Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/325217149

Optimal Planning of PV Inverter in the Presence of Capacitor Bank in Medium-


Voltage Distribution Networks

Conference Paper · May 2018


DOI: 10.1109/ICHQP.2018.8378862

CITATIONS READS

0 290

3 authors, including:

Abdelfatah Ali David Raisz


South Valley University Budapest University of Technology and Economics
38 PUBLICATIONS   206 CITATIONS    73 PUBLICATIONS   453 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Electricity Market Simulation View project

Evaluation and Mitigation of Electric Vehicles Charging Impacts on Distribution Networks View project

All content following this page was uploaded by Abdelfatah Ali on 20 July 2018.

The user has requested enhancement of the downloaded file.


Optimal Planning of PV Inverter in the Presence of
Capacitor Bank in Medium-Voltage Distribution
Networks
Abdelfatah Ali1,2 David Raisz2 Karar Mahmoud3
1Department 2Department of Electric Power Engineering 3Department
of Electrical Engineering of Electrical Engineering
Faculty of Engineering Faculty of Electrical Engineering and Informatics Faculty of Engineering
South Valley University Budapest University of Technology and Economics Aswan University
83523 Qena, Egypt 1111 Budapest, Hungary 81542 Aswan, Egypt
E-mail: abdelfatah.mohamed@vet.bme.hu E-mail: raisz.david@vet.bme.hu E-mail: karar.alnagar@aswu.edu.eg

Abstract—As the penetration level of the photovoltaic (PV) distribution networks beside load centers. One of the major
system increases over the coming decades, reverse power flows concerns about PV is voltage regulation problems, i.e.,
on the distribution feeder will happen and the associated voltage voltage rise/drop. Such voltage deviations from the nominal
rise might lead to violations of voltage limits. The severity of the values have a negative impact on the domestic/industrial
voltage regulation problem depends on the relative size and
loads and affect their functionality [6]–[12]. The traditional
location of PV system, loads, and the distribution feeder
topology. This paper proposes an approach to solve the voltage voltage control devices, e.g., capacitors, often face many
rise problem associated with PV system and to improve the total operational problems when employed to solve the voltage
voltage deviation by optimally increasing the capacity of the PV regulation problems with PV. The reason for this behavior is
inverter over the capacity of the PV modules in the presence of that the output power of PV is highly fluctuated and so the
capacitor banks. An optimization model is constructed to shunt capacitors are required to be switched frequently with
calculate the optimal inverter capacity with minimizing the cost high rate.
of PV inverter as well as the total voltage deviation on the
distribution network. The overall system constraints are The inverters of PV systems are often recommended to
considered in the optimization model. The proposed approach is work at unity power factor, in other words, to supply only
tested using the IEEE 119-node distribution network. The active power to the distribution system. However, several
effectiveness of the proposed approach is demonstrated by recent research studies have investigated the case when the
calculating the optimal capacity of the PV inverter for PV inverter is allowed to inject/absorb reactive power [13]–
mitigating the voltage rise problem and reducing the total [18]. It is demonstrated that the latter control scheme of the
voltage deviation.
inverter can greatly solve the voltage regulation locally at the
Index Terms-- Distribution networks, photovoltaic (PV), optimal point of common connection (PCC). As a result, the stress on
inverter capacity, voltage rise, capacitor bank, reactive power the conventional devices of voltage control will be
capability. significantly reduced. However, the spare capacity of the PV
inverter during high generation occasions (i.e., sunny
I. INTRODUCTION conditions) may not be sufficient to supply reactive power.
To release the capacity of PV inverter during such event, a
Supplying electrical power to consumers was typically common practice is to increase the capacity of the interfaced
based on centralized generation stations connected at the inverter over the capacity of the modules of PV systems. As a
transmission system level. Recently, small-size distributed result, the cost of the PV system will be increased. Therefore,
generations have been interconnected at the distribution an optimal capacity of the PV inverter has to be determined
network level to supply electricity locally. This modification during the planning stage with considering the cost as well as
in the infrastructure of the power system has many benefits, the benefits. In addition, the capacity of capacitors must be
including: reducing losses, increasing supply reliability, and considered in the optimization problem.
improving voltage profile in distribution networks [1]–[6].
In this paper, the capacity of PV inverter is optimally
Photovoltaic (PV) is one of the most common types of DG, planned in the presence of capacitor banks in MV distribution
and its cost is being dramatically decreased. PV units are networks. To do so, an optimization model is constructed in
distributed in low-voltage (LV) and medium-voltage (MV) which the total voltage deviation and the cost of the capacity

978-1-5386-0517-2/18/$31.00 ©2018 IEEE


of PV inverter are considered as the objective function to be new capacity of PV inverter. The proposed optimization
minimized. The equality/inequality constraints of the model is mathematically formulated as follows:
distribution network and the PV units are considered. To
solve the optimization model, the AMPL solver is employed. min f = f1 + αf 2 (1)
The proposed planning method of the PV inverter is tested on
the 119-bus distribution network. The results demonstrate the NB
(Vi − VNi )2
effectiveness of the proposed method to properly plan the f1 = VD = 
i =1
VNi
(2)
capacity of the PV inverter for the purpose of preventing the
voltage regulation problems with PV system. 2
f 2 = a + bSinv + cSinv (3)
The rest of this paper is organized as follows. Section II
describes the voltage regulation problem with PV system. 2
Sinv = Pinv 2
+ Qinv (4)
The optimization model for calculating the optimal capacity
of PV inverter is formulated in Section III. Sections IV and V where α, NB, Vi, and VNi are a scaling factor, number of
present the simulation results and conclusions, respectively. nodes, voltage at node i, and nominal voltage at node i
(VNi=1), respectively. Sin, Pinv, and Qinv are the PV inverter
II. PROBLEM DESCRIPTION capacity, active power of PV inverter, and reactive power of
PV inverter, respectively.
High PV penetration in distribution networks can cause
several problems, such as reverse power flow, interaction B. Constraints
with capacitor banks and voltage regulators, and excessive
losses. In many cases, it is observed that specific parts of the 1) Equality Constraints
distribution networks undergo reverse power flow due to the
NB
high penetration of PV or high PV power generation,
especially during time periods with low load demand. This
Pgi − PDi − Vi V [G
j =1
j ij ]
cos(δ ij ) + Bij sin(δ ij ) = 0 ∀i (5)
results in voltage rises and increases in the power losses.
Thus, appropriate consideration should be taken into account NB
about these problems during the planning of active
distribution systems.
Qgi − QDi − Vi V [G
j =1
j ij sin(δ ij ) − Bij ]
cos(δ ij ) = 0 ∀i (6)

The common method for regulating voltage in


V1 = 1 , δ1 = 0 (7)
transmission networks is reactive power control, while the
reactive power has a relatively lower impact on voltage where Pgi, Qgi are the active and reactive power generated of
regulation in the distribution networks due to the high R/X at node i, respectively; PDi and QDi are the active and reactive
ratio. Nevertheless, appropriate reactive power control can power demand at node i, respectively; Gij and Bij are the
regulate the voltage in the distribution networks [19], [20]. conductance and susceptance of the line i-j, respectively.
For this purpose, the capacitor banks and spare capacity of
2) Inequality Constraints
PV inverters can be used for reactive power
injection/absorption to regulate the voltages in the min max
Qinv ≤ Qinv ≤ Qinv (8)
distribution networks. During high irradiance and PV
generation levels, the reactive power capacity of PV inverter
reduces. Once the capacity limit is reached, voltage rise V min ≤ VPCC ≤ V max (9)
prevention by the reactive power of PV inverter will not be
S rated ≤ Sinv ≤ 2 S rated (10)
possible. In this situation, the capacity of PV inverter could
be increased to allow further reactive power capability in where Qinv min max
, Qinv , VPCC, Vmin, Vmax, and Sreated are the
which the new capacity of the PV inverter should be
optimally calculated. minimum reactive power limit of PV inverter, maximum
reactive power limit of PV inverter, voltage at the point of
III. PROBLEM FORMULATION common coupling (PCC), minimum voltage limit at PCC,
maximum voltage limit at PCC, and rated capacity of PV
A. Objective function inverter, respectively. The optimization model described in
this section is solved by using AMPL solver.
At high PV generation, the PV inverter is fully loaded.
Therefore, there is no spare capacity for reactive power IV. RESULTS AND DISCUSSIONS
injection/absorption. For further reactive power capability,
the capacity of PV inverter could be increased. The new A 119-node radial distribution network (Figure 1) has been
capacity of PV inverter should be optimally calculated with used to validate the proposed approach. It is a balanced three-
considering the impact of the capacitor bank in the network. phase radial network consisting of 119 nodes with 11 kV as
Two objective functions are considered in this work as operating voltage level at 100 MVA base. The total active
follows: 1) total voltage deviation (VD), and 2) cost of the and reactive loads are 22.710 MW and 17.041 Mvar,
13 14 15 16 17 18
Case 1 Case 2 Case 3
Figure 1. Single line diagram of 119-node distribution network (Node
11 12
1.3
numbers
19 20 21are22reordered).
23 24 25 26 27 28
1.25

3 5 6 7 8 9 10 1.2

Voltage at PCC (pu)


1.15
4 39 40 41 42 43 44 45 46 47
1.1
Vmax
1.05
29 30 31 32 33 34 35 36 48 49 50 51 52 53 54 55
1

37 38 0.95

0.9

102
106
110
114
118
2
6
10
14
18
22
26
30
34
38
42
46
50
54
58
62
66
70
74
78
82
86
90
94
98
56 57 58 59 60 61 62 63

PV location
97 98 99 100
Figure 2. Voltage profile at PCC of the three cases at different
locations of PV.
1 2 90 91 92 93 94 95 96

Case 1 Case 2 Case 3


64 65 66 67 68 69 70 71 72 73 74 75 76 77 78
S/S 0.55
0.5
Capacitor bank
0.45

Voltage deviation (pu)


79 80 81 82 83 84 85 86
0.4
0.35
87 88 89
0.3

101 102 103 104 105 106 107 108 109 110 111 113 114 0.25
0.2
115 116 117 118 119 112 0.15
0.1
2
6

102
106
110
114
118
10
14
18
22
26
30
34
38
42
46
50
54
58
62
66
70
74
78
82
86
90
94
98
Figure 1. Single line diagram of 119-node distribution network (Node PV location
numbers are reordered).
Figure 3. Total voltage deviation of the three cases at different
respectively. The initial active and reactive power losses at locations of PV.
nominal loading are 1.298 MW and 0.979 Mvar, respectively.
It is observed that the minimum node voltage magnitude of • Case 3: the PV inverter has reactive power
0.8688 p.u occurs at node number 78 at nominal load capability and the impact of the capacitor bank is
condition. The complete data of the network are obtained considered.
from [21]. The node numbers of the network are renumbered Case 1 represents the base case in which PV inverter works at
and the tie switches (normally open) are removed from the unity power factor, while Case 2 considers the reactive power
network. capability of PV inverter without considering the capacitor
bank. Because PV inverter is fully loaded, its capacity could
A capacitor bank with a capacity of 5 Mvar is assumed to
be optimally increased to allow more reactive power
be connected to node 69. The simulation results are
capability. Both reactive power capability of PV inverter and
performed with changing the location of PV system. The
capacitor bank are considered in Case 3.
penetration level of PV system is assumed to be 50% with
respect to the total load. The analysis is performed at mid-day The voltage profiles at PCC for different cases are shown
in which the generated power of PV system is equal to the in Figure 2 (PV system is connected to one node in the whole
rated capacity of PV inverter (PPV=Srated). Note that the lower network). As shown in Figure 2, the voltage at PCC violates
and upper limits of PCC voltage are 0.95 p.u. and 1.05 p.u., the upper limit at many locations of the PV system in the base
respectively [22]. These thresholds can be changed according case. However, the voltage at PCC is within limits at some
to the region (e.g., in Europe, according to EN 50160, the locations (e.g., nodes 1-14, 29-40, 64-68, and 101-105). The
voltage thresholds are 0.9 and 1.1 p.u). To demonstrate the voltage rise at PCC is completely mitigated after considering
effectiveness of the proposed approach, the following cases the reactive power capability of PV inverter or both reactive
are studied in this paper. power capability and capacitor bank (Case 2, Case 3).
• Case 1: this base case is simulated based on the The total voltage deviation at different locations for the
original state of distribution system without three study cases is shown in Figure 3. Figure 3 shows that
considering neither capacitor bank nor reactive the total voltage deviation in Case 2 is reduced at many
power capability of PV inverter. locations of the PV system, while in Case 3 it is significantly
• Case 2: the PV inverter has reactive power reduced at all locations of the PV system. It demonstrates that
capability without considering the capacitor bank. using both optimal reactive power of PV inverter and
Figure 5 shows the optimal capacity of PV inverter with
Case 1 Case 2 Case 3
respect to the rated capacity. This figure illustrates that if the
0.6
PV system is connected to certain locations, e.g., nodes 2-13,
0.5 29, 56, 67, the increase in PV inverter capacity will not be
required where PV inverter capacity is 100%. On the other
Objective function

0.4
hand, when PV system is connected to other nodes, the
0.3 capacity of PV inverter is increased in Cases 2 and 3 to
reduce the total voltage deviations. Note that at location 65,
0.2
the capacity of PV inverter is reduced from 199.3% to
0.1 132.1% when the capacitor bank is considered (Case 3). The
capacity of PV inverter with considering the capacitor bank
0
may be larger than that without considering the capacitor

102
106
110
114
118
2
6
10
14
18
22
26
30
34
38
42
46
50
54
58
62
66
70
74
78
82
86
90
94
98
PV location bank in some locations, but the improvement of total voltage
deviation and reducing of the objective function are better
Figure 4. The values of the objective function of the three cases at
different locations of when the capacitor bank is considered as shown in Figures 2
PV and 3.
Case 1 Case 2 Case 3
The optimal injected/absorbed reactive power of PV
220
inverter reactive is described in Figure 6 for all cases. As
200 shown in the figure, the negative values imply that PV
inverter injects reactive power into the distribution network to
Inverter capacity (%)

180 improve the voltage deviation, while the positive values


160
imply that PV inverter absorbs reactive power from the
distribution network to alleviate the voltage rise at PCC and
140 to improve the total voltage deviation.
120 This analysis demonstrates that the optimal capacity of PV
inverter and the improvement in the voltage deviation are
100
significantly varies depending on the PV location and the
102
106
110
114
118
2
6
10
14
18
22
26
30
34
38
42
46
50
54
58
62
66
70
74
78
82
86
90
94
98

PV location capacitor bank consideration. Therefore, it is important to


Figure 5. Optimal capacity of PV inverter of the three cases at different
compute the capacity of the PV inverter optimally using the
locations of PV. proposed formulation for reducing the voltage deviation with
minimum cost. We can note that the optimal location of PV
Case 1 Case 2 Case 3 system and the optimal capacity of PV inverter without
15 considering capacitor bank are node 68 and 101.5%,
Reactive power absorbtion
10 respectively; while they are node 35 and 100%, respectively,
5 when the capacitor bank is considered. The percentage of
Reactive power (Mvar)

0 total voltage deviation reduction (VDR) with and without


-5
considering capacitor bank (Case 2 and Case 3) can be
described as follows:
-10
Reactive power injection
-15
VDbase − VDn
-20 VDR(%) = × 100 (11)
VDn
-25
102
106
110
114
118
2
6
10
14
18
22
26
30
34
38
42
46
50
54
58
62
66
70
74
78
82
86
90
94
98

where VDbase and VDn are the total voltage deviation at the
PV location
base case and total voltage deviation at Case 2/Case 3,
Figure 6. Optimal reactive power of PV inverter of the three cases at respectively. Therefore, VDR for Cases 2 and 3 at optimal
different locations of PV.
locations are 2.7% and 59.5%, respectively. This implies that
capacitor bank can do a better job in minimizing the total the capacitor bank has a significant impact in reducing the
voltage deviation than only using the reactive power of PV total voltage deviation.
inverter alone.
V. CONCLUSIONS
Figure 4 illustrates the objective function values at
different locations for all the three study cases. The figure This paper has presented an approach for the optimal
shows that the objective function in case 3 has lower values planning of the inverter of PV systems to solve the voltage
than Cases 1 and 2, where the objective function values in regulation problems with the intermittent PV generation. The
Case 2 is lower than that in Case 1. It is demonstrated that traditional voltage control device (capacitor bank) is
considering the capacitor bank has a significant role in considered in the proposed optimization model. This
reducing the objective function. optimization model has been built to compute the optimal
inverter capacity with reducing the cost of PV inverter as well [7] H. L. Willis and W. G. Scott, Distributed power generation : planning
and evaluation. Marcel Dekker, 2000.
as the total voltage deviation of the distribution network. The
[8] K. Mahmoud, N. Yorino, and A. Ahmed, “Optimal Distributed
proposed approach has been tested on the IEEE 119-node Generation Allocation in Distribution Systems for Loss Minimization,”
distribution network. The calculated results demonstrate the IEEE Trans. Power Syst., vol. 31, no. 2, pp. 960–969, Mar. 2016.
efficiency of the proposed approach for calculating an [9] A. Gómez Expósito, A. J. Conejo, and C. Cañizares, Electric energy
systems : analysis and operation. CRC Press, 2009.
optimal capacity of the PV inverter which completely solve [10] A. Y. Elrayyah, M. Z. C. Wanik, and A. Bouselham, “Simplified
the voltage regulation problems caused by PV. Approach to Analyze Voltage Rise in LV Systems With PV
It has to be noted, that this paper exclusively focuses on a Installations Using Equivalent Power Systems Diagrams,” IEEE Trans.
Power Deliv., vol. 32, no. 4, pp. 2140–2149, Aug. 2017.
technical solution, regardless of the underlying regulatory and [11] G. De Carne, G. Buticchi, Z.-X. Zou, and M. Liserre, “Reverse power
business model. Further work should include a broader flow control in a ST-fed distribution grid,” IEEE Trans. Smart Grid,
context, in which the financial or regulatory motivation of the pp. 1–1, 2017.
players should be highlighted or elaborated. (e.g. why should [12] A. Ali, D. Raisz, and K. Mahmoud, “Optimal scheduling of electric
vehicles considering uncertain RES generation using interval
a PV-owner overrate its PV inverter, how can a DSO optimization,” Electr. Eng., pp. 1–13, Sep. 2017.
motivate the grid users to take part in the voltage regulation [13] R. K. Varma, S. A. Rahman, and T. Vanderheide, “New Control of PV
problem.) Solar Farm as STATCOM (PV-STATCOM) for Increasing Grid Power
Transmission Limits During Night and Day,” IEEE Trans. Power
VI. ACKNOWLEDGMENT Deliv., vol. 30, no. 2, pp. 755–763, Apr. 2015.
[14] K. Turitsyn, P. Sulc, S. Backhaus, and M. Chertkov, “Options for
Project no. FIEK_16-1-2016-0007 has been implemented Control of Reactive Power by Distributed Photovoltaic Generators,”
Proc. IEEE, vol. 99, no. 6, pp. 1063–1073, Jun. 2011.
with the support provided from the National Research, [15] K. Turitsyn, P. Sulc, S. Backhaus, and M. Chertkov, “Local Control of
Development and Innovation Fund of Hungary, financed Reactive Power by Distributed Photovoltaic Generators,” in 2010 First
under the FIEK_16 funding scheme. IEEE International Conference on Smart Grid Communications, 2010,
The Authors wish to thank Péter Sőrés and Bálint Hartmann pp. 79–84.
[16] I. S. Lelis, I. A. Drougakis, E. E. Pompodakis, and M. C. Alexiadis,
for their valuable comments. “Photovoltaic systems in low-voltage networks and overvoltage
VII. REFERENCES correction with reactive power control,” IET Renew. Power Gener., vol.
10, no. 3, pp. 410–417, Mar. 2016.
[1] P. Mohammadi and S. Mehraeen, “Challenges of PV Integration in [17] M. Farivar, R. Neal, C. Clarke, and S. Low, “Optimal inverter VAR
Low-Voltage Secondary Networks,” IEEE Trans. Power Deliv., vol. control in distribution systems with high PV penetration,” in 2012
32, no. 1, pp. 525–535, Feb. 2017. IEEE Power and Energy Society General Meeting, 2012, pp. 1–7.
[2] N. Mahmud and A. Zahedi, “Review of control strategies for voltage [18] A. Ali, R. David, and K. Mahmoud, “Adaptive multi-objective
regulation of the smart distribution network with high penetration of optimization for power loss minimization and voltage regulation in
renewable distributed generation,” Renew. Sustain. Energy Rev., vol. distribution systems,” in 2016 Eighteenth International Middle East
64, pp. 582–595, Oct. 2016. Power Systems Conference (MEPCON), 2016, pp. 573–578.
[3] K. Mahmoud, N. Yorino, and A. Ahmed, “Power loss minimization in [19] W. Zheng, W. Wu, B. Zhang, H. Sun, and Y. Liu, “A Fully Distributed
distribution systems using multiple distributed generations,” IEEJ Reactive Power Optimization and Control Method for Active
Trans. Electr. Electron. Eng., vol. 10, no. 5, pp. 521–526, Sep. 2015. Distribution Networks,” IEEE Trans. Smart Grid, pp. 1–1, 2015.
[4] K. Mahmoud, M. Abdel-Akher, and A.-F. A. Ahmed, “Sizing and [20] A. Molina-Garcia, R. A. Mastromauro, T. Garcia-Sanchez, S. Pugliese,
locating distributed generations for losses minimization and voltage M. Liserre, and S. Stasi, “Reactive Power Flow Control for PV
stability improvement,” in 2010 IEEE International Conference on Inverters Voltage Support in LV Distribution Networks,” IEEE Trans.
Power and Energy, 2010, pp. 600–604. Smart Grid, vol. 8, no. 1, pp. 447–456, Jan. 2017.
[5] A. S. Bouhouras, K. I. Sgouras, P. A. Gkaidatzis, and D. P. Labridis, [21] D. Zhang, Z. Fu, and L. Zhang, “An improved TS algorithm for loss-
“Optimal active and reactive nodal power requirements towards loss minimum reconfiguration in large-scale distribution systems,” Electr.
minimization under reverse power flow constraint defining DG type,” Power Syst. Res., vol. 77, no. 5–6, pp. 685–694, Apr. 2007.
Int. J. Electr. Power Energy Syst., vol. 78, pp. 445–454, Jun. 2016. [22] “Australian Standard AS/NZS 61000.3.100:2011, Electromagnetic
[6] M. Bollen and F. Hassan, Integration of Distributed Generation in the compatibility (EMC) – Limits – Steady state voltage limits in public
Power System. Hoboken, NJ, USA: John Wiley & Sons, Inc., 2011. electricity systems,” 2011.

View publication stats

You might also like