Providing additional class Rooms to Acadamic block in Damadaraya Sanjivayya National Law University at Sabbavarm,

Visakhapatnam.

Ground Floor
Measurements
Sl. No. Description of item Nos Quanity
L B D
1 Earth work excavation for foundations (Manual Means) of buildings in ordinary soils and depositing on
bank with an initial lead of 10m and depth up to 3m including all operational,incidental, labour charges
such as shoring, sheeting, planking, strutting etc., complete for finished item of work including seigniorage
excluding dewatering charges etc., as per SS 20 B(APSS 308)

columns 1,2,10 3 2.5 2.5 2 37.5


columns 4,6,8 3 2.7 2.7 2 43.74
in Bewten columns 10-8,9-12 2 1.63 0.75 0.75 1.83
in Bewten columns 8-6,9-7 2 1.41 0.75 0.75 1.59

In bewten columns 4-6,7-5 2 1.46 0.75 0.75 1.64


In bewten columns 4-1,5-3 2 1.68 0.75 0.75 1.89
In bewten columns 10-11 1 1.79 0.75 0.75 1.01
In bewten columns 1-2 1 1.22 0.75 0.75 0.69
In bewten columns 11-12.2-3 2 1.88 0.75 0.75 2.12
Verndha Long wall 4 13.2 0.75 0.75 29.70
Entire Verndha Long wall 1 10.2 0.75 0.75 5.74
Cross walls Lshape 2 4 0.75 0.75 4.50
131.94
Say 135
Cum
2 Plain Cement Concrete (1:5:10) proportion nominal mix (cement: fine aggregate: Coarse aggregate)
for foundations and under flooring bed using 40mm size (SS5) hard,machine crushed granite metal from
approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water
etc. to site, including seigniorage charges, sales & other taxes on all materials and including all charges for
machine mixing, laying concrete in foundations and under flooring bed, ramming in 15 cm layers finishing
top surface to the required level curing etc., complete for finished item of work. (APSS No. 402)

columns 1,2,10 3 2.5 2.5 0.15 2.81


columns 4,6,8 3 2.7 2.7 0.15 3.28
in Bewten columns 10-8,9-12 2 1.63 0.75 0.15 0.37
in Bewten columns 8-6,9-7 2 1.41 0.75 0.15 0.32
In bewten columns 4-6,7-5 2 1.46 0.75 0.15 0.33
In bewten columns 4-1,5-3 2 1.68 0.75 0.15 0.38
In bewten columns 10-11 1 1.79 0.75 0.15 0.20
In bewten columns 1-2 1 1.22 0.75 0.15 0.14
In bewten columns 11-12.2-3 2 1.88 0.75 0.15 0.42
Verndha Long wall 4 13.2 0.75 0.15 5.94
Entire Verndha Long wall 1 10.2 0.75 0.15 1.15
Cross walls Lshape 2 4 0.75 0.15 0.90
16.23
Say 17
Cum
3 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456 using 20mm size
(SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry, including
cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to
site and cost of seigniorage charges on all materials including centering, shuttering and scaffolding
with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for Column bases

Columns 1,2,10, 3 2.3 2.3 0.3 4.8


Columns 1,2,10, 3 1.1 1.1 0.25 0.9
Columns 4,6,8 3 2.5 2.5 0.3 5.6
In bewten Footing Second Step 3 1.3 1.3 0.35 1.8
13.1
Total qty 14
Cum
4 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456 using 20mm size
(SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry, including
cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to
site and cost of seigniorage charges on all materials including centering, shuttering and scaffolding
with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for Column

Columns Up to slab 1,2,3,10,11,12 6 0.6 0.23 5.9 4.89


Columns 4,5,6,7,8,9 6 0.6 0.35 5.9 7.43
2 0.6 0.23 5.9 1.63
13.95
Total qty 14
Cum
5 Providing R.R Masonary in cm(1:6) using rough stone etc complete
First footing inbewteen 1-4,3-5 2 3.99 0.6 0.9 4.31
Second footing 2 3.99 0.45 0.6 2.15
First footing inbewteen 4-6,5-7 2 3.76 0.6 0.6 2.71
In between2nd footing 2 3.76 0.45 0.45 1.52
First footing inbewteen 6-8,7-9 2 3.68 0.6 0.6 2.65
Second footing 2 3.68 0.45 0.45 1.49
First footing inbewteen 8-10,9-12 2 3.94 0.6 0.6 2.84
Second footing 2 3.94 0.45 0.45 1.60
First footing inbewteen 1-2 2 2.39 0.6 0.9 2.58
Second footing inbewteen 2 2.39 0.45 0.6 1.29
First footing inbewteen 2-3,11,-12 2 3.96 0.6 0.9 4.28

Second footing inbewteen 2 3.96 0.45 0.6 2.14


First vertical wall 4 13.2 0.6 0.9 28.51
Second vertical wall 4 13.2 0.45 0.6 14.26
First vertical wall 1 10.2 0.6 0.9 5.51
Second vertical wall 4 13.2 0.45 0.6 14.26
First cross wall 2 4 0.6 0.9 4.32
Second cross wall 2 4 0.45 0.6 2.16
98.57
Total qty 100
Cum
6 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456 using 20mm size
(SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry, including
cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to
site and cost of seigniorage charges on all materials including centering, shuttering and scaffolding
with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for Plinth Beams

over long walls 2 16.76 0.23 0.45 3.47


over cross walls 1 10.79 0.23 0.45 1.12
over cross walls 1 8.92 0.23 0.45 0.92
over verndha walls 4 13.2 0.23 0.3 3.64
over verndha walls 1 10.2 0.23 0.3 0.70
Verndha cross walls 2 4 0.23 0.3 0.55
10.41
Total qty 11
Cum
7 Filling with excavated earth by lorries including Consolidations at 15cm layers watering etc complete as
directed by Engineer Incharge

columns 1,2,10 3 2.5 2.5 2 37.5


columns 4,6,8 3 2.7 2.7 2 43.74
in Bewten columns 10-8,9-12 2 1.63 0.75 0.75 1.83
in Bewten columns 8-6,9-7 2 1.41 0.75 0.75 1.59
In bewten columns 4-6,7-5 2 1.46 0.75 0.75 1.64
In bewten columns 4-1,5-3 2 1.68 0.75 0.75 1.89
In bewten columns 10-11 1 1.79 0.75 0.75 1.01
In bewten columns 1-2 1 1.22 0.75 0.75 0.69
In bewten columns 11-12.2-3 2 1.88 0.75 0.75 2.12
Verndha Long wall 4 13.2 0.75 0.75 29.70
Entire Verndha Long wall 1 10.2 0.75 0.75 5.74
Cross walls Lshape 2 4 0.75 0.75 4.50
131.94
Say 135
Cum
8 Filling withborrowed earth by lorries including Consolidations at 15cm layers watering etc complete as
directed by Engineer Incharge
basement filling 1 16.3 10.33 0.9 151.54
verndha filling 2 13.2 2 0.92 48.58
200.12
Total qty 210
Cum
9 Plain Cement Concrete (1:5:10) proportion nominal mix (cement: fine aggregate: Coarse aggregate)
for foundations and under flooring bed using 40mm size (SS5) hard,machine crushed granite metal from
approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water
etc. to site, including seigniorage charges, sales & other taxes on all materials and including all charges for
machine mixing, laying concrete in foundations and under flooring bed, ramming in 15 cm layers finishing
top surface to the required level curing etc., complete for finished item of work. (APSS No. 402)

class Rooms 1 16.76 10.79 180.84


Verndha 2 13.2 2 52.80
Verndha 1 10.2 3.85 39.27
272.91
Total qty 275
Sqm
10 Providing Antitermite treatment as per IS 6315 (Part - 2) 2001 (Pre-constructional chemical treatment
measures) along the internal & external vertical faces of the columns, plinth beams, basement and top surface
of the basement filling below flooring bed as per the specified procedure conforming to IS 6315 (Part-2) 2001
and other relevant approved specification duly using Chlorpyriphos/ Lindane emulsifiable concentrate 20%
with 1% concentration @ 7.5 Liters/ sqm of the vertical surface & @ 5.0 Liters/ sqm of the horizontal surface
of the substructure to a depth of 500 mm around columns & 300 mm deep around plinth beams, basements &
floor filling area including excavation channel along the wall & rodding etc & cost & conveyance of all materials
to the site, cost of labour for spraying, rodding etc complete for finished item of work as per the approval of the
Engineer-in-Charge
Class Rooms 1 16.76 10.79 180.84
Verndha 2 13.2 2 52.80
Verndha 1 10.2 3.85 39.27
272.91
Total qty 275
Sqm
11 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456 using 20mm size
(SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry, including
cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to
site and cost of seigniorage charges on all materials including centering, shuttering and scaffolding
with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for Roof beams

Beam 1-2-3 1 8.09 0.23 0.45 0.84


Beam4-5,6-9 3 9.59 0.3 0.55 4.75
Beam 10-11-12 1 8.96 0.23 0.45 0.93
Beam 1-4-6-8-10 1 15.4 0.23 0.45 1.59
Beam 3-5-7-9-12 1 15.4 0.23 0.45 1.59
Corridor connecting 4 13.85 0.23 0.45 5.73
Entrance corridor beam 1 10.2 0.23 0.45 1.06
Side Entrance beam 1 8.75 0.23 0.45 0.91
Cross beams at corridor 4 1.87 0.23 0.45 0.77
18.17
Total qty 19
Cum
12 Masonry for panel walls in superstructure with CM (1:6) prop: (cement : sand) using Fly ash
lime solid blocks of size 290mm X 225mm X 140mm and having minimum crushing strength of 75
Kg/Sqcm and using flyash of 80 kgs, cement of 15 kgs, Gypsum of 5 kgs and stone dust for manufacturing
of Fly ash lime solid blocks including cost and conveyance of all materials like cement, sand, fly ash solid
blocks, water etc., to site, including seigniorage charges, sales & other taxes on all materials and such as
labour charges, like mixing cement mortar, scaffolding charges, constructing masonry, lift charges, curing,
etc., complete for finished item of work. (APSS No. 501 & 504).
Long wall 2 15.1 0.23 3.65 25.35
Cross wall opp dias 1 8.99 0.23 3.55 7.34
Cross wall at dias 1 7.86 0.23 3.55 6.42
Corridor walls 2 13.07 0.23 2 12.02
Corridor walls 2 13.11 0.23 2 12.06
Corridor at dias 1 3.74 0.23 2 1.72
Corridor at dias 1 2 0.23 2 0.92
wall opp 1 10.16 0.23 2 4.67
Deduct Door 2 1.5 0.23 2.4 1.66
Deduct Windows W1 6 1.82 0.23 1.22 3.06
Dias wall 1 8 0.23 0.45 0.83
Dias wall 1 3 0.23 0.45 0.31
steps 2 3 0.3 0.15 0.27
71.92 4.72
Total qty 67.20
Say 68
Cum
13 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456 using 20mm size
(SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry, including
cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to
site and cost of seigniorage charges on all materials including centering, shuttering and scaffolding
with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for Lintels

over Long wall 2 16.76 0.23 0.2 1.54


over cross wall 2 10.79 0.23 0.2 0.99
Corridor sides 2 13.07 0.23 0.2 1.20
Corridor sides 2 13.11 0.23 0.2 1.21
At Dias L Shape 1 5.74 0.23 0.2 0.26
L Shape 1 14.16 0.23 0.2 0.65
5.86
Say 6
Cum
14 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456 using 20mm size
(SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry, including
cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to
site and cost of seigniorage charges on all materials including centering, shuttering and scaffolding
with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for Sunshades

At windows 3 2.28 0.6 4.10


At corridor sides 2 13.07 0.6 15.68
At corridor sides 2 13.11 0.6 15.73
At Door 1 3.74 0.6 2.24
At Door 1 2.6 0.6 1.56
Lshape at entrance 1 4 0.6 2.40
opp at entrance wall 1 10.16 0.6 6.10
47.82
Say 49
Sqm
15 Vibrated Reinforced Cement Concrete M-30 Design Mix as per Table 9 of IS 456 using 20mm size
(SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry, including
cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to
site and cost of seigniorage charges on all materials including centering, shuttering and scaffolding
with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for 15cm Thick slab.

class Rooms 1 16.76 10.05 168.44


Deduct staircase portion 0.5 1.13 4.19 2.37
Corridor Entrance 1 10.16 4 40.64
Corridor connecting 1 13.11 2 26.22
Sides of door 1 5.8 2 11.60
connecting 1 13.07 2 26.14
273.04 2.37
270.67
Say 275
Sqm
16 Plastering 12mm thick in CM(1:3) for even surfaces including cost and conveyance of all materials
like cement, sand (screened), water etc., to site, including seigniorage charges, sales & other taxes on
all materials, and all operational, incidental charges on materials and including cost of all labour charges
for mixing mortar, finishing, curing as directed by Engineer-in-charge etc., complete for finished item of
work(APSS No. 901 & 903)

ceiling plastering aty same as slab 1 275 275.00


Qty of Sunshades 1 50 0.75 37.50
Projected column all round 9 1.1 4 39.60
Beams a class Room 6 9.59 0.55 31.65
383.75
Say 390
Sqm
17 Plastering 12mm thick in CM(1:4) for even surfaces including cost and conveyance of all materials
like cement, sand (screened), water etc., to site, including seigniorage charges, sales & other taxes on
all materials, and all operational, incidental charges on materials and including cost of all labour charges
for mixing mortar, finishing, curing as directed by Engineer-in-charge etc., complete for finished item of
work(APSS No. 901 & 903)
Class room long wall 2 16.3 4 130.4
Class room cross wall 2 9.59 4 76.72
Corridor walls at main entrance 1 23.27 2.78 64.69
Corridor walls at main entrance 1 13.11 2.78 36.45
Sides of corridor 2 13.07 2.78 72.67
1 3.74 2.78 10.40
Cross walls 2 2 2.78 11.12
Deduct qty of Door 1 7.2
Deduct qty of Window 1 13.22
402.44 20.42
382.02
Say 390
Sqm
18 Plastering 20 mm thick in CM(1:4) for even surfaces including cost and conveyance of all materials
like cement, sand (screened), water etc., to site, including seigniorage charges, sales & other taxes on
all materials, and all operational, incidental charges on materials and including cost of all labour charges
for mixing mortar, finishing, curing as directed by Engineer-in-charge etc., complete for finished item of
work(APSS No. 901 & 903)

Building o/s walls 2 16.76 4 134.08


Crass walls 2 10.51 4 84.08
Corridor walls o/s at entarnce 1 10.16 2.78 28.24
Corridor walls connecting 1 13.11 2.78 36.45
Lshape at entrance 1 4 2.78 11.12
Sides corridor connecting o/s 2 13.07 2.78 72.67
1 3.59 2.78 9.98
Cross walls 2 2 2.78 11.12
Deduct qty of doors 1 7.2 7.2
Deduct qty of windows 1 13.32 13.32
387.74 20.52
367.22
Say 370
Sqm
19 Supply and Fixing the UPVC Doors with necessary furniture and Locking arrangements
Doors 2 1.5 2.4 7.20
7.20
Say 7.2
Sqm
20 Supply and Fixing the UPVC windows with necessary furniture and Locking arrangements
Windows 6 1.82 1.52 16.60
16.60
Say 16.6
Sqm
21 Flooring / treads with vitrified polished floor tiles of 1st quality and make as approved by Engineer-
in-charge of size 1000 mm x 1000 mm , 8mm to 10mm thick , normal colour with borders and
design as per the approved flooring pattern as directed by the Engineer-In -Charge set over a base coat
of CM (1:8) prop. 12mm thick over CC bed already laid or RCC roof slab , including neat cement slurry
of honey like consistancy spread @ 3.3 kgs per Sqm. and jointed neately with white cement paste to full
depth mixed with pigment of matching shade including cost and conveyance of all materials like
cement, sand, water, tiles, white cement etc., to site (excluding cost of C.C. bed) including cost of
seigniorage charges on all materials, cost of base coat and all labour charges for mixing of cement
mortar, laying tiles to required slope as directed by the Engineer- in-charge etc., complete for
finished item of work. (APSS No.701 & 707)

Class room 1 16.3 9.59 156.32


Skurtting 2 16.3 0.1 3.26
Skurtting 8 9.59 0.1 7.67
Dias wall 1 8 0.45 3.60
Cross wall 1 3 0.45 1.35
Connecting corridor 2 13.85 2 55.40
Skurtting 4 13.85 0.1 5.54
front Coridor 1 10.2 3.85 39.27
Skurtting 2 10.2 0.1 2.04
Dias side corridor 1 5.74 1.87 10.73
Skurtting 1 5.74 0.1 0.57
Skurtting 1 1.87 0.1 0.19
285.94
Say 290
Sqm
22 Painting with plastic emulsion paint of grade-1 standard make to interior faces of new walls two coat of
approved make shade and colour over primer coat two coats of putty with cement primer grade - I including
cost and conveyance of materials like Plastic Emulsion paint, white cement to site including cost of brushes,
scaffolding charges, lift charges and labour charges such as preparing the wall, applying primer coat , two
coats of Plastic Emulsion etc., complete for finished item of work (APSS No.910, 911&1201) in all floors.

qty same as (1:3) 12mm thick 1 390 390


qty same as (1:4) 12mm thick 1 390 390
qty same as (1:4)20mm thick 1 370 370
1150
Say 1150
Sqm
23 Providing Enamel Paint two coats approved brand and shade over base coat of Zich Chromite approved
brand and shade etc complete

Grills 1 16.6 1 16.6


16.6
Say 16.6
Sqm
24 Supplying , fitting and placing HYSD / TMT bar reinforcement in VRCC works complete as per drawings
and technical specifications for bars below 36mm dia including over laps and wastage,where they are not
welded including cost and conveyance of steel , binding wire etc., lifting charges of steel , placing in position,
tying with binding wire , all tools etc., complete for finished item of work
Column 1 14 175 2450
plinth beams 1 11 100 1100
Roof Beams 1 19 175 3325
15cm thick salb 1 275 0.15 80 3300
Lintels 1 6 120 600
Sunshades 1 49 0.06 80 168
10943
Say 11000
Kgs
`
Providing additional class Rooms to Acadamic block in Damadaraya Sanjivayya National Law University
at Sabbavarm, Visakhapatnam.

FIRST Floor
Measurements
Sl. No. Description of item Nos Quanity
L B D

1 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456
using 20mm size (SS5) hard granite machine crushed graded metal (Coarse aggregate)
from approved quarry, including cost and conveyance of all materials like cement, fine
aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges
on all materials including centering, shuttering and scaffolding with props and
steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication
charges for finished item of work (APSS No. 402 & 403) for Columns

columns 1,2,3,10,11,12 6 0.6 0.23 4 3.31


columns 4,5,6,7,8,9 6 0.6 0.35 4 5.04
columns 2 0.6 0.23 4 1.10
9.46
Total qty 10
Cum
2 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456
using 20mm size (SS5) hard granite machine crushed graded metal (Coarse aggregate)
from approved quarry, including cost and conveyance of all materials like cement, fine
aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges
on all materials including centering, shuttering and scaffolding with props and
steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication
charges for finished item of work (APSS No. 402 & 403) for Roof beams

Beam 1-2-3 1 8.09 0.23 0.45 0.84


Beam4-5,6-9 3 9.59 0.3 0.55 4.75
Beam 10-11-12 1 8.96 0.23 0.45 0.93
Beam 1-4-6-8-10 1 15.4 0.23 0.45 1.59
Beam 3-5-7-9-12 1 15.4 0.23 0.45 1.59
Corridor connecting 4 13.85 0.23 0.45 5.73
Entrance corridor beam 1 10.2 0.23 0.45 1.06
Side Entrance beam 1 8.75 0.23 0.45 0.91
Cross beams at corridor 4 1.87 0.23 0.45 0.77
18.17
Total qty 19
Cum
3 Masonry for panel walls in superstructure with CM (1:6) prop: (cement : sand)
using Fly ash lime solid blocks of size 290mm X 225mm X 140mm and having
minimum crushing strength of 75 Kg/Sqcm and using flyash of 80 kgs, cement of 15 kgs,
Gypsum of 5 kgs and stone dust for manufacturing of Fly ash lime solid blocks including
cost and conveyance of all materials like cement, sand, fly ash solid blocks, water etc., to
site, including seigniorage charges, sales & other taxes on all materials and such as
labour charges, like mixing cement mortar, scaffolding charges, constructing masonry, lift
charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).
Long wall 2 15.1 0.23 3.65 25.35
Cross wall opp dias 1 8.99 0.23 3.55 7.34
Cross wall at dias 1 7.86 0.23 3.55 6.42
Corridor walls 2 13.07 0.23 2 12.02
Corridor walls 2 13.11 0.23 2 12.06
Corridor at dias 1 3.74 0.23 2 1.72
Corridor at dias 1 2 0.23 2 0.92
wall opp 1 10.16 0.23 2 4.67
Deduct Door 2 1.5 0.23 2.4 1.66
Deduct Windows W1 6 1.82 0.23 1.22 3.06
Dias wall 1 8 0.23 0.45 0.83
Dias wall 1 3 0.23 0.45 0.31
steps 2 3 0.3 0.15 0.27
71.92 4.72
Total qty 67.20
Say 68
Cum
4 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456
using 20mm size (SS5) hard granite machine crushed graded metal (Coarse aggregate)
from approved quarry, including cost and conveyance of all materials like cement, fine
aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges
on all materials including centering, shuttering and scaffolding with props and
steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication
charges for finished item of work (APSS No. 402 & 403) for Lintels

over Long wall 2 16.76 0.23 0.2 1.54


over cross wall 2 10.79 0.23 0.2 0.99
Corridor sides 2 13.07 0.23 0.2 1.20
Corridor sides 2 13.11 0.23 0.2 1.21
At Dias L Shape 1 5.74 0.23 0.2 0.26
L Shape 1 14.16 0.23 0.2 0.65
5.86
Say 6
Cum
5 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456
using 20mm size (SS5) hard granite machine crushed graded metal (Coarse aggregate)
from approved quarry, including cost and conveyance of all materials like cement, fine
aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges
on all materials including centering, shuttering and scaffolding with props and
steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication
charges for finished item of work (APSS No. 402 & 403) for Sunshades

At windows 3 2.28 0.6 4.10


At corridor sides 2 13.07 0.6 15.68
At corridor sides 2 13.11 0.6 15.73
At Door 1 3.74 0.6 2.24
At Door 1 2.6 0.6 1.56
Lshape at entrance 1 4 0.6 2.40
opp at entrance wall 1 10.16 0.6 6.10
47.82
Say 49
Sqm
6 Vibrated Reinforced Cement Concrete M-30 Design Mix as per Table 9 of IS 456
using 20mm size (SS5) hard granite machine crushed graded metal (Coarse aggregate)
from approved quarry, including cost and conveyance of all materials like cement, fine
aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges
on all materials including centering, shuttering and scaffolding with props and
steel plate as per the approved shuttering plan, machine mixing, laying concrete,
vibrating, lift charges, curing etc., complete but excluding cost of steel and it’s fabrication
charges for finished item of work (APSS No. 402 & 403) for 15cm Thick slab.

class Rooms 1 16.76 10.05 168.44


Deduct staircase portion 0.5 1.13 4.19 2.37
Corridor Entrance 1 10.16 4 40.64
Corridor connecting 1 13.11 2 26.22
Sides of door 1 5.8 2 11.60
connecting 1 13.07 2 26.14
273.04 2.37
270.67
Say 275
Sqm
7 Plastering 12mm thick in CM(1:3) for even surfaces including cost and conveyance
of all materials like cement, sand (screened), water etc., to site, including seigniorage
charges, sales & other taxes on all materials, and all operational, incidental charges on
materials and including cost of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., complete for finished item of work(APSS No. 901 &
903)
ceiling plastering aty same a 1 275 275.00
Qty of Sunshades 1 50 0.75 37.50
Projected column all round 9 1.1 4 39.60
Beams a class Room 6 9.59 0.55 31.65
383.75
Say 390
Sqm
8 Plastering 12mm thick in CM(1:4) for even surfaces including cost and conveyance
of all materials like cement, sand (screened), water etc., to site, including seigniorage
charges, sales & other taxes on all materials, and all operational, incidental charges on
materials and including cost of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., complete for finished item of work(APSS No. 901 &
903)

Class room long wall 2 16.3 4 130.4


Class room cross wall 2 9.59 4 76.72
Corridor walls at main entra 1 23.27 2.78 64.69
Corridor walls at main entra 1 13.11 2.78 36.45
Sides of corridor 2 13.07 2.78 72.67
1 3.74 2.78 10.40
Cross walls 2 2 2.78 11.12
Deduct qty of Door 1 7.2
Deduct qty of Window 1 13.22
402.44 20.42
382.02
Say 390
Sqm
9 Plastering 20 mm thick in CM(1:4) for even surfaces including cost and conveyance
of all materials like cement, sand (screened), water etc., to site, including seigniorage
charges, sales & other taxes on all materials, and all operational, incidental charges on
materials and including cost of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., complete for finished item of work(APSS No. 901 &
903)
Building o/s walls 2 16.76 4 134.08
Crass walls 2 10.51 4 84.08
Corridor walls o/s at entarn 1 10.16 2.78 28.24
Corridor walls connecting 1 13.11 2.78 36.45
Lshape at entrance 1 4 2.78 11.12
Sides corridor connecting o/ 2 13.07 2.78 72.67
1 3.59 2.78 9.98
Cross walls 2 2 2.78 11.12
Deduct qty of doors 1 7.2 7.2
Deduct qty of windows 1 13.32 13.32
387.74 20.52
367.22
Say 370
Sqm
Supply and Fixing the UPVC Doors with necessary furniture and Locking arrangements
10
Doors 2 1.5 2.4 7.20
7.20
Say 7.2
Sqm
11 Supply and Fixing the UPVC windows with necessary furniture and Locking arrangements

Windows 6 1.82 1.52 16.60


16.60
Say 16.6
Sqm
12 Flooring / treads with vitrified polished floor tiles of 1st quality and make as
approved by Engineer-in-charge of size 1000 mm x 1000 mm , 8mm to 10mm thick
, normal colour with borders and design as per the approved flooring pattern as directed
by the Engineer-In -Charge set over a base coat of CM (1:8) prop. 12mm thick over
CC bed already laid or RCC roof slab , including neat cement slurry of honey like
consistancy spread @ 3.3 kgs per Sqm. and jointed neately with white cement paste to
full depth mixed with pigment of matching shade including cost and conveyance of all
materials like cement, sand, water, tiles, white cement etc., to site (excluding cost of
C.C. bed) including cost of seigniorage charges on all materials, cost of base coat and
all labour charges for mixing of cement mortar, laying tiles to required slope as
directed by the Engineer- in-charge etc., complete for finished item of work. (APSS
No.701 & 707)

Class room 1 16.3 9.59 156.32


Skurtting 2 16.3 0.1 3.26
Skurtting 8 9.59 0.1 7.67
Dias wall 1 8 0.45 3.60
Cross wall 1 3 0.45 1.35
Connecting corridor 2 13.85 2 55.40
Skurtting 4 13.85 0.1 5.54
front Coridor 1 10.2 3.85 39.27
Skurtting 2 10.2 0.1 2.04
Dias side corridor 1 5.74 1.87 10.73
Skurtting 1 5.74 0.1 0.57
Skurtting 1 1.87 0.1 0.19
285.94
Say 290
Sqm
13 Painting with plastic emulsion paint of grade-1 standard make to interior faces of new
walls two coat of approved make shade and colour over primer coat two coats of putty with
cement primer grade - I including cost and conveyance of materials like Plastic Emulsion
paint, white cement to site including cost of brushes, scaffolding charges, lift charges and
labour charges such as preparing the wall, applying primer coat , two coats of Plastic
Emulsion etc., complete for finished item of work (APSS No.910, 911&1201) in all floors.

1 390 390
qty same as (1:3) 12mm
thick
1 390 390
qty same as (1:4) 12mm
thick
qty same as (1:4)20mm 1 370 370
thick
1150
Say 1150
Sqm
14 Providing Enamel Paint two coats approved brand and shade over base coat of Zich
Chromite approved brand and shade etc complete
Grills 1 16.6 1 16.6
16.6
Say 16.6
Sqm
15 Supplying , fitting and placing HYSD / TMT bar reinforcement in VRCC works complete
as per drawings and technical specifications for bars below 36mm dia including over laps
and wastage,where they are not welded including cost and conveyance of steel , binding
wire etc., lifting charges of steel , placing in position, tying with binding wire , all tools etc.,
complete for finished item of work

Column 1 14 175 2450


Roof Beams 1 19 175 3325
15cm thick salb 1 275 0.15 80 3300
Lintels 1 6 120 600
Sunshades 1 49 0.06 80 168
9843
Say 10000
Kgs
Providing additional class Rooms to Acadamic block in Damadaraya Sanjivayya National Law University at
Sabbavarm, Visakhapatnam.

Second Floor
Measurements
Sl. No. Description of item Nos Quanity
L B D

1 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456 using 20mm
size (SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry,
including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site and cost of seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel plate as per the approved shuttering plan,
machine mixing, laying concrete, vibrating, lift charges, curing etc., complete but excluding cost of
steel and it’s fabrication charges for finished item of work (APSS No. 402 & 403) for Columns

columns 1,2,3,10,11,12 6 0.6 0.23 4 3.31


columns 4,5,6,7,8,9 6 0.6 0.35 4 5.04
columns 2 0.6 0.23 4 1.10
9.46
Total qty 10
Cum
2 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456 using 20mm
size (SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry,
including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site and cost of seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel plate as per the approved shuttering plan,
machine mixing, laying concrete, vibrating, lift charges, curing etc., complete but excluding cost of
steel and it’s fabrication charges for finished item of work (APSS No. 402 & 403) for Roof beams

Beam 1-2-3 1 8.09 0.23 0.45 0.84


Beam4-5,6-9 3 9.59 0.3 0.55 4.75
Beam 10-11-12 1 8.96 0.23 0.45 0.93
Beam 1-4-6-8-10 1 15.4 0.23 0.45 1.59
Beam 3-5-7-9-12 1 15.4 0.23 0.45 1.59
Corridor connecting 4 13.85 0.23 0.45 5.73
Entrance corridor beam 1 10.2 0.23 0.45 1.06
Side Entrance beam 1 8.75 0.23 0.45 0.91
Cross beams at corridor 4 1.87 0.23 0.45 0.77
18.17
Total qty 19
Cum
3 Masonry for panel walls in superstructure with CM (1:6) prop: (cement : sand) using Fly
ash lime solid blocks of size 290mm X 225mm X 140mm and having minimum crushing
strength of 75 Kg/Sqcm and using flyash of 80 kgs, cement of 15 kgs, Gypsum of 5 kgs and stone
dust for manufacturing of Fly ash lime solid blocks including cost and conveyance of all materials
like cement, sand, fly ash solid blocks, water etc., to site, including seigniorage charges, sales &
other taxes on all materials and such as labour charges, like mixing cement mortar, scaffolding
charges, constructing masonry, lift charges, curing, etc., complete for finished item of work. (APSS
No. 501 & 504).
Long wall 2 15.1 0.23 3.65 25.35
Cross wall opp dias 1 8.99 0.23 3.55 7.34
Cross wall at dias 1 7.86 0.23 3.55 6.42
Corridor walls 2 13.07 0.23 2 12.02
Corridor walls 2 13.11 0.23 2 12.06
Corridor at dias 1 3.74 0.23 2 1.72
Corridor at dias 1 2 0.23 2 0.92
wall opp 1 10.16 0.23 2 4.67
Deduct Door 2 1.5 0.23 2.4 1.66
Deduct Windows W1 6 1.82 0.23 1.22 3.06
Dias wall 1 8 0.23 0.45 0.83
Dias wall 1 3 0.23 0.45 0.31
steps 2 3 0.3 0.15 0.27
71.92 4.72
Total qty 67.20
Say 68
Cum
4 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456 using 20mm
size (SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry,
including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site and cost of seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel plate as per the approved shuttering plan,
machine mixing, laying concrete, vibrating, lift charges, curing etc., complete but excluding cost of
steel and it’s fabrication charges for finished item of work (APSS No. 402 & 403) for Lintels

over Long wall 2 16.76 0.23 0.2 1.54


over cross wall 2 10.79 0.23 0.2 0.99
Corridor sides 2 13.07 0.23 0.2 1.20
Corridor sides 2 13.11 0.23 0.2 1.21
At Dias L Shape 1 5.74 0.23 0.2 0.26
L Shape 1 14.16 0.23 0.2 0.65
5.86
Say 6
Cum
5 Vibrated Reinforced Cement Concrete M-25 Design Mix as per Table 9 of IS 456 using 20mm
size (SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry,
including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site and cost of seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel plate as per the approved shuttering plan,
machine mixing, laying concrete, vibrating, lift charges, curing etc., complete but excluding cost of
steel and it’s fabrication charges for finished item of work (APSS No. 402 & 403) for Sunshades

At windows 3 2.28 0.6 4.10


At corridor sides 2 13.07 0.6 15.68
At corridor sides 2 13.11 0.6 15.73
At Door 1 3.74 0.6 2.24
At Door 1 2.6 0.6 1.56
Lshape at entrance 1 4 0.6 2.40
opp at entrance wall 1 10.16 0.6 6.10
47.82
Say 49
Sqm
6 Vibrated Reinforced Cement Concrete M-30 Design Mix as per Table 9 of IS 456 using 20mm
size (SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry,
including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site and cost of seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel plate as per the approved shuttering plan,
machine mixing, laying concrete, vibrating, lift charges, curing etc., complete but excluding cost of
steel and it’s fabrication charges for finished item of work (APSS No. 402 & 403) for 15cm Thick
slab.

class Rooms 1 16.76 10.05 168.44


Deduct staircase portion 0.5 1.13 4.19 2.37
Corridor Entrance 1 10.16 4 40.64
Corridor connecting 1 13.11 2 26.22
Sides of door 1 5.8 2 11.60
connecting 1 13.07 2 26.14
273.04 2.37
270.67
Say 275
Sqm
7 Plastering 12mm thick in CM(1:3) for even surfaces including cost and conveyance of all
materials like cement, sand (screened), water etc., to site, including seigniorage charges, sales &
other taxes on all materials, and all operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as directed by Engineer-in-charge etc.,
complete for finished item of work(APSS No. 901 & 903)

ceiling plastering aty same a 1 275 275.00


Qty of Sunshades 1 50 0.75 37.50
Projected column all round 9 1.1 4 39.60
Beams a class Room 6 9.59 0.55 31.65
383.75
Say 390
Sqm
8 Plastering 12mm thick in CM(1:4) for even surfaces including cost and conveyance of all
materials like cement, sand (screened), water etc., to site, including seigniorage charges, sales &
other taxes on all materials, and all operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as directed by Engineer-in-charge etc.,
complete for finished item of work(APSS No. 901 & 903)
Class room long wall 2 16.3 4 130.4
Class room cross wall 2 9.59 4 76.72
Corridor walls at main entra 1 23.27 2.78 64.69
Corridor walls at main entra 1 13.11 2.78 36.45
Sides of corridor 2 13.07 2.78 72.67
1 3.74 2.78 10.40
Cross walls 2 2 2.78 11.12
Deduct qty of Door 1 7.2
Deduct qty of Window 1 13.22
402.44 20.42
382.02
Say 390
Sqm
9 Plastering 20 mm thick in CM(1:4) for even surfaces including cost and conveyance of all
materials like cement, sand (screened), water etc., to site, including seigniorage charges, sales &
other taxes on all materials, and all operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as directed by Engineer-in-charge etc.,
complete for finished item of work(APSS No. 901 & 903)

Building o/s walls 2 16.76 4 134.08


Crass walls 2 10.51 4 84.08
Corridor walls o/s at entarn 1 10.16 2.78 28.24
Corridor walls connecting 1 13.11 2.78 36.45
Lshape at entrance 1 4 2.78 11.12
Sides corridor connecting o/ 2 13.07 2.78 72.67
1 3.59 2.78 9.98
Cross walls 2 2 2.78 11.12
Deduct qty of doors 1 7.2 7.2
Deduct qty of windows 1 13.32 13.32
387.74 20.52
367.22
Say 370
Sqm
10 Supply and Fixing the UPVC Doors with necessary furniture and Locking arrangements

Doors 2 1.5 2.4 7.20


7.20
Say 7.2
Sqm
11 Supply and Fixing the UPVC windows with necessary furniture and Locking arrangements

Windows 6 1.82 1.52 16.60


16.60
Say 16.6
Sqm
12 Flooring / treads with vitrified polished floor tiles of 1st quality and make as approved by
Engineer-in-charge of size 1000 mm x 1000 mm , 8mm to 10mm thick , normal colour with
borders and design as per the approved flooring pattern as directed by the Engineer-In -Charge set
over a base coat of CM (1:8) prop. 12mm thick over CC bed already laid or RCC roof slab ,
including neat cement slurry of honey like consistancy spread @ 3.3 kgs per Sqm. and jointed
neately with white cement paste to full depth mixed with pigment of matching shade including
cost and conveyance of all materials like cement, sand, water, tiles, white cement etc., to site
(excluding cost of C.C. bed) including cost of seigniorage charges on all materials, cost of base
coat and all labour charges for mixing of cement mortar, laying tiles to required slope as
directed by the Engineer- in-charge etc., complete for finished item of work. (APSS No.701 &
707)

Class room 1 16.3 9.59 156.32


Skurtting 2 16.3 0.1 3.26
Skurtting 8 9.59 0.1 7.67
Dias wall 1 8 0.45 3.60
Cross wall 1 3 0.45 1.35
Connecting corridor 2 13.85 2 55.40
Skurtting 4 13.85 0.1 5.54
front Coridor 1 10.2 3.85 39.27
Skurtting 2 10.2 0.1 2.04
Dias side corridor 1 5.74 1.87 10.73
Skurtting 1 5.74 0.1 0.57
Skurtting 1 1.87 0.1 0.19
285.94
Say 290
Sqm
13 Painting with plastic emulsion paint of grade-1 standard make to interior faces of new walls two
coat of approved make shade and colour over primer coat two coats of putty with cement primer grade
- I including cost and conveyance of materials like Plastic Emulsion paint, white cement to site
including cost of brushes, scaffolding charges, lift charges and labour charges such as preparing the
wall, applying primer coat , two coats of Plastic Emulsion etc., complete for finished item of work
(APSS No.910, 911&1201) in all floors.

qty same as (1:3) 12mm 1 390 390


thick
1 390 390
qty same as (1:4) 12mm
thick
1 370 370
qty same as (1:4)20mm
thick
1150
Say 1150
Sqm
14 Providing Enamel Paint two coats approved brand and shade over base coat of Zich Chromite
approved brand and shade etc complete
Grills 1 16.6 1 16.6
16.6
Say 16.6
Sqm
15 Supplying , fitting and placing HYSD / TMT bar reinforcement in VRCC works complete as per
drawings and technical specifications for bars below 36mm dia including over laps and wastage,where
they are not welded including cost and conveyance of steel , binding wire etc., lifting charges of steel ,
placing in position, tying with binding wire , all tools etc., complete for finished item of work
Column 1 14 175 2450
Roof Beams 1 19 175 3325
15cm thick salb 1 275 0.15 80 3300
Lintels 1 6 120 600
Sunshades 1 49 0.06 80 168
9843
Say 10000
Kgs
Abstract
Providing additional class Rooms to Acadamic block in Damadaraya Sanjivayya National Law University
at Sabbavarm, Visakhapatnam.
GROUND FLOOR

S.No Quantity Description of work Rate per Amount


1 135 Cum Earth work excavation for foundations (Mechanical 101.59 1Cum 13715
Means) of buildings in ordinary soils and depositing on
bank with an initial lead of 10m and depth up to 3m
including all operational,incidental, labour charges such as
shoring, sheeting, planking, strutting etc., complete for
finished item of work including seigniorage excluding
dewatering charges etc., as per SS 20 B(APSS 308)

2 17 Cum Plain Cement Concrete (1:5:10) proportion nominal 3675.65 1Cum 62487
mix (cement: fine aggregate: Coarse aggregate) for
foundations and under flooring bed using 40mm size
(SS5) hard,machine crushed granite metal from
approved quarry including cost and conveyance of all
materials like cement, sand, coarse aggregate, water etc.
to site, including seigniorage charges, sales & other taxes
on all materials and including all charges for machine
mixing, laying concrete in foundations and under flooring
bed, ramming in 15 cm layers finishing top surface to the
required level curing etc., complete for finished item of
work. (APSS No. 402)
3 14 Cum Vibrated Reinforced Cement Concrete M-25 Design 8637.9 1Cum 120931
Mix as per Table 9 of IS 456 using 20mm size (SS5)
hard granite machine crushed graded metal (Coarse
aggregate) from approved quarry, including cost and
conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site and cost of
seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel
plate as per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges, curing
etc., complete but excluding cost of steel and it’s
fabrication charges for finished item of work (APSS No.
402 & 403) for Column bases

4 14 Cum Vibrated Reinforced Cement Concrete M-25 Design 12006.58 1Cum 168093
Mix as per Table 9 of IS 456 using 20mm size (SS5)
hard granite machine crushed graded metal (Coarse
aggregate) from approved quarry, including cost and
conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site and cost of
seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel
plate as per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges, curing
etc., complete but excluding cost of steel and it’s
fabrication charges for finished item of work (APSS No.
402 & 403) for Column
5 100 Cum Providing R.R Masonary in cm(1:6) using rough stone etc 4131.04 1Cum 413104
complete
6 11 Cum Vibrated Reinforced Cement Concrete M-30 Design 11305.58 1Cum 124362
Mix as per Table 9 of IS 456 using 20mm size (SS5)
hard granite machine crushed graded metal (Coarse
aggregate) from approved quarry, including cost and
conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site and cost of
seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel
plate as per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges, curing
etc., complete but excluding cost of steel and it’s
fabrication charges for finished item of work (APSS No.
402 & 403) for Plinth Beams

7 135 Cum Filling with excavated earth by lorries including 34.51 1Cum 4659
Consolidations at 15cm layers watering etc complete as
directed by Engineer Incharge

8 210 Cum Filling withborrowed earth by lorries including 503.48 1Cum 105731
Consolidations at 15cm layers watering etc complete as
directed by Engineer Incharge

9 275 Sqm Plain Cement Concrete (1:5:10) proportion nominal 3675.65 10Sqm 101081
mix (cement: fine aggregate: Coarse aggregate) for
foundations and under flooring bed using 40mm size
(SS5) hard,machine crushed granite metal from
approved quarry including cost and conveyance of all
materials like cement, sand, coarse aggregate, water etc.
to site, including seigniorage charges, sales & other taxes
on all materials and including all charges for machine
mixing, laying concrete in foundations and under flooring
bed, ramming in 15 cm layers finishing top surface to the
required level curing etc., complete for finished item of
work. (APSS No. 402)
10 275 Sqm Providing Antitermite treatment as per IS 6315 (Part - 2) 170.43 1Sqm 46869
2001 (Pre-constructional chemical treatment measures)
along the internal & external vertical faces of the columns,
plinth beams, basement and top surface of the basement
filling below flooring bed as per the specified procedure
conforming to IS 6315 (Part-2) 2001 and other relevant
approved specification duly using Chlorpyriphos/ Lindane
emulsifiable concentrate 20% with 1% concentration @ 7.5
Liters/ sqm of the vertical surface & @ 5.0 Liters/ sqm of
the horizontal surface of the substructure to a depth of 500
mm around columns & 300 mm deep around plinth beams,
basements & floor filling area including excavation channel
along the wall & rodding etc & cost & conveyance of all
materials to the site, cost of labour for spraying, rodding etc
complete for finished item of work as per the approval of
the Engineer-in-Charge

11 19 Cum Vibrated Reinforced Cement Concrete M-25 Design 11170.38 1Cum 212238
Mix as per Table 9 of IS 456 using 20mm size (SS5)
hard granite machine crushed graded metal (Coarse
aggregate) from approved quarry, including cost and
conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site and cost of
seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel
plate as per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges, curing
etc., complete but excluding cost of steel and it’s
fabrication charges for finished item of work (APSS No.
402 & 403) for Roof Beams

12 68 Cum Masonry for panel walls in superstructure with CM 6416.5 1Cum 436322
(1:6) prop: (cement : sand) using Fly ash lime solid
blocks of size 290mm X 225mm X 140mm and
having minimum crushing strength of 75 Kg/Sqcm and
using flyash of 80 kgs, cement of 15 kgs, Gypsum of 5
kgs and stone dust for manufacturing of Fly ash lime
solid blocks including cost and conveyance of all
materials like cement, sand, fly ash solid blocks, water
etc., to site, including seigniorage charges, sales & other
taxes on all materials and such as labour charges, like
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., complete for finished
item of work. (APSS No. 501 & 504).
13 6 Cum Vibrated Reinforced Cement Concrete M-25 Design 11905.23 1Cum 71432
Mix as per Table 9 of IS 456 using 20mm size (SS5)
hard granite machine crushed graded metal (Coarse
aggregate) from approved quarry, including cost and
conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site and cost of
seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel
plate as per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges, curing
etc., complete but excluding cost of steel and it’s
fabrication charges for finished item of work (APSS No.
402 & 403) for Lintels
14 49 Sqm Vibrated Reinforced Cement Concrete M-25 Design 1178.93 1Sqm 57768
Mix as per Table 9 of IS 456 using 20mm size (SS5)
hard granite machine crushed graded metal (Coarse
aggregate) from approved quarry, including cost and
conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site and cost of
seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel
plate as per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges, curing
etc., complete but excluding cost of steel and it’s
fabrication charges for finished item of work (APSS No.
402 & 403) for Sunshades
15 275 Sqm Vibrated Reinforced Cement Concrete M-25 Design 14762.99 10Sqm 405983
Mix as per Table 9 of IS 456 using 20mm size (SS5)
hard granite machine crushed graded metal (Coarse
aggregate) from approved quarry, including cost and
conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site and cost of
seigniorage charges on all materials including centering,
shuttering and scaffolding with props and steel
plate as per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges, curing
etc., complete but excluding cost of steel and it’s
fabrication charges for finished item of work (APSS No.
402 & 403) for 15cm Thick slab.
16 390 Sqm Plastering 12mm thick in CM(1:3) for even 3776.47 10Sqm 147283
surfaces including cost and conveyance of all materials
like cement, sand (screened), water etc., to site,
including seigniorage charges, sales & other taxes on all
materials, and all operational, incidental charges on
materials and including cost of all labour charges for
mixing mortar, finishing, curing as directed by Engineer-
in-charge etc., complete for finished item of work(APSS
No. 901 & 903)
17 390 Sqm Plastering 12mm thick in CM(1:4) for even 3500 10Sqm 136500
surfaces including cost and conveyance of all materials
like cement, sand (screened), water etc., to site,
including seigniorage charges, sales & other taxes on all
materials, and all operational, incidental charges on
materials and including cost of all labour charges for
mixing mortar, finishing, curing as directed by Engineer-
in-charge etc., complete for finished item of work(APSS
No. 901 & 903)
18 370 Sqm Plastering 20 mm thick in CM(1:4) for even 3900 10Sqm 144300
surfaces including cost and conveyance of all materials
like cement, sand (screened), water etc., to site,
including seigniorage charges, sales & other taxes on all
materials, and all operational, incidental charges on
materials and including cost of all labour charges for
mixing mortar, finishing, curing as directed by Engineer-
in-charge etc., complete for finished item of work(APSS
No. 901 & 903)
19 7.2 Sqm Supply and Fixing the UPVC Doors with necessary 9335.74 1Sqm 6722
furniture and Locking arrangements

20 16.6 Sqm Supply and Fixing the UPVC windows with necessary 9155 1Sqm 15198
furniture and Locking arrangements three track
21 290 Sqm Flooring / treads with vitrified polished floor tiles 1010.83 1Sqm 29315
of 1st quality and make as approved by Engineer-in-
charge of size 1000 mm x 1000 mm , 8mm to
10mm thick , normal colour with borders and design
as per the approved flooring pattern as directed by the
Engineer-In -Charge set over a base coat of CM (1:8)
prop. 12mm thick over CC bed already laid or RCC roof
slab , including neat cement slurry of honey like
consistancy spread @ 3.3 kgs per Sqm. and jointed
neately with white cement paste to full depth mixed with
pigment of matching shade including cost and
conveyance of all materials like cement, sand, water,
tiles, white cement etc., to site (excluding cost of C.C.
bed) including cost of seigniorage charges on all
materials, cost of base coat and all labour charges for
mixing of cement mortar, laying tiles to required slope
as directed by the Engineer- in-charge etc., complete
for finished item of work. (APSS No.701 & 707)
22 1150 Sqm Painting with plastic emulsion paint of grade-1 1920.89 10Sqm 220903
standard make to interior faces of new walls two coat of
approved make shade and colour over primer coat with
cement primer grade - I including cost and conveyance of
materials like Plastic Emulsion paint, white cement to site
including cost of brushes, scaffolding charges, lift charges
and labour charges such as preparing the wall, applying
primer coat , two coats of Plastic Emulsion etc., complete
for finished item of work (APSS No.910, 911&1201) in all
floors.

23 20 Sqm Providing Enamel Paint two coats approved brand and 1791.99 10Sqm 3584
shade over base coat of Zich Chromite approved brand
and shade etc complete

24 11000 Kgs Supplying , fitting and placing HYSD / TMT bar 62.92 1Kg 69212
reinforcement in VRCC works complete as per drawings
and technical specifications for bars below 36mm dia
including over laps and wastage,where they are not welded
including cost and conveyance of steel , binding wire etc.,
lifting charges of steel , placing in position, tying with
binding wire , all tools etc., complete for finished item of
work
3117792
25 Add GST @12% 374136
26 Add Sciegniorege charges 52000
27 Ls Contengency and Unforseen items 1072
Total Amount 3545000
Abstract
Providing additional class Rooms to Acadamic block in Damadaraya Sanjivayya National Law
University at Sabbavarm, Visakhapatnam.

FIRST FLOOR
S.No Quantity Description of work Rate per Amount
1 10 Cum Vibrated Reinforced Cement Concrete M-25 12707.15 1Cum 127072
Design Mix as per Table 9 of IS 456 using 20mm
size (SS5) hard granite machine crushed graded
metal (Coarse aggregate) from approved quarry,
including cost and conveyance of all materials like
cement, fine aggregate (Sand), coarse aggregate,
water etc., to site and cost of seigniorage charges
on all materials including centering, shuttering
and scaffolding with props and steel plate as
per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges,
curing etc., complete but excluding cost of steel and
it’s fabrication charges for finished item of work
(APSS No. 402 & 403) for Column
2 19 Cum Vibrated Reinforced Cement Concrete M-25 11654.68 1Cum 221439
Design Mix as per Table 9 of IS 456 using 20mm
size (SS5) hard granite machine crushed graded
metal (Coarse aggregate) from approved quarry,
including cost and conveyance of all materials like
cement, fine aggregate (Sand), coarse aggregate,
water etc., to site and cost of seigniorage charges
on all materials including centering, shuttering
and scaffolding with props and steel plate as
per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges,
curing etc., complete but excluding cost of steel and
it’s fabrication charges for finished item of work
(APSS No. 402 & 403) for Roof Beams

3 68 Cum Masonry for panel walls in superstructure with 6840.18 1Cum 465133
CM (1:6) prop: (cement : sand) using Fly ash
lime solid blocks of size 290mm X 225mm X
140mm and having minimum crushing strength of
75 Kg/Sqcm and using flyash of 80 kgs, cement of
15 kgs, Gypsum of 5 kgs and stone dust for
manufacturing of Fly ash lime solid blocks including
cost and conveyance of all materials like cement,
sand, fly ash solid blocks, water etc., to site,
including seigniorage charges, sales & other taxes
on all materials and such as labour charges, like
mixing cement mortar, scaffolding charges,
constructing masonry, lift charges, curing, etc.,
complete for finished item of work. (APSS No. 501
& 504).
4 6 Cum Vibrated Reinforced Cement Concrete M-25 12502.42 1Cum 75015
Design Mix as per Table 9 of IS 456 using 20mm
size (SS5) hard granite machine crushed graded
metal (Coarse aggregate) from approved quarry,
including cost and conveyance of all materials like
cement, fine aggregate (Sand), coarse aggregate,
water etc., to site and cost of seigniorage charges
on all materials including centering, shuttering
and scaffolding with props and steel plate as
per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges,
curing etc., complete but excluding cost of steel and
it’s fabrication charges for finished item of work
(APSS No. 402 & 403) for Lintels
5 49 Sqm Vibrated Reinforced Cement Concrete M-25 1240.78 1Sqm 60799
Design Mix as per Table 9 of IS 456 using 20mm
size (SS5) hard granite machine crushed graded
metal (Coarse aggregate) from approved quarry,
including cost and conveyance of all materials like
cement, fine aggregate (Sand), coarse aggregate,
water etc., to site and cost of seigniorage charges
on all materials including centering, shuttering
and scaffolding with props and steel plate as
per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges,
curing etc., complete but excluding cost of steel and
it’s fabrication charges for finished item of work
(APSS No. 402 & 403) for Sunshades
6 275 Sqm Vibrated Reinforced Cement Concrete M-25 15386.06 10Sqm 423117
Design Mix as per Table 9 of IS 456 using 20mm
size (SS5) hard granite machine crushed graded
metal (Coarse aggregate) from approved quarry,
including cost and conveyance of all materials like
cement, fine aggregate (Sand), coarse aggregate,
water etc., to site and cost of seigniorage charges
on all materials including centering, shuttering
and scaffolding with props and steel plate as
per the approved shuttering plan, machine
mixing, laying concrete, vibrating, lift charges,
curing etc., complete but excluding cost of steel and
it’s fabrication charges for finished item of work
(APSS No. 402 & 403) for 15cm Thick slab.
7 390 Sqm Plastering 12mm thick in CM(1:3) for even 4106.13 10Sqm 160140
surfaces including cost and conveyance of all
materials like cement, sand (screened), water
etc., to site, including seigniorage charges, sales &
other taxes on all materials, and all operational,
incidental charges on materials and including cost of
all labour charges for mixing mortar, finishing,
curing as directed by Engineer-in-charge etc.,
complete for finished item of work(APSS No. 901 &
903)
8 390 Sqm Plastering 12mm thick in CM(1:4) for even 3700 10Sqm 144300
surfaces including cost and conveyance of all
materials like cement, sand (screened), water
etc., to site, including seigniorage charges, sales &
other taxes on all materials, and all operational,
incidental charges on materials and including cost of
all labour charges for mixing mortar, finishing,
curing as directed by Engineer-in-charge etc.,
complete for finished item of work(APSS No. 901 &
903)
9 370 Sqm Plastering 20 mm thick in CM(1:4) for even 4100 10Sqm 151700
surfaces including cost and conveyance of all
materials like cement, sand (screened), water
etc., to site, including seigniorage charges, sales &
other taxes on all materials, and all operational,
incidental charges on materials and including cost of
all labour charges for mixing mortar, finishing,
curing as directed by Engineer-in-charge etc.,
complete for finished item of work(APSS No. 901 &
10 7.2 Sqm 903)
Supply and Fixing the UPVC Doors with necessary 9335.74 1Sqm 67218
furniture and Locking arrangements

11 16.6 Sqm Supply and Fixing the UPVC windows with 9155 1Sqm 151973
necessary furniture and Locking arrangements

12 290 Sqm Flooring / treads with vitrified polished floor 1056.9 1Sqm 306501
tiles of 1st quality and make as approved by
Engineer-in-charge of size 1000 mm x 1000 mm
, 8mm to 10mm thick , normal colour with
borders and design as per the approved flooring
pattern as directed by the Engineer-In -Charge set
over a base coat of CM (1:8) prop. 12mm thick
over CC bed already laid or RCC roof slab , including
neat cement slurry of honey like consistancy
spread @ 3.3 kgs per Sqm. and jointed neately
with white cement paste to full depth mixed with
pigment of matching shade including cost and
conveyance of all materials like cement, sand,
water, tiles, white cement etc., to site (excluding
cost of C.C. bed) including cost of seigniorage
charges on all materials, cost of base coat and all
labour charges for mixing of cement mortar, laying
tiles to required slope as directed by the
Engineer- in-charge etc., complete for finished item
13 1150 Sqm of work. (APSS
Painting No.701 &
with plastic 707)
emulsion paint of grade-1 1920.89 10Sqm 220903
standard make to interior faces of new walls two
coat of approved make shade and colour over primer
coat with cement primer grade - I including cost and
conveyance of materials like Plastic Emulsion paint,
white cement to site including cost of brushes,
scaffolding charges, lift charges and labour charges
such as preparing the wall, applying primer coat ,
two coats of Plastic Emulsion etc., complete for
finished item of work (APSS No.910, 911&1201) in all
floors.
14 20 Sqm Providing Enamel Paint two coats approved brand 1791.99 10Sqm 3584
and shade over base coat of Zich Chromite approved
brand and shade etc complete

15 10000 Kgs Supplying , fitting and placing HYSD / TMT bar 64.58 1Kg 645800
reinforcement in VRCC works complete as per
drawings and technical specifications for bars below
36mm dia including over laps and wastage,where
they are not welded including cost and conveyance of
steel , binding wire etc., lifting charges of steel ,
placing in position, tying with binding wire , all tools
etc., complete for finished item of work

3224694
16 Add GST @12% 386964
17 Add Sciegniorege charges 14500
18 Ls Contengency and Unforseen items 842
Total Amount 3627000
Abstract
Providing additional class Rooms to Acadamic block in Damadaraya Sanjivayya National Law University
at Sabbavarm, Visakhapatnam.

SECOND FLOOR
S.No Quantity Description of work Rate per Amount
1 10 Cum Vibrated Reinforced Cement Concrete M-25 Design 13407.22 1Cum 134073
Mix as per Table 9 of IS 456 using 20mm size (SS5) hard
granite machine crushed graded metal (Coarse aggregate)
from approved quarry, including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site and cost of seigniorage
charges on all materials including centering, shuttering
and scaffolding with props and steel plate as per the
approved shuttering plan, machine mixing, laying
concrete, vibrating, lift charges, curing etc., complete but
excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for Column
2 19 Cum Vibrated Reinforced Cement Concrete M-25 Design 12140.56 1Cum 230671
Mix as per Table 9 of IS 456 using 20mm size (SS5) hard
granite machine crushed graded metal (Coarse aggregate)
from approved quarry, including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site and cost of seigniorage
charges on all materials including centering, shuttering
and scaffolding with props and steel plate as per the
approved shuttering plan, machine mixing, laying
concrete, vibrating, lift charges, curing etc., complete but
excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for Roof
Beams

3 68 Cum Masonry for panel walls in superstructure with CM 7866.63 1Cum 534931
(1:6) prop: (cement : sand) using Fly ash lime solid
blocks of size 290mm X 225mm X 140mm and having
minimum crushing strength of 75 Kg/Sqcm and using flyash
of 80 kgs, cement of 15 kgs, Gypsum of 5 kgs and stone
dust for manufacturing of Fly ash lime solid blocks including
cost and conveyance of all materials like cement, sand, fly
ash solid blocks, water etc., to site, including seigniorage
charges, sales & other taxes on all materials and such as
labour charges, like mixing cement mortar, scaffolding
charges, constructing masonry, lift charges, curing, etc.,
complete for finished item of work. (APSS No. 501 & 504).

4 6 Cum Vibrated Reinforced Cement Concrete M-25 Design 13098.01 1Cum 78589
Mix as per Table 9 of IS 456 using 20mm size (SS5) hard
granite machine crushed graded metal (Coarse aggregate)
from approved quarry, including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site and cost of seigniorage
charges on all materials including centering, shuttering
and scaffolding with props and steel plate as per the
approved shuttering plan, machine mixing, laying
concrete, vibrating, lift charges, curing etc., complete but
excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for Lintels

5 49 Sqm Vibrated Reinforced Cement Concrete M-25 Design 1146.52 1Sqm 56180
Mix as per Table 9 of IS 456 using 20mm size (SS5) hard
granite machine crushed graded metal (Coarse aggregate)
from approved quarry, including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site and cost of seigniorage
charges on all materials including centering, shuttering
and scaffolding with props and steel plate as per the
approved shuttering plan, machine mixing, laying
concrete, vibrating, lift charges, curing etc., complete but
excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for Sunshades
6 275 Sqm Vibrated Reinforced Cement Concrete M-25 Design 15993.2 10Sqm 439813
Mix as per Table 9 of IS 456 using 20mm size (SS5) hard
granite machine crushed graded metal (Coarse aggregate)
from approved quarry, including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site and cost of seigniorage
charges on all materials including centering, shuttering
and scaffolding with props and steel plate as per the
approved shuttering plan, machine mixing, laying
concrete, vibrating, lift charges, curing etc., complete but
excluding cost of steel and it’s fabrication charges for
finished item of work (APSS No. 402 & 403) for 15cm
Thick slab.

7 390 Sqm Plastering 12mm thick in CM(1:3) for even surfaces 4511.05 10Sqm 175931
including cost and conveyance of all materials like cement,
sand (screened), water etc., to site, including seigniorage
charges, sales & other taxes on all materials, and all
operational, incidental charges on materials and including
cost of all labour charges for mixing mortar, finishing,
curing as directed by Engineer-in-charge etc., complete for
finished item of work(APSS No. 901 & 903)
8 390 Sqm Plastering 12mm thick in CM(1:4) for even surfaces 3900 10Sqm 152100
including cost and conveyance of all materials like cement,
sand (screened), water etc., to site, including seigniorage
charges, sales & other taxes on all materials, and all
operational, incidental charges on materials and including
cost of all labour charges for mixing mortar, finishing,
curing as directed by Engineer-in-charge etc., complete for
finished item of work(APSS No. 901 & 903)
9 370 Sqm Plastering 20 mm thick in CM(1:4) for even surfaces 4300 10Sqm 159100
including cost and conveyance of all materials like cement,
sand (screened), water etc., to site, including seigniorage
charges, sales & other taxes on all materials, and all
operational, incidental charges on materials and including
cost of all labour charges for mixing mortar, finishing,
curing as directed by Engineer-in-charge etc., complete for
finished item of work(APSS No. 901 & 903)

10 7.2 Sqm Supply and Fixing the UPVC Doors with necessary furniture 9335.74 1Sqm 67218
and Locking arrangements

11 16.6 Sqm Supply and Fixing the UPVC windows with necessary 9155 1Sqm 151973
furniture and Locking arrangements

12 290 Sqm Flooring / treads with vitrified polished floor tiles of 1102.97 1Sqm 319862
1st quality and make as approved by Engineer-in-charge
of size 1000 mm x 1000 mm , 8mm to 10mm thick ,
normal colour with borders and design as per the
approved flooring pattern as directed by the Engineer-In
-Charge set over a base coat of CM (1:8) prop. 12mm
thick over CC bed already laid or RCC roof slab , including
neat cement slurry of honey like consistancy spread @
3.3 kgs per Sqm. and jointed neately with white cement
paste to full depth mixed with pigment of matching shade
including cost and conveyance of all materials like
cement, sand, water, tiles, white cement etc., to site
(excluding cost of C.C. bed) including cost of seigniorage
charges on all materials, cost of base coat and all labour
charges for mixing of cement mortar, laying tiles to
required slope as directed by the Engineer- in-charge
etc., complete for finished item of work. (APSS No.701 &
707)
13 1150 Sqm Painting with plastic emulsion paint of grade-1 standard 1920.89 10Sqm 220903
make to interior faces of new walls two coat of approved
make shade and colour over primer coat with cement primer
grade - I including cost and conveyance of materials like
Plastic Emulsion paint, white cement to site including cost of
brushes, scaffolding charges, lift charges and labour charges
such as preparing the wall, applying primer coat , two coats
of Plastic Emulsion etc., complete for finished item of work
(APSS No.910, 911&1201) in all floors.

14 16.6 Sqm Providing Enamel Paint two coats approved brand and shade 1791.99 10Sqm 2975
over base coat of Zich Chromite approved brand and shade
etc complete
15 10000 Kgs Supplying , fitting and placing HYSD / TMT bar 66.25 1Kg 66250
reinforcement in VRCC works complete as per drawings and
technical specifications for bars below 36mm dia including
over laps and wastage,where they are not welded including
cost and conveyance of steel , binding wire etc., lifting
charges of steel , placing in position, tying with binding wire ,
all tools etc., complete for finished item of work

2790569
16 Add GST @12% 334869
17 Add Sciegniorege charges 14000
18 Ls Contengency and Unforseen items 562
Total Amount 3140000