Professional Documents
Culture Documents
Hamzah, Kho, Wang Late Payments and Non Payment Fast Developing Economy
Hamzah, Kho, Wang Late Payments and Non Payment Fast Developing Economy
Abstract: Late payment and nonpayment is explicitly recognized as a widespread problem in the construction sector and recurs in project
after project. Although the Construction Industry Payment and Adjudication Act was enacted in 2012 by the Parliament of Malaysia to ease
Downloaded from ascelibrary.org by Univ Of The West Indies on 09/17/19. Copyright ASCE. For personal use only; all rights reserved.
timely and regular payment, it does not apply to a construction contract entered into by a natural person for any construction work involving a
building which is less than four stories high and which is wholly intended for his or her occupation. Further, the majority of resident buildings
in Malaysia are mostly low-rise buildings that are less than four stories high. Also, CIPA Act 2012 does not address the underlying causes of
late payment. This study aims to identify the underlying causes of late payment in the construction sector in a fast-developing economy—
Malaysia—and to develop effective solutions to mitigate this kind of risk. A structured questionnaire survey was conducted for contractors
registered as Grade 3 to Grade 7 under Malaysian Construction Industry Development Board (CIDB). A sample of 1,000 contractors was
selected, approximately 5.3% of the population. Findings reveal that the “cash flow problems due to deficiencies in client’s management
capacity” is the most significant underlying cause for late payment. In mitigation of late payment risks, “investigating the owner’s ability to
pay” was analyzed as the most effective solution. Indicators for late payment and nonpayment identified in this study enable contractors to
forecast payment risks in both the current project and future projects. DOI: 10.1061/(ASCE)EI.1943-5541.0000189. © 2013 American
Society of Civil Engineers.
Author keywords: Nonpayment risk; Late payment; Fast-developing economy; Contracting firms; Payment capacity; Cash flow risks.
Introduction According to Davis (1999), the motto for strategic cash flow is
to “collect early and pay late.” This has created a dilemma in which
When the flow of money into a project is delayed, the net cash flow delay in payment is a two-edged sword. It is common for clients to
becomes negative (Paul et al. 2012; Ranyard and McHugh 2012; withhold the money as long as possible, whereas contractors want
Kaka and Price 1991). In a construction project, payments are their money as soon as possible. Consequently, late payment is a
needed to pay for materials, labor, subcontractors’ account ren- predicament which is difficult to deal with in view of the different
dered, and preliminary and general overheads expended during interests and perceptions of the parties involved (Lou and Wang
the progress of the work. Some practitioners may regard late pay- 2013). Owners who presumably wish to protect their own reputa-
ment as acceptable, and perceptions of this kind merely exacerbate tions seem to give biased responses when asked whether clients
a problem that is already difficult to handle (Massoud et al. 2011). pay the prime contractors on time. Subcontractors and general con-
Because late payment can affect a company’s cash flow to the ex- tractors agree that payment is not made on time nearly as often as
tent of leading to insolvency, timeliness of payment is important is claimed (Arditi and Chotibhongs 2005). This research aims to
(Yang and Chang 2013). Once a payment problem starts to develop, identify the underlying causes of late payment from the contactors’
it typically gets worse over time and shifts financial burdens from perspective in the expectation to develop appropriate corrective
one participant to another while creating cash flow problems actions.
(Scholnick et al. 2013). Clients have become more demanding,
more discerning, and less willing to accept risk (Lee et al.
2012). It is a normal practice for some clients to shift some risks Cash Flow in Construction Projects
to other parties further down the chain by delaying payments and
thus reducing their financing costs. In this way, the financial burden Late payment is closely connected to cash flow and is a matter of
is transferred to contractors who may not have sufficient capital great concern in the construction industry, perhaps more so than in
assets or available credit to cover delays (Chung 2013). other less labor-intensive industries (Yang and Chang 2013). Work-
ers have to be paid whether the contractor has been paid or not. Too
1 often, people concentrate on making a profit and overlook the ef-
Vice-Chancellor’s Office, International Univ. of Malaya-Wales,
Kuala Lumpur 50480, Malaysia. fects on their cash flow of delayed payment. If the profit is tied up
2
Faculty of Built Environment, Univ. of Malaya, Kuala Lumpur 50603, in debts or work in progress and there is not enough left over to pay
Malaysia. the bills, then that profit is of little use (Low and Goi 2003). Cash
3
Associate Professor, Faculty of Built Environment, Univ. of Malaya, flow in the construction industry is critical because projects tend to
Kuala Lumpur 50603, Malaysia (corresponding author). E-mail: be larger and take longer to complete than in other industries, and
derekisleon@gmail.com
progress payments also tend to be large. Any delays in the project
Note. This manuscript was submitted on June 24, 2013; approved on
October 17, 2013; published online on December 2, 2013. Discussion per- or cash flow can have a major impact, and cash flow problems are
iod open until May 2, 2014; separate discussions must be submitted for largely responsible for the high level of insolvency in the construc-
individual papers. This paper is part of the Journal of Professional Issues tion industry. Because construction projects are extremely complex
in Engineering Education & Practice, © ASCE, ISSN 1052-3928/ and usually governed by highly detailed contracts, the payment
04013013(9)/$25.00. process is one of the most sensitive areas for all parties. It is
n=N ¼ 1000=ð10533 þ 3009 þ 1052 þ 4123Þ respondents are involved in both public and private projects
(Table 4). Respondents cover both public and private sectors, which
¼ 1000=18717 ¼ 0.053 ð1Þ
helps to reduce bias on the relative prevalence of late payment in
government or private projects.
where n = size of the sample; and N = size of the population. The seriousness of late payment in public and private projects
From a total of 1,000 questionnaires, the response rate was 10.2%, were ranked using a Likert scale rating from 1 to 4 (least significant
which was close to the 10.8% reported by Adams (2008) in a study to most significant). Table 5 shows that late payment was a more
on payment risk. significant problem in the private sector (Mean ¼ 2.89) than in the
government sector (Mean ¼ 2.50). The difference in the serious-
ness of late payment between public and private projects affects
Results of Analysis and Discussion the size of the mark up and contractors’ bidding behavior.
Subsequently, the acceptability of late payment, shown in
Nonparametric testing was conducted because it does not require Table 6, indicates that 80% of respondents were able to accept
any assumptions about the shape of the underlying population payment delay by only a few days, i.e., less than five work-
distribution. Table 3 contains demographic information on the
ing days.
respondents according to current job position, years of experience,
There are significant differences in the frequency of perspectives
and the company’s information. The study features a high degree
towards the acceptable duration of late payment. The homogeneity
of reliability because the majority of respondents were CEOs,
of variance assumptions has been violated (p < 0.05), which re-
managers, and directors. The range of main business activity indi-
flects Coakes and Steed’s (2003) results. The acceptable lateness
cated that the findings cover a wide variety of contractors in the
ranged from 3 to 45 days, and the most serious delay was one year.
Malaysian construction industry. A majority (54.9%) of the
As shown in Table 7, most of the respondents (58.8%) did not
explicitly allow for the risk of late payment when bidding for a
Table 3. Frequency Distribution of Respondents’ Profile project. However, a clear majority (75.5%) quote different prices
Demographic for clients who pay late and those who pay promptly. Contractors
categories Category breakdown Frequency Percent have, in practice, traditionally used high markups to cover risk,
but this approach is no longer effective when their margins are
Job position CEOs, managers, directors, 61 59.8
and other managerial posts
squeezed, which is in line with the findings from Baloi and Price
Senior executive 14 13.7 (2003). A bid price must consider the financial position of the cus-
Executive 24 23.5 tomer or client, including cash flow needs. There is a significant
Administration officer 2 2.0 difference between the frequency of perspectives towards the incor-
Others 1 1.0 poration of late payment risk and the pricing of a project with the
Years of 1–5 45 44.1 client who tends to pay late (p < 0.05), which suggests that re-
experience 6–10 17 16.7 spondents were not aware that they had actually allowed for late
11–15 21 20.6
16–20 5 4.9
>20 14 13.7 Table 4. Government and Private Projects under Survey
Company’s main Prime contractor 72 70.6
Valid Cumulative
business
Project funding Frequency Percent percent percent
Activity Subcontractor
Building works 39 38.2 Government funded project 16 15.7 15.7 15.7
Civil and structural works 33 32.4 Private funded project 30 29.4 29.4 45.1
Mechanical and electrical works 13 12.7 Both government and 56 54.9 54.9 100.0
Infrastructure works 22 21.6 private project
Architectural works 13 12.7 Total 102 100.0 100.0
payment when bidding for a project but had unconsciously priced mitigation of late payment problems is “understanding and re-
according to the client’s promptness in payment. The respondents searching the owner’s ability to pay” (mean ¼ 3.89), followed
generally have a poor understanding on the incorporation of late by “to solve late payment by implementing the Construction Indus-
payment risk when bidding for a project. This confirms the findings try Payment and Adjudication Act” (mean ¼ 3.69). The third to
of Thevendran and Mawdesley (2004), in which only 17% of re- fifth were “negotiating payment terms with the client to facilitate
Downloaded from ascelibrary.org by Univ Of The West Indies on 09/17/19. Copyright ASCE. For personal use only; all rights reserved.
spondents had experience in risk management. Wong and Hui a healthy cash flow” (mean ¼ 3.68), “to obtain the payment due
(2006) support the finding that the contractors may inflate the ten- before handing over the project to the client” (mean ¼ 3.67),
der price if the clients have a record of late payment. Smith and and “the importance of understanding and studying the payment
Bohn (1999) also found that markups are affected by the adequacy requirement of each individual project” (mean ¼ 3.66).
of the clients’ project financing and their ability to pay on time.
© ASCE
Standard
Main causes Subcauses 1 2 3 4 5 Mean deviation Rank
Client’s poor financial Deficiencies in client’s management capacity 3 (2.9%) 10 (9.8%) 17 (16.7%) 36 (35.3%) 35 (34.3%) 3.96 1.091 1
management Client’s ineffective utilization of funds (http:// 4 (3.9%) 10 (9.8%) 28 (27.5%) 29 (28.4%) 30 (29.4%) 3.88 1.122 2
www.financialmanagement.org)
Lack of proper process implementation 1 (1.0%) 15 (14.7%) 27 (26.5%) 34 (33.3%) 24 (23.5%) 3.66 1.089 5
Overlook the ripple effect of economic downturn 7 (6.9%) 9 (8.8%) 44 (43.1%) 23 (22.5%) 13 (12.7%) 3.31 1.084 22
Scarcity of capital to finance the project (Meng 8 (7.8%) 6 (5.9%) 19 (18.6%) 39 (38.2%) 28 (27.5%) 3.81 1.190 3
2002)
Financial failure due to bankruptcy (Xenidis and 15 (14.7%) 16 (15.7%) 15 (14.7%) 20 (19.6%) 34 (33.3%) 3.55 1.444 10
Angelides 2005; Low and Goi 2003)
Insufficient financial Clients failure to generate income from bank 2 (2.0%) 9 (8.8%) 25 (24.5%) 39 (38.2%) 24 (23.5%) 3.72 0.986 4
resources when sales do not hit the targeted amounta
Clients underestimate the time period and the cash 4 (3.9%) 11 (10.8%) 29 (28.4%) 42 (41.2%) 12 (11.8%) 3.50 0.925 13
flow from the investment (Lip 2006)
Clients inaccurate forecasting of market demand 3 (2.9%) 15 (14.7%) 35 (34.3%) 29 (28.4%) 16 (15.7%) 3.42 1.034 17
when preselling property (Zou et al. 2007)
Shortage allocation of fund from sources of 2 (2.0%) 7 (6.9%) 40 (39.2%) 29 (28.4%) 20 (19.6%) 3.57 0.966 9
funding when contract sum increased due to
variation orders
Clients loan from bank not in place to pay the 3 (2.9%) 15 (14.7%) 26 (25.5%) 34 (33.3%) 19 (18.6%) 3.57 1.136 9
contractorsa
Banks refuse to provide credit facilities to small 5 (4.9%) 16 (15.7%) 25 (24.5%) 33 (32.4%) 19 (18.6%) 3.43 1.171 16
construction company
Paymaster’s withholding Clients deliberate delay for their own financial 1 (1.0%) 13 (12.7%) 33 (32.4%) 32 (31.4%) 19 (18.6%) 3.61 1.018 7
04013013-5
of payment advantage
Delay in releasing of the retention monies to 0 (0%) 10 (9.8%) 35 (34.3%) 32 (31.4%) 20 (19.6%) 3.66 0.940 5
contractor (Park et al. 2005; Low and Goi 2003)
Wilful withholding of payment for personal 7 (6.9%) 29 (28.4%) 24 (23.5%) 19 (18.6%) 18 (17.6%) 3.11 1.245 25
reasonsa
Conflict and poor Client’s lack of trust with the consultants in 9 (8.8%) 29 (28.4%) 25 (24.5%) 24 (23.5%) 10 (9.8%) 3.05 1.133 27
communication among certification of contractors progress claim and
parties involved variation ordersa
Table 8. (Continued.)
Significance of late payment (1 = least significant to 5 = most significant)
© ASCE
Standard
Main causes Subcauses 1 2 3 4 5 Mean deviation Rank
Financial market instability Increment of interest rate in repayment of loan 11 (10.8%) 21 (20.6%) 37 (36.3%) 25 (24.5%) 3 (2.9%) 2.95 1.045 30
(Baloi and Price 2003)
Increment of foreign exchange rate (Kapila and 15 (14.7%) 27 (26.5%) 31 (30.4%) 18 (17.6%) 5 (4.9%) 2.72 1.188 32
Hendrickson 2001)
Inflation (Xenidis and Angelides 2005; Hwee and 6 (5.9%) 18 (17.6%) 19 (18.6%) 33 (32.4%) 22 (21.6%) 3.59 1.249 8
Tiong 2002; Kaming et al. 1997)
Delay in certification/poor Delay in evaluation and certification of interim 1 (1.0%) 13 (12.7%) 26 (25.5%) 37 (36.3%) 21 (20.6%) 3.66 1.011 5
documentation and final payment (Abdul Kadir et al. 2005)
Late in consultant’s site staff attending to 4 (3.9%) 13 (12.7%) 41 (40.2%) 28 (27.5%) 14 (13.7%) 3.32 1.061 20
inspection work (Abdul Kadir et al. 2005)
Involvement of too many parties in the process of 4 (3.9%) 12 (11.8%) 32 (31.4%) 35 (34.3%) 17 (16.7%) 3.53 0.940 11
honoring interim certificatea
Bureaucracy or inefficient procedures of payment 4 (3.9%) 13 (12.7%) 29 (28.4%) 27 (26.5%) 25 (24.5%) 3.51 1.088 12
process
Consultant’s quantity Underpaid claims (Hwee and Tiong 2002) 4 (3.9%) 13 (12.7%) 36 (35.3%) 30 (29.4%) 15 (14.7%) 3.39 1.057 19
surveyor Consultant’s quantity surveyor not a quality 9 (8.8%) 20 (19.6%) 30 (29.4%) 29 (28.4%) 10 (9.8%) 3.01 1.092 29
management system company (Odeh and
Battaineh 2002)
Contractor’s default Slow processing and delay in finalizing of 3 (2.9%) 10 (9.8%) 36 (35.3%) 29 (28.4%) 22 (21.6%) 3.64 1.041 6
variations and final accounts (Lip 2006)
Contractor’s capital lock-up (Palmer et al. 1999) 3 (2.9%) 19 (18.6%) 34 (33.3%) 31 (30.4%) 13 (12.7%) 3.45 1.075 15
Contractor’s do not research paymaster ability to 3 (2.9%) 17 (16.7%) 34 (33.3%) 34 (33.3%) 12 (11.8%) 3.41 1.019 18
pay when tender for a projecta
04013013-6
Contractors submit incomplete payment claims 11 (10.8%) 18 (17.6%) 31 (30.4%) 28 (27.5%) 12 (11.8%) 3.11 1.277 25
(Lip 2006)
Contractors delay in submitting claimsa 20 (19.6%) 19 (18.6%) 28 (27.5%) 26 (25.5%) 7 (6.9%) 2.81 1.341 31
Contractors do not incorporate financial charges 9 (8.8%) 22 (21.6%) 36 (35.3%) 21 (20.6%) 11 (10.8%) 3.08 1.202 26
when bidding for project with poor payment
recorda
Financial blunder the contractor underpriced the 2 (2.0%) 23 (22.5%) 35 (34.3%) 28 (27.5%) 12 (11.8%) 3.30 1.082 23
project costs during tender (Yiu and Tam 2006;
Implementation of financial management 4 (3.9%) 9 (7.8%) 23 (22.5%) 41 (40.2%) 21 (20.6%) 3.65 1.083 6
to ease cash flow problems (Hyung et al.
2005)
Requires the owner to provide the owner’s 8 (7.8%) 9 (8.8%) 33 (32.4%) 14 (13.7%) 34 (33.3%) 3.63 1.262 7
payment guarantee or bonda
The authority should list down the late 5 (4.9%) 18 (17.6%) 22 (21.6%) 23 (22.5%) 30 (29.4%) 3.59 1.247 8
payers in the industrya
Provide the contractor rights to either 4 (3.9%) 18 (17.6%) 25 (24.5%) 26 (25.5%) 25 (24.5%) 3.57 1.163 9
suspend work or reduce the rate of work
(Scheffler 2003)
Clients to bond with the capital market to 2 (2.0%) 7 (6.9%) 41 (40.2%) 32 (31.4%) 17 (16.7%) 3.55 0.946 10
get credit to fund the projecta
Train and educate all parties on the effects 7 (6.9%) 6 (5.9%) 29 (28.4%) 39 (38.2%) 17 (16.7%) 3.53 1.072 11
of payments on the project progress
Contractors are encouraged to complain to 6 (5.9%) 16 (15.7%) 29 (28.4%) 19 (18.6%) 28 (27.5%) 3.52 1.203 12
Biro Aduan Negara (BAN) and assured
them that this will not affect them in
securing future worksa
Contractors should submit timely accurate 4 (3.9%) 14 (13.7%) 28 (27.5%) 30 (29.4%) 23 (22.5%) 3.49 1.093 12
invoices with complete documents (Tarek
2006)
The finance and accounting team reviews 3 (2.9%) 11 (10.8%) 30 (29.4%) 40 (39.2%) 14 (13.7%) 3.49 0.922 12
what is required for timely project billing
and prompt payment
Impose interest penalties on late payers 9 (8.8%) 20 (19.6%) 18 (17.6%) 26 (25.5%) 25 (24.5%) 3.45 1.277 13
(Meng 2002; Scheffler 2003)
Mutual discussions of problems with 3 (2.9%) 15 (14.7%) 32 (31.4%) 35 (34.3%) 14 (13.7%) 3.45 0.982 13
employer to address the problems in a
timely manner (Tarek 2006)
Contractor’s entitlement to establish legal 9 (8.8%) 12 (11.8%) 38 (37.3%) 17 (16.7%) 22 (21.6%) 3.39 1.208 14
lien in Malaysia (Meng 2002)
Apply term loan from bank to cover the 9 (8.8%) 15 (14.7%) 32 (31.4%) 22 (21.6%) 19 (18.6%) 3.32 1.209 15
consequences of late paymenta
Contractors should chase payments due 8 (7.8%) 15 (14.7%) 36 (35.3%) 28 (27.5%) 12 (11.8%) 3.26 1.088 16
relentlesslya
Sign another supplementary agreement 11 (10.8%) 21 (20.6%) 37 (36.3%) 21 (20.6%) 9 (8.8%) 3.05 1.134 17
with the employer to reduce the rate of
work due to insufficient budget from
sources of fundinga
Reschedule work to help client ease their 11 (10.8%) 18 (17.6%) 34 (33.3%) 27 (26.5%) 9 (8.8%) 3.03 1.139 18
cash flowa
Contractors should mark up the tender 19 (18.6%) 9 (8.3%) 38 (37.3%) 23 (22.5%) 10 (9.8%) 2.98 1.203 19
price for a project with bad payment record
(Arditi Chotibhongs 2005)
Note: Friedman test: chi-square = 100.570; p < 0.001.
a
Indicated possible solutions obtained from pilot questionnaire survey.
are less than four stories high. According to Omar et al. (2012), the of new houses available in the market. In a study conducted
Malaysian contemporary terraced house has been around for more by Chong et al. (2011), most respondents prefer to buy property
than 40 years. It is widely built by private developers and is cur- (77.1%) instead of an apartment or condominium although the
rently the most preferred form of property in the country price of apartment is much cheaper than property.
because of its affordability. In the second quarter of 2008 alone, Therefore, this research is vital to fill this gap, as the targeted
Malaysia had seen terraced housing dominate the overall supply contracting firms for this research were registered contractors that