Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

Contractor

Legends & Scope Logo

LEGENDS & DEFINITATIONS


"H" - HOLD POINT - Work shall not be proceeded further without the inspection for this stage. Contractor
shall notify the COMPANY / PMC and raise RFI.

"W" - WITNESS POINT - Work shall be witnessed for the inspection stage. Contractor shall notify the
COMPANY / PMC and raise RFI.

"S" - SURVEILLANCE - Surveillance can be carried out for on-going activity but formal notification and RFI is
not required.

"R" - REVIEW - Document shall submitted for review and approval through transmittal. Work shall not be
proceeded unless contractor has received Code-A / Code-B from PMC / COMPANY.

"RFI" - REQUEST FOR INSPECTION - Contractor shall submit the FRI along-with their inspection
notification.

SCOPE OF WORK
Contractor shall "briefly" specify their Scope of Work:
ITP - INSPECTION & TEST PLAN
Building Construction - Civil
Document No : ITD-GEN-000-CIV-CHK-0005; Rev-0
Verifying Document
Reference Document Chcecklist
No. Activity (Inspection Report & Contractor PMC
Acceptance Criteria Reference
Checklist)

Please follow the following ITP: 1-1


1 Excavation & Backfilling
ITD-GEN-000-CIV-CHK-0001 - Earthwork 1-2

Please follow the following ITP: 2-1


2 Concrete Work for Building Structure
ITD-GEN-000-CIV-CHK-0002 - Concreting 2-2

3 Masonary Work Brickwall Installation Contactor's Form & RFI W W 5-1


Constrction Drawing

4 Plastering Construction Drawings Contactor's Form & RFI W W 5.2

5 Doors & Windows Construction Drawings Contactor's Form & RFI W W 5-3

6 Plumbing, Drainage & Sanitry Fixing Construction Drawings Contactor's Form & RFI W W 5-6

Waterproofing & Thermal Insulation for of


7 Construction Drawings Contactor's Form & RFI W W 5-4
Roof Slab
8 Walkways & Curbs Construction Drawings Contactor's Form & RFI W W Nil

Construction Drawings & Spec


9 Painting , Tiles and Decoration for color Coding
Contactor's Form & RFI W W 5-5

10 Furnitures Construction Drawings & MTO Contactor's Form & RFI W W Nil

Note :
1. Contractor shall attach "Inspection Reports" of ITP along-with RFI.
2. PMC to complete the "Inspection Checklist" attached with RFI.
3. PMC is to ensure that all inspection record is complete and has been placed in MC / PA / Dossiers.
Inspection Checklist
Brick Masonry
Document # : Checklist-5-1
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg # : Location :
Reference:

Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)

DWG # : ………………………………………………………..
Availability of AFC DWGs:
1 Are AFC Drawings available at site?

Brick Test Reports: □Yes □No


2 Are Brick samples are sent to laboratory for test , and test report is
available at site. Results_________________________

Unloading of Bricks: □Yes □No


3 Ensure that unloading of bricks shall take place by hand to avoid
damages. Results_________________________

Mortar Mix Proportion: □Yes □No


4 Check the mortar mix proportion to ensure the proper ratio is
taking care during the mixing by mixer machine. Remarks_________________________

Soaking of Bricks & Blocks: □Yes □No


5 Ensure brick/block is fully wetted and cleaned prior to the masonry
work.

Brick-Concrete Colum Intersection: □Yes □No


6 Ensure tie rebar or anchor between brick wall and column is
installed as per the drawings. Remarks_________________________

□Yes □No
Plumbness of Wall:
7 Ensure the Plumbness / Verticality of wall?
Remarks_________________________

Lintel's & Canopies: □Yes □No


8 Ensure lintels and canopies are constructed correctly if required by
the drawings. Remarks_________________________
□Yes □No
Openings:
9 Check sizes for openings of doors , windows and other services.
Remarks_________________________

Curing:
All constructed masonry work to be cured for minimum three days □Yes □No
10 after construction and keep damped continuously during the curing
period.

Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements (Specifications,
Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other activities can be added
to the checklist.

CONTRACTOR PMC

Name
Date

Signature
Inspection Checklist
Cement Plastering
Document # :Checklist-5-2
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg #: Location:
Reference :

Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)

DWG # : ………………………………………………………..
Availability of AFC DWGs:
1 Are AFC Drawings available at site?

Sand : Shall be cleaned and must be of required grade.


□Yes □No
Water : Water shall be cleaned, potable and free from deleterious
2 material Remarks_________________________
Cement: Portable Cement, Type-I as peer dwg & spec.

Mortar Mix Ratio: □Yes □No


3 Mortar sand cement ratio and thickness of the plaster are as per
drawings. Remarks_________________________

Intersection of Brickwall & Column:


□Yes □No
Strip of metal lath / mesh shall be fixed on wall joints between
4 bricks and concrete elements to prevent future plaster cracking
Remarks_________________________
with overlap on each side shall be at least 100mm.

Corner Beads: □Yes □No


5 Corner Beads (Wherever Applicable),Where detailed and where
required shall be placed & fixed Remarks_________________________

Surface Roughness : □Yes □No


6 Roughing the surface by cement rendering after fixing the metal
accessories to give grip for plastering Remarks_________________________
Finishing:
Ensure plumb, rounding / chamfer of corners and evenness of □Yes □No
7 surface are finished according to drawings and thickness of
plastering is as per drawings

Curing: □Yes □No


8 Curing of plastered surfaces is done on time for minimum 3 days.

Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements (Specifications,
Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other activities can be added
to the checklist.

CONTRACTOR PMC

Name
Date

Signature
Inspection Checklist
Doors, Windows
Document # : Checklist-5-3
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg # / Line # : Location/Joint # :
Reference:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)

DWG # : ………………………………………………………..
Availability of AFC DWG:
1 Are AFC Drawings available at site?

Material Inspection: □Yes □No


2 All the materials to be used for construction are as per specifications and
drawings and approved by owner/PMC Remarks_________________________

Metal Frame installation: □Yes □No


3 The metal frames shall be checked agains damages before built into walls
and are installed true to correct plumb/ level. Remarks_________________________

Correct Wall Thickness: □Yes □No


4 Thickness/ gauge and type of doors and window are checked
Remarks_________________________

Glass & Fly Scree: □Yes □No


5 Thickness and type of glazing ( double glass ) is checked and approved fly
screens are installed Remarks_________________________

□Yes □No
Check Door Locks , Latches, Handles , Hinges, Weather Stripping and Door
6 Stoppers shall require approval .
Remarks_________________________

□Yes □No
All opening sections to doors and windows are fitted with approved
7 weather seals and checked for water/ air tightness.
Remarks_________________________

Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements (Specifications,
Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other activities can be added
to the checklist.

CONTRACTOR PMC
Name
Date
Signature
Inspection Checklist
Roof Water Proofing
Document # : Checklist-5-4
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg # / Line # : Location/Joint # :
Reference:

Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)

Availability of AFC DWG: DWG # : ………………………………………………………..


1 Are AFC Drawings available at site?

Material Inspection: □Yes □No


2 All the materials to be used for construction are as per
specifications and drawings and approved by owner/PMC Remarks_________________________

Slope & Thickness of Screed:


□Yes □No
Ensure concrete screed layer is completed in according to the
3 drawings, and the slope not less than 2%. The screed thickness Remarks_________________________
shall not be less than 30 mm .

Bitumen Coat: □Yes □No


5 Ensure two layers of bitumen coats as per drawings is applied over
the roof screed. Remarks_________________________

Insulating Board:
□Yes □No
Ensure the polystyrene thermal insulation boards are proper make
6 and are installed as per drawings and manufacturer's Remarks_________________________
recommendations.

Mortar Mix: □Yes □No


7 Ensure cement and sand mortar levelling course rate (1:3) as per
drawing is min. 20mm thickness. Remarks_________________________

EPDM Water Proof Membrane:


Ensure the high polymer modified bituminous water proof member □Yes □No
8 (EPDM) with minimum thickness 3- 4 mm , are installed as per
drawings and manufacturer's recommendations and checked for Remarks_________________________
hollowness, bubbles etc..
Screed to Protect Membrane: □Yes □No
9 Protection layer is spread over the EPDM water proof member and
is ensured that it penetrates and seals the surface properly. Remarks_________________________

□Yes □No
Flood Test:
10 The roof structure is flood tested and leaking & slope areas are
Remarks_________________________
correctly repaired.

Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements (Specifications,
Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other activities can be added
to the checklist.

CONTRACTOR PMC

Name
Date

Signature
Inspection Checklist
Painting and Decoration
Document # : Checklist-5-5
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg # : Location :
Reference:

Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)

Material Inspection - Paint


All the painting material are according to specifications and drawings
DWG # : ………………………………………………………..
and approved by owner/PMC. Ensure all materials are stored as
1 owner approved manufacturers recommendations and all damaged
Spec # : ………………………………………………………..
or out of specification materials are quarantined as per PCH
Procedure # HFY-FC-PM-PD-0033

Material Inspection - Tiles: DWG # : ………………………………………………………..


2 All the tiles materials are according to specifications, drawings , and
tiles samples already approved by owner/PMC. Spec # : ………………………………………………………..

DWG # : ………………………………………………………..
Availability of AFC DWGs:
3 Are AFC Drawings is available at site?
Spec # : ………………………………………………………..

□Yes □No
Approval of procedure:
4 Tiles installation procedure is already approved by owner/PMC.
Remarks_________________________

Color Coding: □Yes □No


5 Ensure that the owner color coding specifications is followed by
contractor and PMC approved the type of painting. Remarks_________________________

□Yes □No
No of Coats:
6 Check and confirm the required numbers of paint coats applied.
Remarks_________________________

Surface Preparation & Protection of surroundings: □Yes □No


7 Ensure all surfaces to receive decorative finishes are prepared
correctly and all surrounding non decorative areas are protected. Remarks_________________________
Mortar Mix Ratio: □Yes □No
8 Mortar sand cement ratio and thickness of the mortar bed are as
per drawings. Remarks_________________________

□Yes □No
Tile Pattern:
9 Check and confirm the Pattern of tiles is OK for laying
Remarks_________________________

□Yes □No
Hollow Sound Test:
10 Hollow Sound Test shall be carried during inspection of tiles works
Remarks_________________________

False Ceiling & Hanger Rods Approval: □Yes □No


11 Check the type of false ceiling , hanger rods are as per approved
drawing Remarks_________________________

Owner Inspection at Final Stage: □Yes □No


12 Ensure that a final owner/PMC inspection of decorative finishing is
carried out. Remarks_________________________

Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements (Specifications,
Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other activities can be added
to the checklist.

CONTRACTOR PMC

Name
Date

Signature
Inspection Checklist
Plumbing, Drainage, Sanitary
& Concealed Work
Document # : Checklist-5-6
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Date:
Dwg # : Location :
Reference :

Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
Material Inspection
1 Ensure that the matrial and fittings for plumbing, drainage and □OK □Not OK
sanitary work has been approved.
Availability of AFC DWGs:
2 Are AFC Drawings is available at site? DWG # : ………………………………………………………..

Installation of Plumbing, Drainage & Sanitry System:


3 Ensure the installation of installation of plumbing, drainage and □OK □Not OK
sanitry fixing is as per drawing
Water Filling / Leak Test:
4 Ensure that Water Filling / Leak Test has been carried out for □OK □Not OK
plumbing, drainage and sanitry prior bury or conceal.
Conceal Work:
Ensure the following has been checked by discipline engineers prior
to conceal:
1. Pressure Test of Water Supply System.
5 2. Pressure Test of Fire Protection Water System.
□OK □Not OK

3. Installation of Fire Detectors


4. Electrical conduits, earthing & other fittings.
5. hanger rods
Sealing of Wall Penetrations
6 Ensure that all gaps of wall penetrations ( HVAC Duct, Sleeve for pipe □OK □Not OK
or conduits) have been filled with fire retardant material.
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements (Specifications,
Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other activities can be added
to the checklist.

CONTRACTOR PMC
Name
Date
Signature

You might also like