Download as pdf or txt
Download as pdf or txt
You are on page 1of 22

Page 1 of 22

CONSTRUCTION OF HYBRID PILE FOUNDATIONS: A CASE STUDY


OF HYBRID PILE FOUNDATION P3 OF BRIDGE NO. 43 AT BAKKAL
OF USBRL PROJECT
Author: Praveen Kumar, IRSE 2009, Senior Safety Officer/Engg., Safety Organisation, Northern Railway

Abstract

This paper describes and analyses the execution aspects of construction of hybrid pile
foundations. To study, understand and analyze the execution aspects, the hybrid pile foundation
P3 of Bridge No. 43 of USBRL project is considered. Bridge No. 43 has hybrid pile foundations
from Abutment A1 to Pier P3. The geology at the site of construction of hybrid pile foundation
P3 is studied along with the recommendations. Thereafter the methodology adopted for
excavation and slope protection works to reach the ground level for drilling and concreting of
piles of hybrid pile foundation P3, is studied. The staking of the survey coordinates of 155 piles
(98 outer and 55 inner piles), drilling of bore holes, lowering of reinforcement cage and
concreting of these piles is discussed. The construction of top ring beam, excavation to the
bottom of bottom pile cap, reinforcement binding of bottom pile cap, concreting of bottom pile
cap, construction of bottom ring beam, plain cement concrete(PCC) infilling and construction of
top raft is then described. The quality of concrete used in construction of hybrid pile foundation
P3 is studied using materials testing, concrete production at the batching plant, 28-days concrete
cube strength test results and permeability test of concrete.

1. INTRODUCTION cap over the hybrid pile foundation P3 are


5.793 m and 1.5 m respectively. The
This paper describes and analyses the spherical bearing which permits movements
execution aspects of construction of hybrid in the longitudinal direction is to be
pile foundations. To study, understand and provided on substructure over hybrid pile
analyze the execution aspects, the hybrid foundation P3. Table 1 and Table 2 provides
pile foundation P3 of Bridge No. 43 of the details of hybrid pile foundation P3.
USBRL project is considered. Bridge No. 43 Figures 1 to 4 provides the construction
is continuous composite welded plate Girder details of the hybrid pile foundation P3.
Bridge of length 777m. Bridge no. 43 has 12
piers-P1 to P12 and abutments A1 and A2 2. GEOLOGICAL INVESTIGATION
with 13 spans of 35m, 53m, 10x64m, 49m
and being constructed under Scheduled The scope of geological investigation works
Contract Agreement for construction of 16 in connection with construction of
Bridges. It has hybrid pile foundations from foundations (from A1 to P3) included
Abutment A1 to Pier P3. The chainage of mainly drilling NX size exploratory
the center line of hybrid pile foundation P3 boreholes at different locations of Abutment
is Km 49/629.713 and the founding level of A1 and Piers P1, P2 and P3 on pier locations
top raft is 840 m. The height of pier and pier as well as on both sides of centre
Page 2 of 22

line/alignment on the up slope and down mesh & rock bolting. The report
slope area. The exploratory drilling was recommended to design the deep well / pile
done from 35 m to 60 m depth below ground foundation at this pier location and rested on
surface at each location with triple tube core bed rock at deeper depth.
barrel for achieving maximum core Further, the report recommended that the
recovery. After analysis of borehole data, cutting of slope should be done in proper
field observations as well as lab test data, way by cutting of slope in a proper angle &
final geotechnical investigation report was height and providing berms of suitable width
prepared along with necessary in between two consecutive slopes. The
recommendations regarding slope stability at overburden should be removed during
A1, P1, P2 and P3 locations. At Bridge site cutting of slope where bedrock is at shallow
16 number of bore holes were drilled depth and overhangs should be removed to
between chainage Km 49/477.713 to Km avoid any incident in the future.
49/629.713 on center line and either sides of Based on the geological, geotechnical
the center line at an offset of 20 m and 40 m investigation reports and site visits to the
in the down slope and at 20 m offset in the location of Bridge No. 43, the designer
up slope area. Picture 1 shows geological L RITES India and RAMBOLL Consultants of
section along hybrid pile foundations A1 to Denmark designed the hybrid pile
P3. Picture 2 shows geological cross section foundations for abutment A1 and piers P1 to
at hybrid pile foundation P3. P3. The proof checking of the design was
The report indicated that at Pier- P3, the bed done by Anwikar Consultants, Germany.
rock encountered at deeper depth of 37.20m
below ground surface at P3D2 location, at 3. EXCAVATION
58.00m below existing ground level at P3D1 The location where the hybrid pile
location and bed rock not met up to explored foundation P3 was to be constructed was not
depth of 50.00m & 55.00m at P3CL & P3U1 directly available as it was overlain by soil
locations respectively indicating thick cover and rock. Therefore excavation had to be
of slope debris material all along the slope. done and access roads had to be created so
The slope was quite steep in the middle part as to enable the manpower, machinery and
due to presence of small exposures of materials to provide the slope protection
brecciated material also exposed along the measures and reach the sites of construction
slope at places which was quite hard & of the hybrid pile foundation P3. The sites
compact in nature but extended up to were cleared of all the obstructions to enable
shallow depth only (as per bore hole data). the setting out for excavation. Thereafter
The cutting of the slope was required to be survey points were marked on the ground
done in slope debris material and brecciated for excavation by considering the excavation
material only at suitable angle with the margin for subsequent works involved in the
provision of berms in between two construction of hybrid pile foundation P3.
consecutive slopes and required support The excavation had to be done in slopes and
measures in the form of shotcreting, wire berms as per the approved drawing. Figure 5
Page 3 of 22

and 6 shows the details of slopes and berms axial tension equivalent to 25 percent of
which had to be achieved by the excavation. design capacity of rock bolt (For 11 m long
For carrying out the protection works, berms rock bolts it comes out to be 5.75 tonnes).
were created in the existing strata on which One percent of working rock bolts of 11 m
the shotcrete spraying machine and Atlas lengths were to be tested up to 10 percent
Copco ROC machine was used for more than the safe working load of 2
shotcreting and rock bolting of slopes tonnes/m.
respectively. The excavators and/or The weep holes were provided on slopes
breakers were used for excavation in soils @2.5 m c/c in both directions. Wherever the
and rocks and thereafter dumpers were used distance of rock bolt was less, the weep
to transport the excavated muck to the holes were located at the center of 4 rock
designated dumping sites. Picture 3 shows bolts.
excavation in progress at the location of The excavation was done at the location of
hybrid pile foundation P3. hybrid pile foundation P3 up to the ground
The steel fibre reinforced shotcrete of 100 level just above the level where the
mm thickness with fibre content of 40 embedded reinforcement of piles had to
kg/cum was provided on slopes in two terminate in the top raft (i.e. 1.5 m above the
layers of 50 mm each, with the bottom of the top raft).
reinforcement wire mesh of 100 mm x 100 The total steel fibre reinforced shotcrete
mm x 3.15 mm dia conforming to IS:1566 provided was 1261 sq.m and total number of
with nominal mass of 1.25 kg/sq.m, in rock bolts provided were 416.
between the two layers by wet shotcreting Table 10 provides the details of number of
method. The grade of Shotcrete was M25 days taken to complete the excavation,
and was to be applied on slopes as per shotcreting and rock bolting for hybrid pile
IS:9012:1997. foundation P3.
The rock bolts of 11 m length were provided
in the slopes with the Atlas Copco ROC 4. SURVEY AND LAYOUT MARKINGS
machine. The rock bolts were 32 mm in FOR PILES
diameter and of grade Fe500D. The rock
bolts were installed in 100 mm diameter The control pillars were established at the
drilled holes and grouted with 30 MPa site of hybrid pile foundation P3 after
cement grout. The orientation of the rock excavation was completed to reach the
bolts were decided by the geologist ground level just above the level where the
considering the site conditions. The spacing embedded reinforcement of piles had to
between the rock bolts was 1.5 m c/c terminate in the top raft i.e around RL 841.5
horizontally and vertically in the staggered m. Picture 4 shows the ground level reached
pattern. The protective coating of cement for starting drilling of piles of hybrid pile
inhibitor solution was applied on rock bolts foundation P3. The top level of the outer
and bearing plate. The rock bolts were piles was higher than that of the inner piles
tightened using torque wrench to generate an but the founding level of all the piles was
same. The pile drilling for all the 153 piles
Page 4 of 22

was done from the same ground level. This and/or water was sent down towards the
innovative working for drilling of piles drilling bit through the annular space in the
avoided the space constraints which would drilling rods for flushing out the drill
have been encountered by the drilling rig cutting/slush. The soil and rock was
had the drilling of outer and inner piles been removed by the rotary and/or percussion
done at different levels. The northing and (hammering) action of the rotating drill bit.
easting coordinates of the 153 piles were The depth of excavation was increased by
determined in AUTOCAD software. Table 9 further additions of the drilling rod at the
shows the survey coordinates of the 153 ends. The length of the first drilling rod
piles of the hybrid pile foundation P3. attached to the drilling bit was 2 m and the
Figure 7 shows the numbering sequence of lengths of subsequent drilling rods were 1.5
these piles and Figure 8 shows the 3D m. After reaching the design depths as
renditioned view of piling work sought to be indicated in the drawing, the drilled hole
achieved. Proper planning was done for the was cleaned, the water was pumped out of
construction of these piles keeping in mind the drilled bore and the drilling bit was taken
the working space requirements at the site. out. The depth of the bore hole was checked
For construction of each pile, its survey by conducting the soundness test. The
coordinates were staked on ground using the excavated material was disposed off. The
control pillars and total station. Picture 5 and diameter of outer and inner piles was 350
6 shows the control pillars used for staking mm. The lengths of the constructed outer
the coordinates of the piles on the ground. and inner piles were 29.325 m and 22 m.
The concrete chipping of these constructed
5. DRILLING AND CONCRETING OF piles was done keeping minimum 50 mm
PILES above the bottom of the top raft and bottom
pile cap in case of outer and inner piles
The DTH 300-01 model drilling rig, water respectively. The final lengths of piles were
tank and air compressor mounted on Ashok 29.3m and 20 m for outer and inner piles
Leyland Truck was used for drilling of piles. respectively. The maximum progress of
Picture 7 shows the drilling rig with water drilling of piles achieved in 1 day was 4
tank and air compressor mounted on the piles but generally the progress achieved in
truck used for drilling of piles at the hybrid a day was 2-3 piles. The theoretical
pile foundation P3 location. The operation quantities of the reinforcement steel and
of drilling rig was done by 2 operators and 2 concrete of grade M40 for each outer and
assistants. Recoverable steel casing of inner pile are given in Table 1.
diameter 390 mm was first drilled into the
soil as a temporary support and thereafter The reinforcement cage for the pile was
the drilling bit mounted on drilling rod was fabricated at the fabrication yard. Picture 8
rotated inside the steel casing over the shows the fabrication yard for fabrication of
staked coordinates of pile. The diamond reinforcement cage of piles of hybrid pile
button head drilling bit of diameter 340 mm foundation P3. Picture 9 shows the
was used for drilling. The compressed air formation of spiral reinforcement of pile.
Page 5 of 22

Picture 10 shows the inhibitor solution foundation P3 upto the bottom of the top raft
application over the reinforcement of piles. thereby exposing the outer piles. Thereafter,
Picture 11 shows the loading of the chipping of concrete of 98 outer piles
reinforcement cage in truck for transporting above the bottom level of top raft was done
it to the site of hybrid pile foundation P3. using the jack hammer. Picture 19 shows the
Picture 12 shows the lowering of chipping of concrete of outer piles in
reinforcement cage in the drilled hole of the progress at hybrid pile foundation P3.
pile of hybrid pile foundation P3. Picture 13 Thereafter, excavation was done in the
shows the closer look into the installation of inside portion of outer piles upto the bottom
reinforcement cage into the bore hole. level of the top ring beam. The
reinforcement binding was then started for
For concreting of piles a special mix of M40 the the top ring beam around the outer 98
grade was developed with maximum piles. Thereafter M35 grade concreting was
aggregate size of 10 mm. Table 3 shows the completed using bucket mounted on long
constituents of concrete in M40 mix design. boom PC 300 crane and subsequently curing
The concreting of piles was done using was done. The width and the depth of the
tremie pipe. The slump of concrete top ring beam were 600 mm and 750 mm
measured at the site was generally 190 mm - respectively. Picture 20 shows the
220 mm. Picture 14 shows the tremie pipe concreting in progress for the top ring beam
attached to hopper at the top used for using bucket and crane arrangement. Picture
concreting of piles. Picture 15 shows the 21 shows the completed top ring beam in
preparations being done for the tremie elevation. After completion of top ring
concreting of pile. Picture 16 shows the beam, the excavation was started in the
tremie concreting in progress for the pile. inside area of the top ring beam for reaching
Picture 17 shows the concrete cube samples the bottom level of the bottom pile cap. The
taken during tremie concreting of piles. excavation was done using excavators,
Table 4 shows the time cycle for the breakers and long boom PC 300 machines.
construction of pile of hybrid pile Pictures 22, 23 and 24 shows the excavation
foundation P3. in progress at the hybrid pile foundation P3
using excavators, breakers and long boom
6. CONSTRUCTION OF TOP RING PC 300 machines. The middle ring beam
BEAM, BOTTOM PILE CAP AND and shotcrete lining on the inside face was
BOTTOM RING BEAM not provided considering the safe and stable
site conditions during excavations. The top
After completion of construction of 98 outer
of the inner piles above the bottom level of
piles and 55 inner piles of hybrid pile
the bottom pile cap was chipped off keeping
foundation P3, the excavation was started
minimum projection of 50 mm above that
around the hybrid pile foundation P3.
level. Picture 25 shows the chipping of
Picture 18 shows the excavation in progress
concrete of inner piles in progress at the
around the hybrid pile foundation P3. The
hybrid pile foundation P3. The diameter and
excavation was done inside the hybrid pile
Page 6 of 22

depth of the bottom pile cap were 13.1 m binding in progress for the top raft of hybrid
and 2 m respectively. Picture 26 shows the pile foundation P3. Picture 36 shows the
arrangement for bending of reinforcement at completed top raft of hybrid pile foundation
the site of hybrid pile foundation P3. The P3.
reinforcement of the bottom pile cap was
transported to the site of work using Hydra 8. REINFORCEMENT BINDING
crane. Picture 27 shows the reinforcement The Bar Bending Schedule (BBS) was
being carried to the site of work using hydra prepared as per the approved drawings for
crane. Pictures 28, 29 and 30 shows the piles, top ring beam, bottom pile cap,
reinforcement binding in progress at bottom ring beam and top raft. The
different stages for bottom pile cap of hybrid reinforcement bars were then cut and bend
pile foundation P3. Picture 31 shows the to the length, shape and numbers for each
concreting in progress for bottom pile cap. bar mark/ID mark as given in the BBS. The
After completion of the construction of the reinforcement bars were treated with anti
bottom pile cap the reinforcement binding of corrosive treatment by using inhibitor
the bottom ring beam was completed. The solution. The reinforcement bars were then
width and the depth of the bottom ring beam tied in position to the spacing, lapping as
were 500 mm and 750 mm respectively. given in the BBS and in the approved
Thereafter construction of bottom ring beam drawings. All reinforcing bars had to be
was completed. Table 3 shows the exactly placed in the position shown in the
constituents of concrete mix design of grade drawings and had to be securely held in
M35 and M40 used for the construction of position during placing of concrete by
top ring beam, bottom pile cap and bottom galvanized steel binding wire not less than
ring beam. 18 SWG in diameter and conforming to IS
280 and by using stays, chairs, spacers,
7. PCC INFILLING AND
metal hangers, supporting wires or other
CONSTRUCTION OF TOP RAFT
approved devices at sufficiently close
The PCC infilling of 1:3:6 was completed intervals. Not more than 50 percent bars had
from the top level of the bottom pile cap up to be lapped at the same section i.e.
to the bottom level of the top raft. The depth staggered lap splices. Lap splices are
of PCC infilling was 8 m and the quantity of staggered if the center to center spacing of
PCC was 1056 cum. Picture 32 shows the the splices is greater than or equal to 1.3
PCC infilling in progress using the funnel times the lap length. The distance between
and canvas chute arrangement. Picture 33 the adjacent laps should be greater than or
shows the competed PCC upto the bottom of equal to 150 mm.
the top raft. On completion of PCC infilling
the process of construction of top raft was 9. FORMWORK
started. The diameter and depth of the top The piles of hybrid pile foundation P3 were
raft were 14 m and 3.2 m respectively. bored and cast in situ piles. The temporary
Pictures 34 and 35 shows the reinforcement support of casing of internal diameter 390
Page 7 of 22

mm, thickness 10 mm and length of 2 m was maximum size of aggregate in M40 mix was
provided at the top only. When the caving in kept as 10 mm to allow the free flow of
of the sides of the bore hole happened, the concrete through the tremie pipe of 100 mm.
bore hole was filled with concrete and After the placing of concrete was started the
drilling was resumed again after 24 hours. lower end of the tremie pipe was to remain
within the top surface of plastic concrete in
The formwork of top and bottom ring beams order to allow the build up of concrete from
consisted of steel plates of dimensions 1.5 m below instead of flowing over the surface.
x 0.5 m and thickness 10 mm. These steel
plates were connected to each other by bolts For top and bottom ring beams, bucket and
and laterally supported by channels and crane concreting methodology was adopted.
props. Picture 20 shows the formwork The bucket of capacity 0.5 cum was attached
provided for the construction of top ring to the long boom PC 300 crane. The bucket
beam. was filled with concrete from the transit
mixer and thereafter was moved to the site
The lateral support for the concreting of the of placement of concrete using the long
bottom cap was provided by the sides of boom PC 300 machine.
bore hole consisting of outer piles.
The concreting of bottom cap was done
The formwork of the top raft consisted of using three concreting methodologies i.e.
steel plates of dimensions 1.5 m x 0.5 m and bucket and crane; pumps connected with
thickness 10 mm. These steel plates were rigid pipes; funnel and canvas chutes. In the
connected to each other by bolts and pumps and rigid pipes methodology, the
laterally supported by channels, walers and concrete from the transit mixer was forced
props. Picture 36 shows the formwork into the rigid pipes through the concrete
provided for the construction of top raft. pump. The other end of the rigid pipe was
10. CONCRETING METHODOLOGY connected to the flexible pipe which could
be moved around for placing the concrete
For the concreting of piles, the tremie inside the reinforcement cage. In the funnel
concreting methodology was adopted. The and canvas chute arrangement, the concrete
diameter of the tremie pipe was 100 mm. from transit mixer was fed into the funnel
The tremie pipe was attached to the hopper which was carried by gravity through the
at its top on which concrete was fed from canvas chutes to the location of placement
the transit mixer. Picture 14 shows the of concrete.
tremie pipe attached to hopper at the top.
The length of tremie pipe could be increased The concreting of the top raft was done
by adding additional pipes. The concrete using rigid pipes and pumps. For details of
was placed at the lower end of tremie pipe the concreting methodology adopted for the
keeping the lower end sufficiently deep into top raft of hybrid pile foundation P3, the
the concrete which had been placed readers are advised to refer paper by the
previously but had not yet set. The Author “CONSTRUCTION OF RAFT
FOUNDATIONS: THE CASE STUDIES
Page 8 of 22

OF RAFT FOUNDATIONS OF BRIDGE per the QAP for civil works for Bridge No.
NO. 43 AND 44 (CHENAB BRIDGE) AT 43.
BAKKAL, USBRL PROJECT” published in
the IPWE proceedings 2019. (iii) Cube strength test results

The cube samples were prepared at site


11. RESULTS
during concreting operations of hybrid pile
(i) Materials testing before concreting foundation P3 and thereafter taken to the
quality control laboratory at the site. Table 7
The size, gradation and moisture content shows the 28 days cube strength test results
tests for coarse aggregates were to be for the various concreting operations in
conducted before each concreting day as hybrid pile foundation P3.
specified in the approved Quality Assurance
Plan (QAP) for civil works for Bridge No. (iv) Permeability test
43. Similarly the tests for size, gradation, silt
content, moisture content of sand were to be The permeability test was conducted for the
conducted as specified in the approved QAP concrete used in the construction of hybrid
for civil works for Bridge No.43. All the pile foundation P3. For illustration purpose
other tests on materials like cement, Table 8 shows the results of permeability
aggregates, reinforcement bars, admixture, test conducted for the pile of hybrid pile
water etc were carried out as per their foundation P3. Sample for permeability test
frequencies as specified in the QAPs for the on concrete as per Appendix-G of IRS
civil works for Bridge No.43. For Concrete Bridge Code was taken on
illustration purpose Table 5 shows the 14.03.2018 for the pile no. 31 of hybrid pile
results of sieve analysis of 10mm coarse foundation P3. Test was conducted at
aggregate before the concreting of pile at Quality Control Laboratory at Reasi as per
hybrid pile foundation P3. Appendix-G of IRS CBC on 15.04.2018 and
observations are given in Table 8. The
(ii) Concrete Production at the batching permissible value of permeability is 25 mm.
plant
(v) Milestone Monitoring
The concrete for hybrid pile foundation P3
was produced at the batching plant of The time periods pertaining to the milestone
capacities 30 cum per hour. The moisture achievements during the construction of
content of aggregates was determined and hybrid pile foundation P3 are presented in
the moisture corrections were incorporated Table 10.
in the approved mix design at SSD 12. CONCLUSIONS
conditions. For illustration purpose Table 6
shows the moisture correction for concrete (i) The workability of concrete as
mix of M40 grade before concreting of pile measured by slump test was maintained as
of hybrid pile foundation P3. The calibration per the design mix range/requirements of job
of batching plant is to be done per month as site in terms of the QAP for civil works for
Page 9 of 22

Bridge No. 43. For piles tremie concreting (iii) IS 12070:1985(Reaffirmed in


was done. For top ring beam, bottom pile 1995) Code of Practice for
cap, bottom ring beam and top raft, concrete Design and Construction of
was poured in layers and each layer was Shallow Foundations on Rocks
vibrated as it was placed. (iv) IS 2911-1-2 (2010) Design and
Construction of Pile
(ii) After initial setting of top surface of Foundations-Code of Practice,
concrete, curing was started by sprinkling Part 1: Concrete Piles, Section 2:
with water, covering with wet hessian cloth Bored Cast In -Situ Concrete
or ponding to reduce early dry shrinkage. Piles
After the removal of the formwork the same (v) IS 9012: 1978 (Reaffirmed in
was covered with hessian cloth on the sides 2002) Recommended practice for
and kept wet by sprinkling of water at Shotcreting
regular intervals to maintain the dampness (vi) IS 11309 (1985) Method of
of the hessian cloth throughout the curing Conducting Pull out test on
period. anchor bars and rock bolts
(iii) Quality of concrete used in the (vii) Data as provided at site and in
construction of hybrid pile foundation P3 as quality control laboratory at
determined from the 28 days cube strength Bakkal for Bridge No. 41, 42, 43.
test results as given in Table 7 and by (viii) Quality Assurance Plan(QAP)
permeability test as given in Table 8 was in for Civil Works for Bridge No.43
the acceptable limits. (ix) Method Statement for excavation
of Bridge 43 (A1 to P3) & Salal
13. REFERENCES Station Yard
(x) Report on Additional
(i) Indian Railway Standard
Geotechnical Investigation for
Concrete Bridge Code
Slope Stability of Bridge No. 43
(ii) IS 456:2000 Plain and
on Katra – Dharam section of
Reinforced concrete – Code of
USBRL Project
Practice

Table 1 Details of Hybrid Pile Foundation P3 - I

S.No. DESCRIPTION THEORETICAL QUANTITIES OF


CONCRETE (CUM) REINFORCEMENT (MT)
1 Single Outer Pile 2.821 1.266
2 Single Inner Pile 2.116 0.828
3 Total of all Piles 392.838 169.608
4 Top Ring Beam 18.941 7.019
5 Bottom Cap 262.232 88.56
6 Bottom Ring Beam 16.864 5.111
7 Top Raft 492.509 124.13
Page 10 of 22

Table 2 Details of Hybrid Pile Foundation P3 - II

DESCRIPTION GRADE OF CLEAR COVER TO


CONCRETE REINFORCEMENT
Piles M40 50 mm
Top Ring Beam M40 75 mm
Bottom Cap M35 75 mm
Bottom Ring Beam M40 75 mm
Top Raft M35 75 mm

Table 3 Concrete Mix Design for Hybrid Pile Foundation P3

CONSTITUENT M35 GRADE FOR TOP M40 GRADE FOR PILES M40 GRADE FOR RING
RAFT, BOTTOM PILE CAP BEAMS
QUANTITY (Kg/cum) QUANTITY (Kg/cum) QUANTITY (Kg/cum)
Cement (OPC) 400 480 430
20 mm Coarse Aggregate 710 - 697
10 mm Coarse Aggregate 473 1080 465
Fine Aggregate 759 762 746
Water 152 158 155
Admixture 4.8 5.28 5.16
(Master Polyheed 8630 (Master Polyheed 8630 (Master Polyheed 8630
@1.2%) @ 1.1%) @1.2%)
Free Water Cement Ratio 0.38 0.329 0.36

Table 4 Time Cycle for Construction of Pile

S.No. DESCRIPTION TIME TAKEN


1 Average time for installation of Casing 45 Minutes
2 Average time for drilling of pile 6 Hours
3 Average time for installation of Reinforcement Cage in excavated 4 Hours
bore hole of pile
4 Average time for lowering of tremie pipe to the bottom of the 1 Hour
excavated bore hole of pile
5 Average time for concreting of pile 1 Hour 45 Minutes

Table 5 Sieve Analysis of 10mm Coarse Aggregate done before concreting of Pile

IS SIEVE SIZE WEIGHT CUMULATIVE PERCENTAGE PERCENTAGE IS 383- 1970


(mm) RETAINED WEIGHT CUMULATIVE PASSING LIMIT
(gm) RETAINED WEIGHT
(gm) RETAINED
12.5 0 0 0 100 100
10 512 512 10.24 89.76 85-100
Page 11 of 22

4.75 4006 4518 90.36 9.64 0-20


2.36 442 4960 99.2 0.8 0-5
Pan 40 - - - -

Table 6 Moisture Correction for concrete Mix M40 before concreting at Hybrid Pile Foundation P3

BATCH WEIGHT FOR 1 CEMENT COURSE AGGREGATES FINE WATER ADMIXTURE


M3 IN SSD CONDITION 20 MM 10 MM AGGREGATE
480 0 1080 762 158 5.28
BATCH WEIGHT FOR 1
M3 AFTER MOISTURE
CORRECTION
Water Absorption(%) - 0.36 0.52 1.28 - -
Moisture Content (%) - 0 0.2 2.8 - -
Moisture - -0.36 -0.32 1.52 - -
Adjustment(%)
Difference in Weight - 0 -3.46 11.58 - -
due to Moisture
Content (Kg)
Corrected Batch 480 0 1076 774 150 5.28
Quantity Kg/m3

Table 7 Cube Strength Test Results for the Hybrid Pile Foundation P3

DESCRIPTION NUMBER OF RANGE OF MEAN OF STANDARD


SAMPLES TAKEN COMPRESSIVE COMPRESSIVE DEVIATION OF
DURING ENTIRE STRENGTH STRENGTH COMPRESSIVE
CONCRETING VALUES VALUES STRENGTH VALUES
OBSERVED(MPa) OBSERVED (MPa) OBSERVED (MPa)
Piles (28 Days) 153 42.58 – 55.70 51.06 2.50
Piles (7-Days) 153 32.14 – 44.5 39.42 2.18
Top Ring beam 3 53.73 - 55.55 54.37 1.02
Bottom Cap 9 46.17-52.6 49.26 2.00
Bottom Ring 3 52.22-53.57 52.74 0.73
beam
Top Raft 10 48.69-50.8 49.88 0.69
Page 12 of 22

Table 8 Permeability test result for Pile No. 31 of Hybrid Pile Foundation P3

SPECIMEN TEST TIME TEST END TIME PRESSURE PERMEABILITY AVERAGE


NUMBER START DATE APPLIED(BAR) MEASURED VALUE
DATE VALUE (mm) (mm)
1 11.04.2018 16.00 15.04.2018 16.00 1st 48 Hours: 1 6
Bar
2 11.04.2018 16.00 15.04.2018 16.00 Next 24 Hours: 3 8
6.67
Bar
3 11.04.2018 16.00 15.04.2018 16.00 Next 24 Hours: 7 6
Bar

Table 10 Milestone achievements in construction of Hybrid Pile Foundation P3

S.No. DESCRIPTION DATE OF DATE OF NUMBER OF


STARTING COMPLETION DAYS TAKEN
1 Excavation for Hybrid Pile Foundation P3 01.10.2017 16.02.2018 51
2 Shotcrete 06.10.2017 21.02.2018 50
3 Rock Bolting 03.10.2017 18.02.2018 49
4 Piling for Hybrid Pile Foundation P3 17.02.2018 15.05.2018 88
5 Chipping of Outer Piles (98 no.s) 15.05.2018 31.05.2018 16
6 Excavation upto bottom level of top ring beam 15.05.2018 20.05.2018 5
7 Construction of top ring beam 31.05.2018 10.06.2018 11
8 Excavation upto bottom of bottom pile cap 22.06.2018 18.07.2018 27
9 Chipping of inner piles (55 no.s) 19.07.2018 25.07.2018 6
10 Construction of bottom pile cap 26.07.2018 18.08.2018 23
11 Construction of bottom ring beam 19.08.2019 21.08.2018 2
12 PCC infill from top of bottom pile cap and upto 20.08.2018 30.08.2018 10
the bottom of top raft
13 Construction of top raft 31.08.2018 30.09.2018 30
Page 13 of 22

Table 9 Survey Coordinates of Piles of Hybrid Pile Foundation P3


Page 14 of 22

Fig.1 Hybrid Pile Foundation P3 in Plan Fig.2 Hybrid Pile Foundation P3 in Elevation

Fig.3 Plan at the top raft level of Hybrid Pile Foundation P3 Fig.4 Plan at the Ring beam level of Hybrid Pile Foundation
P3

Fig.5 Excavation in Cutting for Hybrid Pile Foundation P3 in Fig.6 Excavation in Cutting for Hybrid Pile Foundation P3 in
Plan Elevation
Page 15 of 22

Fig. 7 Numbering Sequence for drilling and construction of Fig. 8 3D View of drilled piles sought to be achieved
piles
Page 16 of 22

Picture 1 Geological L section from Hybrid pile foundations A1 – P3

Picture 2 Geological Cross Section at Hybrid Pile Picture 3 Excavation in Progress at Hybrid Pile
Foundation P3 Foundation P3 Location

Picture 4 Ground Level reached for starting Picture 5 Control Pillar -I at Hybrid Pile
drilling of piles at Hybrid Pile Foundation P3 Foundation P3 Location
Page 17 of 22

Picture 6 Control Pillar -II at Hybrid Pile Picture 7 Drilling Rig with Air Compressor, water
Foundation P3 Location tank mounted on Truck

Picture 8 Fabrication Yard for Reinforcement Cage Picture 9 Fabrication of Spiral Reinforcement of
of Piles of Hybrid Pile Foundation P3 Piles

Picture 10 Inhibitor Solution Application to Picture 11 Transportation of Reinforcement Cage


Reinforcement at Fabrication Yard for Piles of Pile from Fabrication Yard to Work Site
Page 18 of 22

Picture 12 Lowering of Reinforcement Cage into Picture 13 Installation of Reinforcement Cage into
the Drilled Hole of Pile the Drilled Hole of Pile in Progress

Picture 14 Tremie Pipe Attached to hopper at the Picture 15 Preparations for Tremie Concreting of
top used for Concreting of Piles Pile in Progress at Hybrid Pile Foundation P3

Picture 16 Tremie Concreting for Pile in Progress Picture 17 Concrete Cube Samples taken during
at Hybrid Pile Foundation P3 Tremie Concreting of Pile
Page 19 of 22

Picture 18 Excavation in Progress around Hybrid Picture 19 Chipping of Concrete of Outer Piles in
Pile Foundation P3 after construction of all piles Progress using Jack Hammer

Picture 20 Concreting in Progress for top ring Picture 21 View in Elevation of completed top
beam of Hybrid Pile Foundation P3 ring beam of Hybrid Pile Foundation P3

Picture 22 Excavation in Progress inside the top Picture 23 Excavation in Progress inside the top
ring beam of Hybrid Pile Foundation P3-I ring beam of Hybrid Pile Foundation P3-II
Page 20 of 22

Picture 24 Excavation in Progress inside the top Picture 25 Chipping of Concrete of Inner Piles in
ring beam of Hybrid Pile Foundation P3-III Progress

Picture 26 Arrangements for Reinforcement Picture 27 Transportation of Reinforcement of


Bending Bottom Pile Cap

Picture 28 Reinforcement Binding in Progress at Picture 29 Reinforcement Binding in Progress at


Bottom Cap-I Bottom Cap-II
Page 21 of 22

Picture 30 Reinforcement Binding Completed at Picture 31 Concreting in Progress at Bottom Pile


Bottom Pile Cap Cap

Picture 32 PCC infilling in Progress at Hybrid Pile Picture 33 PCC infilling Completed at Hybrid Pile
Foundation P3 Foundation P3

Picture 34 Reinforcement Binding in Progress at Picture 35 Reinforcement Binding in Progress at


Top Raft of Hybrid Pile Foundation P3 Top Raft of Hybrid Pile Foundation P3
Page 22 of 22

Picture 36 Construction of top raft of Hybrid Pile


Foundation P3 Completed

You might also like