Professional Documents
Culture Documents
ITD-GEN-000-CIV-CHK-0004 - 0 - Bored Piles ITPs
ITD-GEN-000-CIV-CHK-0004 - 0 - Bored Piles ITPs
"W" - WITNESS POINT - Work shall be witnessed for the inspection stage. Contractor shall notify the
COMPANY / PMC and raise RFI.
"S" - SURVEILLANCE - Surveillance can be carried out for on-going activity but formal notification and RFI is
not required.
"R" - REVIEW - Document shall submitted for review and approval through transmittal. Work shall not be
proceeded unless contractor has received Code-A / Code-B from PMC / COMPANY.
"RFI" - REQUEST FOR INSPECTION - Contractor shall submit the FRI along-with their inspection
notification.
SCOPE OF WORK
Contractor shall "briefly" specify their Scope of Work:
ITP - INSPECTION & TEST PLAN
BORED CAST-IN-SITU PILES
Document No : ITD-GEN-000-CIV-CHK-0004; Rev-0
Reference Document Verifying Document Contractor Checklist
No. Activity PMC Reference
Acceptance Criteria (Inspection Report & Checklist) QC
RFI
Checklist-
1 Piles Locations / Coordinates AFC Drawing Checklist 4-1 H W 4-1
Survey Report
AFC Drawing.
RFI
Checklist-
3 Steel Cages and Lowering MOS & DS for Bentonite.
Checklist 4-1
4-1
MOS for Casing Erection.
H R
AFC Drawing. RFI
Concrete Placing, Slump and Approved Mix design Checklist 4-1 Checklist-
4
Speciments for Crushing Test. Approved PB Crushing Test Report 4-1
Approved TPI list
AFC Drawing RFI
Integrity Test
5 MOS for Integrity test Integrity Test report H R/W
(Random witness by PMC)
Approval of Lab
AFC Drawing
Pile Load Test RFI
6 MOS for Pile load test
Pile Load Test Report
H R/W
(Random witness by PMC)
Approval of Lab
Note :
1. Contractor shall attach "Inspection Reports" of ITP along-with RFI.
2. PMC / Contractor to complete the "Inspection Checklist" attached with RFI.
3. PMC is to ensure that all inspection record is complete and has been placed in MC / PA / Dossiers.
Inspection Checklist
Bored Cast-in-Place Piles
Document # : Checklist-3-4
Report # PRID #: Project Name: Contractor :
RFI No :
Inspector's Checklist
Inspector's Observation -
Sr # Description of Activity State NA if not applicable
(Record the Data)
□ Yes □ No
PTW:
1
PTW issued and approved by relative parties. PTW # : …………………………………………..
□ OK □ Not OK
Accessibility :
Comments:…………………………………………………
2 Accessibility to work location and availability of suitable space for
……………………………………………………………
manouvering.
□ Done □ Not Done
Existing Facilities: Comments:…………………………………………………
3
Identify and Protection of Existing Facilities (AG&UG) …………………………………………………………
□ Yes □ No
Good Condition Drilling Machine, Vibro-hammer, Complete Services
Comments:…………………………………………………
5 Equipment and Drilling tools (Augers & Pockets for clay and rock)
…………………………………………………………
available at site.
□ Yes □ No □ N/A
Steel Cages: Main Rebar: Dia……...…
6 Fabricated Steel Cages free of rust and meeting the specification & Stirrups: Dia……...…
AFC drawing requirements available and achievable for lowering. Rings: Dia……...…
□ Yes □ No □ N/A
Bentonite: Comments:…………………………………………………
7 Sufficient quantity of Bentonite with necessary mixing pumps and …………………………………………………………
tools available at site.
□ Yes □ No □ N/A
Availability of Correct Casing: Dia………………………...
8 Thickness………………..
Casing of suitable length, diameter and thickness available at site.
CONTRACTOR QC PMC
Name
Date
Signature