Professional Documents
Culture Documents
Case Gil, N. (2008) - BAA: The T5 Project Agreement (A) : Background
Case Gil, N. (2008) - BAA: The T5 Project Agreement (A) : Background
Case Gil, N. (2008) - BAA: The T5 Project Agreement (A) : Background
Background:
Project T5 includes 16 major projects with a total cost of about 3.1 billion pounds,
including buildings and baggage handling systems for London Heathrow Airport. It is a
large-scale and extremely challenging project for BAA whose valuation is only 5.5 billion
pounds. BAA decided to implement the T5 agreement, considering that if the project is
carried out as usual, it will delay delivery and exceed the budget.
designing the contract by BAA's legal and commercial team is to minimize the conflicts that
usually plague major projects and ensure the successful completion of the project. The T5
agreement aims to encourage suppliers to adopt best practices and excellent performance,
actively seek and provide affordable and excellent solutions, and get rid of the traditional
practice of infrastructure customers choosing the supplier with the lowest bid. Under T5
agreement, BAA reserves the right to carry out audit reviews to all the financial information
of suppliers and encourage them to change their work habits. In addition, the T5 agreement is
associated with a policy document that sets out the commercial terms and conditions
applicable to the relationship between BAA and its primary suppliers. And it turns out that
under the framework of T5 agreement, the project did not exceed the budget or overtime
when the project was halfway through. Therefore, BAA is considering whether to continue to
The first option is using the first tier suppliers who have been involved in the previous
project. They will take responsibility for procuring key suppliers from the global market,
training employees and undertaking the project management. Mitigating the risks is the first
advantage of contracting with the incumbent suppliers in the work packages selection. Since
these suppliers had cooperated with BAA in the previous project, they knew exactly the
clauses of the T5 agreement, the possibility of miscommunication which directly impacts the
project deliverables can be avoided. Cost-saving is a crucial advantage as well. The previous
project met both the financial constraints and the project schedule, and there were not any
conflicts during the collaboration process, the BAA do not need to spend money on training
suppliers for adjusting to their styles. Time-saving is the last advantage. To find fit-out
time-consuming. And BAA suffers the stress unders the project time schedule.
suppliers to procure suitable key suppliers for the fit-out work packages would not be the
optimal choice, considering the economic benefit. Since the first-tier suppliers helped reduce
the operational risks in the process, BAA would have to pay more for the overheads and
profit recovery of the first-tier suppliers. It would also be easy for them to utilize the
information asymmetry between BAA and the sub-tier suppliers to bargain for more.
Furthermore, once implemented this mode, BAA might not be able to inform the second-tier
suppliers of some necessary changes or monitor their performance directly due to the
existence of hierarchy, instead the information would be passed through the first-tier
BBA directly selects fit-out suppliers from the international market by putting out to
tender is an alternative plan for fit-out work, and whether extending the application of T5
tier suppliers, finishing works on time and within budget. In general, T5 agreement is an
enabler for BAA, it makes supplier teams and BAA staffs work as one team, trusting and
relying on each other to achieve the same goal. Because the high level of transparency is
required by T5 agreement, BAA can better control new suppliers in profit margin and risks.
Also, the policies in T5 agreement such as, incentive plan, risk management, and the way of
compensating can engage the suppliers from the international market which are the leader in
Option3: Procure new fit-out suppliers using traditional commercial contract (Without
T5 Agreement)
The third choice is that BAA can seek potential suppliers for the fit-out work
packages from the market around the world. By issuing a notice at the OJEC with a call for
pre-qualification documents, BAA is able to have some potential qualified suppliers who will
be invited for presentations. Next, BAA will negotiate the final commercial arrangements for
each work package with the suppliers that are selected according to the bids. Different from
the second choice, these fit-out suppliers will not be considered as the first supplier and use
T5 agreement. BAA should make commercial contracts with these fit-out companies. Then
things will go as the suppliers normally do on major construction projects without the
The fit-out work of the Terminal 5 is relatively scattered, and many small decoration
companies need to be invited if BAA try to directly procure key suppliers for the fit-out work
packages from the international market. These small decoration companies are not familiar
with the working process and mode of T5 contract. Introducing and explaining T5 contracts
to these small companies will bring a lot of extra expenses. Compared with T5 contracts,
expenditures. If BAA applies the T5 contract, BAA needs to audit the financial information
of the decoration company, which will bring great pressure to the management, while the
Since the T5 agreement proved to be successful in the massive works, BAA definitely
could still trust those first-tier suppliers and let them handle the fit-out phase. Since the
previous data shows that the implementation of T5 agreement will neither delay the
construction period nor overrun the budget, there is reason to believe that the first-tier
contractor can bring this good inertia into the next stage of work. Because the entire project
budget has been locked, and there is no sign of exceeding the budget, there is no need to
If BAA insists on procuring the fit-out suppliers from the market, there are still two
ways it could help BAA do better. First, before the end of the first stage, the bidding will be
started in advance, and all subsequent processes will be followed up in turn. In this way, the
time saved compared with the original plan can be used to implement T5 agreement with new
partners. Second, BAA can also invite relevant responsible persons from the original first-tier
suppliers to give guest speeches, to help new partners accelerate their understanding and use
from the perspective and thinking of the people who have benefited. Of course, in reverse, it
is also possible for the new partner to send a representative to the first-tier suppliers to