Professional Documents
Culture Documents
MENG471 Assignment 2
MENG471 Assignment 2
Monitoring results:
A total of 10 ground settlement markers, 37 column settlement markers and 29 Demec
crack width monitoring stations were installed to monitor the movement behavior of
the building block.
Monitoring stations were set up on some selected columns of the building that had
severely distorted/distressed visibly.
Places with fewer distress marks were also monitored for comparison reasons. During
20day inspection period, 15 trips were completed, general conclusion of all ground
settlement markers showed fluctuation/deflection throughout the monitoring
inspection. For column settlement markers, 37 of them were divided into two specific
groups based on severe distress signals.
For group (i), markers CS01 to CS05 (minimum -0.4mm to maximum -6.8mm); markers CS31
to CS37 (3 to -3mm); for group (ii) settlement activity in first two readings, was heaving for
the rest of the period.
All the Demec crack with monitoring stations except for D24 was recorded with stable crack
propagation and crack width fluctuating ranging from (0.3 to -0.2mm), a major crack in D24
had widened to 1.1mm but it was stabilized towards the end. The supervision had to be
kept extended to learn more about the patterns and behavior of the cracks.
The Soil and Foundation Investigation:
Eight rotary boreholes counted were examined (BH1-BH8), out of them seven were
around the building block perimeter and one was near the tube well.
The tasks were to obtain the disturbed and undisturbed soil samples for laboratory
examinations, excavation in certain selected areas to study about the foundation
system and extraction of soil samples for testing compaction level in the laboratory.
A Mackintosh probe test was carried out at each of the excavation/trial pit locations
and several selected areas near the building block.
The soil results showed it was clayey silt material in all the eight boreholes. The
depth for SPT values exceeded 50 and was between (9-17.5m). The topsoil was
(6-10 m) thick very soft compared to clayey silt, underneath the topsoil was very stiff
clayey silt and below there was still competent layers of hard stratum (SPT>=50).
The two bottom layers were 10 and 15 mm deep respectively. The soil liquid limit
ranged between 41 and 53%, and the plasticity index between 10 and 28%, ground
water level 0.7 and 7m. The filled materials concise of clayey silt with traces of sand
and gravel, contained an SPT value (1 to 39) blows/ 0.3 (averaging =20) and moisture
content (23-36%, averaging 30%).
Finally, total of seven trail pits were excavated to visualize the actual foundation of
the building, the study shows the system compiled with the original building
specifications
Gridlines 11 and 20 is placed on excavated land, the front part between gridlines 1 and 11, is
where the filled land of thickness showed up to about 10 m near gridline 4.
Soil Investigation:
Total of eight boreholes were drilled all around the site, the subsoil generally consisted of
clayey silts, but in the case of boreholes BH-1,BH-2, BH-3,BH-7 and BH-8 indicated very soft to
firm (SPTN<=4) clayey silts extending from the ground surface to a depth pf 6 to 10 m. This soft
soil is kind of filler earth that was dumped in the location long back in past. Otherwise the
building stands completely fine, competent hard stratum of (SPT>= 50) between 10 and 15m
from the actual ground surface.
Underground Water:
The ground levels in the boreholes BH-1to BH-7 indicated low levels between 0.7 to 7m below
the ground surface. The average depth of groundwater was about 4.8 m in height.
(i) Lowering of ground water level: It was not realized until the settlements could be
caused by a lowering of groundwater level till Terzaghi’s investigation led in 1920’s
when the concept of effective stress was proposed. For saturated soils, effective stress is
equal to total stress less than pore water pressure,
σ ' =σ−u
It was noticed that drawdown of groundwater table can cause a significant reduction in
pore water pressure in subsoil resulting in an increase effective stress. This process lead
to consolidation and settlement of subsoil.
A classic example is Mexico City where lowering of the groundwater level has caused
vast areas of the land around the city to settle or subside. In 1948, parts of the city were
settling at a rate of about 1 mm per day. Since measurements began in 1898, more than
6 m of subsidence has been recorded. In this city, consolidation settlement was possibly
due to several factors including lowering of groundwater level beneath the building.
(ii) Soft soil underfill/structure loads: Consolidation settlement exists if a structure or fill is
placed over an existing layer of compressible soft soil.
(iii) Improperly compacted fill materials: Consolidation settlement can also result from
improperly compacted fill materials as they compress under their own weight. If top 6-
10m thick very soft to firm clayey silts encountered in boreholes BH-1 to BH-8 are fill
materials hen consolidation settlement exists.
(i) Consolidation settlements due low groundwater levels, the results showed opposite in this case
the ground settlement and column settlement markers experienced heaves instead of
settlements during the recharge of groundwater at its original level.
(ii) Consolidation due to improper compacted fills, this problem is negligible (due to insignificant
after about 10 years of the completion of building), most of the consolidation must have
occurred during the 10 years and rate of consolidation must reduce with time.
(iii) Excessive pile settlements or insufficient load-carrying capacities in individual or group piles due
to negative skin friction that is induced on pile shafts.
(iv) Unknown condition of existing affected piles i.e. if any piles damaged by the negative skin
friction in the past.
(v) The actual pile length and number of piles driven, and unknown actual loads imposed on piles
after load sharing and redistribution.
(vi) Uncertainties of the previous design of the foundation as it was informed from beginning the
cracks have been visible since the completion of the building.
(i) Ignore the working load capacity of already affected piles for the current design.
(ii) Strengthen the affected pile foundations by underpinning with adequate micropiles. A
minimum of two micropiles are required for each affected group of pile.
(iii) Considering adding new pile loads in the existing and newly proposed pile foundation.
(iv) Some old ones were destroyed due to negative skin friction, details of the proposed
micropile:
Diameter of micropile: 200mm.
Estimated length of micropile: 20-30 m.
Working load of micropile: 50 TONS.
Usage of minimum grade 30 non-shrink cement grout.