Professional Documents
Culture Documents
05-ASME B31.3 Quiz
05-ASME B31.3 Quiz
Quiz
1. All welding terms found in ASME B31.3 are found in the Code and:
A. ASME Section IX
B. ASME Section V
C. AWS A2.4
D. AWS A3.0
2. A fluid service in which the potential for personnel exposure is judged to be significant:
3. Snow and ice loads due to both sentimental and operating conditions are considered:
A. Dead Loads
B. Live Loads
C. Environmental Loads
D. Structural Loads
4. The required thickness of straight sections shall be determined in accordance with Eq. 2,
A. tm = t + d
B. tm = d - t
C. tm = t +c
D. tm = c - t
6. A Charpy V-notch specimen for impact testing shall be made using a standard:
7. Qualification of welding Procedures to be used in compliance with ASME B 31.3 shall conform
to the requirements of:
A. ASME B 31.3
B. BPV Code, Section IX
C. API 570
D. ASME Section V
8. Subject to the specific approval of the Inspector, welding procedures qualified:
A. E7018
B. E7016
C. E6011
D. E6010
10. A welder may pass a performance qualification test for Company A, quit the job, then within 6
months be hired by Company B. This welder can perform similar welding work without retest..
A. True
B. False
C. True only in certain states
D. False, in compliance with ASME B 31.3
A. AWS A5.1
B. ASME Section IX
C. ASME Section V
D. API 570
A. ±1/16”
B. ±1/32”
C. within the dimensional limits in the WPS
D. the fabricator’s discretion
13. The root pass and final pass of a weld may not be:
A. peened
B. cleaned
C. stress relieved
D. painted
15. The preheat zone shall extent at least ______ beyond the edge of the weld.
A. 10 mm
B. 1 inch
C. 50 mm
D. 3 inches
16. The owner’s Inspector shall have:
17. In reviewing radiography of a Normal Fluid Service piping weld joint, a crack was noticed. If the
pipe wall thickness was 0.375”, what length crack is acceptable?
A. none
B. T/3
C. 3/16”
D. cracks will not show on radiographs
18. An examiner perfoming a PT test of completed weld on the outside of a Category D Fluid Service
piping system noted a transverse crack in the root pass:
19. Individual slag trapped in a weld in Severe Cyclic Conditions piping system, maximum length
may be:
A. > TWX3
B. TW/3
C. 12T
D. 3/23”
A. ASME Section IX
B. ASME Section V
C. ASNT SNT-TC-1A
D. API 570
API ASME B31.3 Quiz
Answer Key
1. D
2. A
3. B
4. C
5. D
6. C
7. B
8. A
9. D
10. C
11. B
12. C
13. A
14. D
15. B
16. D
17. A
18. D
19. B
20. C