DAILY REPORT

FEBRUARY 9, 2021
TABLE OF CONTENTS
Actual Activity Schedule for the day.............................................................................................2
Equipment on site...........................................................................................................................3
The weather.....................................................................................................................................5
Labor on site....................................................................................................................................5
Material brought to the site...........................................................................................................6
Construction Progress Summary..................................................................................................6
Safety................................................................................................................................................6
Quality..............................................................................................................................................6
Any issue arising/ Concerns...........................................................................................................6
annex: photos..................................................................................................................................7

1|Page
Daily Report

Project FOAM FIREFIGHTING SYSTEM


Location NSPP
Date February 9, 2021

Actual Activity Schedule for the day


Activity Worker 8:00-10:00 10:3- 1400-
1300 1730
Orientation/induction 1. ALEX GITHINJI

2. ROBERT MBUGUA

3. FELIX ODHIAMBO
4. EMMANUEL OTHIAMBO

5. CALVIN OOKO
6. SAMUEL KIUMA
7. JUMAA NYANJE

8. JOHN MACHARIA

Offloading scaffolds and other 1. ALEX GITHINJI


tools and equipment from the
truck and the container. 2. ROBERT MBUGUA

3. FELIX ODHIAMBO

4. EMMANUEL OTHIAMBO
5. CALVIN OOKO

6. SAMUEL KIUMA

7. JUMAA NYANJE

8. JOHN MACHARIA

2|Page
Equipment on site
Equipment and tools Type quantity/ Function/use
on site
1. Dumpy Level  12’’ (300mm) 1pcs Establish or check points in
the same horizontal plane.
 24’’(600mm) 1ps Establish or check points in
the same horizontal plane.
2. Hilti Drill head  TE-C chuck 1pcs To be used together with the
drill head
3. Drill Machine  Makita Making round holes or
driving fasteners.
4. Lase
5. Spanners  Ring spanner set 1 set Used to provide grip and
tighten or loosen fasteners.

 Combination set 1 set Used to provide grip and


tighten or loosen fasteners.

6. Allen keys  Long 9pcs 1.5mm- 1pcs Driving bolts and screws with
10mm a hexagonal socket.
7. measuring tapes  8m tylon Stanley 2pcs Measure size or distance.

 3m tylon Stanley 1pc Measure size or distance.

8. cutting disks  9’’ 12pcs Cutting metal and pipes

 4.5’’ 12pcs Cutting metal and pipes

9. Metal girding disk  9’’ 6pcs Grinding, cutting, cleaning

3|Page
and polishing surfaces
 4.5’’ 5pcs Grinding, cutting, cleaning
and polishing surfaces
10. Hacksaws  Frame adjustable 1pc cutting metal, and other
chrome various materials
•Framed fixed: replaced 1pc cutting metal, and other
with 1pc of anchor bolts various materials
11. Testers  100-500V Stanley 1pcs Determine the presence of
178mm electricity in a piece of
equipment under test.
12. Welding shield  Head mounted 1pc s Prevent arc eye, a painful
condition where the cornea is
inflamed.
13. File  Half round 2ND cut 1pcs Used for sharpening the hack
kingtony 10’ saws
14. Try square  Zinc Handel 1pcs marking and checking 90°
10’’(250mm Stanley)
15. Anchor bolts M16 by 182 9pcs connect structural and non-
structural elements to
concrete
16. Drill bit  8mm by 75mm by 2pcs remove fasteners to create
117mm holes

 10mm by 87mm by 2pcs remove fasteners to create


133mm holes

 12mm by 101mm by 2pcs remove fasteners to create


115mm holes

4|Page
• 5mm by 57mm by 2pcs remove fasteners to create
86mm holes
17. Chalk line and blue  Winder set 30m 1 set Used for measurement
power winder set Stanley purposes
30m

The weather
Was cold in the morning and hot the rest of the day.

Labor on site
The labor on site included the following workers:
No. Name Trade

1. ALEX GITHINJI Supervisor


2. Mechanical fitter
ROBERT MBUGUA
3. FELIX ODHIAMBO Helpers
4. EMMANUEL OTHIAMBO Helpers
5. CALVIN OOKO Helpers
6. SAMUEL KIUNA Mechanical fitter
7. kUMAA NYANJE Scaffolder
8. JOHN MACHARIA Helpers

Material brought to the site


Materials on site included the following:
 20ft container
 Pipe wrenches
 Measuring tapes

Construction Progress Summary


Neither of the works begun this on this day. Basically what was carried was offloading

Safety
• There were no recorded incidences.

5|Page
Quality
No quality issues arose.

Any issue arising/ Concerns.


A safety officer was need on site the following day as it was beginning of the works.

Annex: photos
9th February, 2021 offloading scaffolds from the container

6|Page
Report was prepared by:

Name Date

And approved by

Name Date