth
• No relief well & no preboring
56
Jacked steel H-pile
• The site is underlain by 20m thick soft clay
• Adjacent building in close proximity
• QP proposed to use steel H-piles as foundation piles.
Each H-pile takes 35 tonnes.
57
Presence of soft clay upto 20m depth
58
Steel H-piles jacked into ground
• Total number of piles = 114
• Volume of one H-pile = 0.15m3
• Total volume of pile inserted = 17m3
• Estimated average heave over entire site area = 28mm
59
No complaint of damage caused
• Due to small volume of
inserted piles (total only
17m3), relief wells and
preboring were not
needed in this project.
• No complaint of damage
to neighbouring buildings
60
What could happen if RC piles were used in
this project instead ?
62
Implication of migration to
Eurocode on role of pile
designers
63
Choice of pile type and installation method
Density of Presence of
piles is high thick soft clay
Adjacent Sensitive
structure in adjacent
close proximity structures
Preferred pile types under
unfavourable conditions
Non-
Small-displacement
displacement
piles
piles
Steel Grouted
pipe pile micropile
Steel H- Bored
pile pile
66
Concluding remark
• Jacked piles are displacement piles, displacing ground as
they are installed . When chosen and used, designer and
builder need to properly manage their adverse impact on
adjacent structures.
68