Professional Documents
Culture Documents
ITD-GEN-000-CIV-CHK-0005 - 0 - Building Civil ITPs
ITD-GEN-000-CIV-CHK-0005 - 0 - Building Civil ITPs
"W" - WITNESS POINT - Work shall be witnessed for the inspection stage. Contractor shall notify the
COMPANY / PMC and raise RFI.
"S" - SURVEILLANCE - Surveillance can be carried out for on-going activity but formal notification and RFI is
not required.
"R" - REVIEW - Document shall submitted for review and approval through transmittal. Work shall not be
proceeded unless contractor has received Code-A / Code-B from PMC / COMPANY.
"RFI" - REQUEST FOR INSPECTION - Contractor shall submit the FRI along-with their inspection
notification.
SCOPE OF WORK
Contractor shall "briefly" specify their Scope of Work:
ITP - INSPECTION & TEST PLAN
Building Construction - Civil
Document No : ITD-GEN-000-CIV-CHK-0005; Rev-0
Verifying Document
Reference Document Chcecklist
No. Activity (Inspection Report & Contractor PMC
Acceptance Criteria Reference
Checklist)
5 Doors & Windows Construction Drawings Contactor's Form & RFI W W 5-3
6 Plumbing, Drainage & Sanitry Fixing Construction Drawings Contactor's Form & RFI W W 5-6
10 Furnitures Construction Drawings & MTO Contactor's Form & RFI W W Nil
Note :
1. Contractor shall attach "Inspection Reports" of ITP along-with RFI.
2. PMC to complete the "Inspection Checklist" attached with RFI.
3. PMC is to ensure that all inspection record is complete and has been placed in MC / PA / Dossiers.
Inspection Checklist
Brick Masonry
Document # : Checklist-5-1
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg # : Location :
Reference:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
DWG # : ………………………………………………………..
Availability of AFC DWGs:
1 Are AFC Drawings available at site?
□Yes □No
Plumbness of Wall:
7 Ensure the Plumbness / Verticality of wall?
Remarks_________________________
Curing:
All constructed masonry work to be cured for minimum three days □Yes □No
10 after construction and keep damped continuously during the curing
period.
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements (Specifications,
Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other activities can be added
to the checklist.
CONTRACTOR PMC
Name
Date
Signature
Inspection Checklist
Cement Plastering
Document # :Checklist-5-2
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg #: Location:
Reference :
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
DWG # : ………………………………………………………..
Availability of AFC DWGs:
1 Are AFC Drawings available at site?
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements (Specifications,
Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other activities can be added
to the checklist.
CONTRACTOR PMC
Name
Date
Signature
Inspection Checklist
Doors, Windows
Document # : Checklist-5-3
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg # / Line # : Location/Joint # :
Reference:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
DWG # : ………………………………………………………..
Availability of AFC DWG:
1 Are AFC Drawings available at site?
□Yes □No
Check Door Locks , Latches, Handles , Hinges, Weather Stripping and Door
6 Stoppers shall require approval .
Remarks_________________________
□Yes □No
All opening sections to doors and windows are fitted with approved
7 weather seals and checked for water/ air tightness.
Remarks_________________________
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements (Specifications,
Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other activities can be added
to the checklist.
CONTRACTOR PMC
Name
Date
Signature
Inspection Checklist
Roof Water Proofing
Document # : Checklist-5-4
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg # / Line # : Location/Joint # :
Reference:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
Insulating Board:
□Yes □No
Ensure the polystyrene thermal insulation boards are proper make
6 and are installed as per drawings and manufacturer's Remarks_________________________
recommendations.
□Yes □No
Flood Test:
10 The roof structure is flood tested and leaking & slope areas are
Remarks_________________________
correctly repaired.
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements (Specifications,
Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other activities can be added
to the checklist.
CONTRACTOR PMC
Name
Date
Signature
Inspection Checklist
Painting and Decoration
Document # : Checklist-5-5
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg # : Location :
Reference:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
DWG # : ………………………………………………………..
Availability of AFC DWGs:
3 Are AFC Drawings is available at site?
Spec # : ………………………………………………………..
□Yes □No
Approval of procedure:
4 Tiles installation procedure is already approved by owner/PMC.
Remarks_________________________
□Yes □No
No of Coats:
6 Check and confirm the required numbers of paint coats applied.
Remarks_________________________
□Yes □No
Tile Pattern:
9 Check and confirm the Pattern of tiles is OK for laying
Remarks_________________________
□Yes □No
Hollow Sound Test:
10 Hollow Sound Test shall be carried during inspection of tiles works
Remarks_________________________
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements (Specifications,
Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other activities can be added
to the checklist.
CONTRACTOR PMC
Name
Date
Signature
Inspection Checklist
Plumbing, Drainage, Sanitary
& Concealed Work
Document # : Checklist-5-6
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Date:
Dwg # : Location :
Reference :
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
Material Inspection
1 Ensure that the matrial and fittings for plumbing, drainage and □OK □Not OK
sanitary work has been approved.
Availability of AFC DWGs:
2 Are AFC Drawings is available at site? DWG # : ………………………………………………………..
CONTRACTOR PMC
Name
Date
Signature