Professional Documents
Culture Documents
Evaluation - of - Design - Capacity - of - Bored High Strain
Evaluation - of - Design - Capacity - of - Bored High Strain
Evaluation - of - Design - Capacity - of - Bored High Strain
Dynamic Test
Nurly Gofar
Faculty of Civil Engineering, Universiti Teknologi Malaysia, Skudai, Johor, Malaysia
Michael Angelo
Geopave Testing Sdn Bhd, Selangor, Malaysia
ABSTRACT: In general, piles are designed analytically based on the load that is transferred from the
structure to the soil, and load tests are performed to verify the design capacity. Up to recently, static load test
is still considered as the most reliable method even though it is not practical and costly; hence it could be
done on limited numbers of pile only. High strain dynamic testing offers a less expensive alternative for pile
load test. Studies have been done to evaluate the performance of dynamic testing in evaluating the design
capacity of displacement piles. This paper focuses on the application of high strain dynamic testing in
evaluating the capacity of replacement or bored piles based on several cases in Malaysia. The study shows
that the high strain dynamic tests, if performed and interpreted correctly, can provide reasonable agreement
with the results of static load test in terms of settlement and of design capacity. Higher design capacity was
predicted by dynamic test, but the discrepancy is mainly due to the time interval between the casting of the
pile and the execution of the test which affect the development of shaft resistance in the pile. The different
contribution of friction resistance along the pile shaft observed by both tests is more dependent on the load
transfer mechanism related to the test rather than on the effect of soil setup.
Key words: pile design capacity, bored pile, dynamic pile testing
ABSTRAK: Pada umumnya pondasi tiang direncanakan secara analitis berdasarkan beban yang disalurkan
dari struktur kepada tanah dan uji beban dilakukan untuk memverifikasi kapasitas tiang. Uji beban statis
masih dianggap sebagai metode standar walaupun metode ini tidak parktis dan mahal, sehingga hanya dapat
dilakukan pada beberapa tiang saja. Uji beban dinamis merupakan alternatif yang lebih murah untuk
pengujian kapasitas beban tiang. Perbandingan antara hasil uji beban dinamis dan uji beban statis telah
dilakukan, terutama pada tiang pancang. Makalah ini membincangkan penggunaan uji beban dinamis pada
tiang bor berdasarkan beberapa studi kasus di Malaysia. Hasil studi menunjukkan bahwa uji beban dinamis,
apabila dilakukan dan diinterpretasikan dengan baik, dapat memberikan hasil yang mendekati hasil uji beban
statis dalam hal kapasitas beban dan penurunan. Kapasitas yang lebih tinggi diberikan oleh uji beban dinamis
karena perbedaan waktu pemasangan tiang dan waktu pengujian, dimana uji beban statis dilakukan lebih awal
daripada uji beban dinamis. Kontribusi beban friksi yang berbeda berdasarkan hasil kedua uji beban .lebih
disebabkan oleh mekanisma penyaluran beban daripada pengaruh peningkatan kekuatan tanah.
Kata Kunci : kapasitas disain tiang, tiang bor, uji beban dinamis
measured in the field during driving and is currently RL47.5 m (Existing GL)
the most used program to evaluate the pile capacity 0.75 m VWSG Level A (Lev A, RL 46.75 m)
from high strain dynamic testing data.
A-9 sensor 1a & 1b
Eventhough the test and the analysis methods
were originally developed for driven pile, their
application for drilled pile was made possible by re-
strike test. The ability of the high strain dynamic
test to accurately predict static capacity for dynamic
pile testing has been the subject of many studies.
3.0 m VWSG Level B (Lev B, RL 44.5 m)
Previous studies such as Siedel and Rausche (1984),
Jianren and Shihong (1992) have demonstrated good
A-9 sensor 2a & 2b
correlation of CAPWAP signal matching results on
dynamically re-strike tests with that of static load 4.0 m VWSG Level C (Lev C, RL 43.5 m)
and cast in-situ piles. Accuracy is slightly better for 6.0 m VWSG Level E (Lev E, RL 41.5 m)
driven pile as compared to bored piles.
A-9 sensor 5a & 5b
This paper focuses on the evaluation of the 6.5 m VWSG Level F (Lev F, RL 41.0 m)
dynamic re-strike test and CAPWAP analysis done
on the bored piles by comparing the results with Pile toe at 7.0 m depth (RL 40.5m)
those obtained from the static load test. The
comparisons were made based on: the distribution of Figure 1 Typical diagram of instrumented bored
load carried at the pile base and along the pile shaft, piles used in this study
Table 4 Results of Dynamic Load Test and Pile capacity Pile 5(JB) >16,573 14,750 17,504 25
Note: *) Pile failed during static load test
Settlement (mm) Pile
Pile Capacity
Reference Table 6 Pile Capacity and Shaft and End bearing contribution
WL TL=2WL (kN) to pile capacity (Static Load Test)
Pile 1(S) 2.3 4.8 9,429
Pile 2(S) 2.3 6.3 5,750 Static Load Test
Pile Pile Shaft End
Pile 3(S) 2.4 5.1 9,550 Capacity Friction Bearing
Reference
Pile 4(JB) 5.3 10.7 22,861 (kN) (%) (%)
Pile 5(JB) 5.3 12.0 17,504 Pile 1(S) 8,000 65 35
Pile 2(S) 7,150 64 36
Pile 3(S) 7,650 92 8
4. DISCUSSION
Pile 4(JB) 17,500 99 1
Table 5 summarizes the comparison between the
Pile 5(JB) 14,750 88 12
actual failure load and the pile capacity predicted by
Davisson’s method from static load test and
CAPWAP analysis from dynamic load test. It is Table 7 Pile Capacity and Shaft and End bearing contribution
observed the dynamic test gives an apparently higher to pile capacity (Dynamic Load Test)
capacity compare to the static load test maybe due to
the time of execution. The last column shows the PDA Test
time interval between the executions of both tests. Pile Pile Shaft End
The dynamic test on Pile 4 was done 262 days after Reference Capacity Friction Bearing
the static load test and the predicted capacity of pile (kN) (%) (%)
is 30% higher than the capacity obtained from static
load test. Other piles, except Pile 2 which failed Pile 1(S) 9,429 36 64
during static load test, exhibit 20% higher predicted Pile 2(S) 5,750 *
45 55
capacity from dynamic load test.
It should be noted that the pile capacity presented Pile 3(S) 9,550 53 47
in Table 5 are the ultimate capacity of the pile which Pile 4(JB) 22,861 89 11
is contributed by the end bearing and shaft friction.
The contribution of each mechanism can be Pile 5(JB) 17,504 70 30
estimated based on the distribution of shaft friction Note: *) Pile failed during static load test
recorded by load cell installed at different level on
the pile during static load test (Figure 1), while Table 6 shows that the contribution of the shaft
derivation of shaft friction distribution from friction for pile at Site 1 (S), is higher compared to
dynamic testing is made by the CAPWAP analysis end bearing. Observation showed that this scenario
based on wave matching technique. The occurred due to large movement at the base of the
contribution of the shaft friction and the end bearing pile. The pile load was fully mobilized causing the
of the pile obtained from both static load test and toe to displace. Since the base of the pile started to
dynamic test are presented in Table 6 and 7 displace, the corresponding load would be taken by
respectively. the shaft.
PERTEMUAN ILMIAH TAHUNAN-X HATTI, 6-7Desember 2006 150
The scenario is different for Site 2 where the load test on pile at site 2 (JB) compared to the
piles are long. Most of the load applied is resisted results of static load test..
by the shaft and only a small part is transferred to
the base. The development of shaft friction is
5. CONCLUSIONS
mainly due to the cohesion of the soil.
The dynamic tests were conducted based on the Predictions of pile capacity based on static load
force induced from the ram. Even though the force test and dynamic test have been performed in this
can mobilize the shaft resistance, the major study to arrive at several conclusions.
contribution of the resistance was transferred to the The pile capacity obtained from CAPWAP
base. The shaft resistance observed by the dynamic Analysis utilized in the PDA test is generally higher
load test is lower compared to that obtained from the than that estimated by Davisson’s Method based on
static load test. Therefore, the load was not able to
the results of static load test due to the time of
cause movement at the pile base; hence the
contribution of end bearing is larger. This is the case testing.
for piles in Site 1 (S). The results of dynamic test Dynamic load test gives more settlement at
agree with that of static load test where major higher load as compared to due to the mechanism of
contributions of pile resistance for piles in Site 2 load transfer.
(JB) are from shaft resistance even though the shaft The contribution of friction resistance along the
resistance observed by the dynamic load test is pile shaft observed by both tests is more dependent
slightly lower. on the load transfer mechanism related to the test
Table 7 shows the comparison between the rather than on the effect of soil setup.
settlement predicted by the static load test and the The relationship between the results of static
dynamic test. load test and dynamic load test is site specific
because it depends on the load transfer mechanism,
Table 7 Comparison on settlement predicted by static load test
the types of pile, the soil properties and other
and dynamic test
factors.
Hence, only after correlation with the static load test,
Settlement (mm)
more dynamic test can be carried out as quality
Pile SLT PDA
Referenc
control to save cost and expedite construction in
W TL=2W W TL=2WL large project. Higher factor of safety should be
e
L L L applied to the results of dynamic load test in the
Pile 1(S) 2.3 4.8 absence of static load test results.
2.3 4.5
Pile 2(S) 2.0 4.9 2.3 6.3
Pile 3(S) 3.5 9.8 2.4 5.1 REFERENCES
Pile 4(JB) 6.5 15.0 5.3 10.7
Beim, J.W., de Rosa, R.L. (2004). Comparison of Static and
Pile 5(JB) 7.0 52.0 5.3 12.0 Dynamic Load Tests Results. Proc. 7th Intl. Conf. on the
Application of Stresswave Theory to Piles, Kuala Lumpur
Chin Y.K., Tan S.L. and Tan S.B. (1985). Ultimate Load Tests
For piles in Site 1 (S), it is observed that under on Instrumented Bored Piles in Singapore Old Alluvium.
working load, the settlements predicted from the Proc. 8th South East Asia Geotech. Conf. Kuala Lumpur.
dynamic tests is less compared to that of static load Coduto DP. (1994) Foundation Design, Principles and
test. On the other hand, under test load of twice the Practices, Prentice Hall.
working load, the settlement predicted by the Fellenius, B. H. (1980). The Analysis of Results from Routine
dynamic test is higher than that obtained from static Pile Load Test. Ground Engineering.
load test. This situation support the conclusion
Fellenius, B. H. (1990). Static or Dynamic Test – Which To
made for the pile capacity and the load transfer Trust Geotechnical News Magazines, December 1990,
mechanism stated previously. Higher force is Vol. 8, No.4.
required from dynamic test to mobilize the stress at
the base of the pile resulting in less settlement Goble Rausche Likins and Associates (1996). CAPWAP
Introduction to Dynamic Pile Testing Methods. Pile
obtained from test under working load but more Dynamic Inc.
settlement under higher load. Less settlement was Jianren D. and Shihong Z. (1992) The Appraisal of Results
obtained from dynamic load test on piles at Site 2 from PDA High Strain Dynamic Tests on Large and Long
(JB) because more load is required to mobilize the Drilled Pile. Proc. 4th Intl. Conf. on Application of Stress
failure at pile base. This agrees with the results of Wave Theory to Piles, The Hague.
the dynamic pile testing in term of pile capacity. Likins, G and Rausche, F. (2004). Correlation of CAPWAP
Higher pile capacity was obtained from dynamic with Static Load Test. Proc. 7th Intl. Conf. on the