BS 07533-3-1997

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 21

British Standard

A single copy of this British Standard is licensed to


Akin Koksal
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

10 December 2002

This is an uncontrolled copy. Ensure use of the most


current version of this document by searching British
Standards Online at bsonline.techindex.co.uk
BRITISH STANDARD |
| BS 7533 :
|
|
|
Part 3 : 1997
|
|
|
|
|
|
|
|
|
|
|
|
|
Pavements constructed |
|
|
|
|
|
with clay, natural stone |
|
|
|
|
|
or concrete pavers |
|
|
|
|
|
|
|
|
Part 3. Code of practice for laying precast |
|
|
concrete paving blocks and clay pavers |
|
|
for flexible pavements |
|
|
|
|
|
|
|
|
|
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ICS 93.080.20 |
|
|
|
|
|
|
|
|
NO COPYING WITHOUT BSI PERMISSION EXCEPT AS PERMITTED BY COPYRIGHT LAW
|
|
|
|
BS 7533 : Part 3 : 1997

Committees responsible for this


British Standard
The preparation of this British Standard was entrusted to Technical Committee
B/507, Paving units and kerbs, upon which the following bodies were represented:

Brick Development Association


British Cement Association
British Ceramic Research Ltd.
British Precast Concrete Federation Ltd.
Cementitious Slag Makers' Association
County Surveyors' Society
Department of Transport (Highways Agency)
Institution of Civil Engineers
Institution of Highways and Transportation
Interlay, the Association of Block Paving Contractors
Interpave the Concrete Block Paving Association
Landscape Institute
Society of Chemical Industry
Stone Federation
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

The following bodies were also represented in the drafting of the standard, through
subcommittees and panels:

British Civil Engineering Test Equipment Manufacturers' Association


Institution of Structural Engineers
National Federation of Clay Industries Ltd.
National Paving and Kerb Association

This British Standard, having


been prepared under the
direction of the Sector Board for
Buiding and Civil Engineering,
was published under the
authority of the Standards Board
and comes into effect on
15 May 1997

 BSI 1997
Amendments issued since publication
Amd. No. Date Text affected

The following BSI references


relate to the work on this
standard:
Committee reference B/507
Draft for comment 95/106259 DC

ISBN 0 580 27071 8


BS 7533 : Part 3 : 1997

Contents

Page
Committees responsible Inside front cover
Foreword ii
Code of practice
1 Scope 1
2 Normative references 1
3 Definitions 1
4 Construction of pavement 1
5 Construction in inclement weather 4
6 Additional work after early trafficking 4
Annexes
A (normative) Reinstatement 5
B (normative) Tolerance of the surfacing 6
C (informative) Typical restraint details 7
D (normative) Grading and application for laying course sand 10
E (informative) Laying patterns 12
F (normative) Compactor details 14
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

Tables
B.1 Tolerance of surface levels 6
B.2 Tolerance of laying course thickness 6
B.3 Surface regularity 6
D.1 Laying course application 10
D.2 Grading for laying course sand 10
D.3 Grading for jointing sand 11
F.1 Compactor details 14
Figures
C.1 Typical restraint details 7
C.2 Detail at ironwork 8
C.3 Typical detail around drainage channels 9
E.1 Laying patterns 12
E.2 Laying patterns at edges 13
List of references Inside back cover

 BSI 1997 i
BS 7533 : Part 3 :1997

Foreword

This Part of BS 7533 has been prepared by Technical Committee B/507. It supersedes
BS 6677 : Part 3 : 1986 and BS 6717 : Part 3 : 1989, which are withdrawn.
Technical Committee B/507 intends to revise BS 7533 in the following Parts.

Part 1 Guide for the structural design of heavy duty pavements constructed of
clay pavers or precast concrete
Part 2 Guide for the structural design of lightly trafficked pavements
constructed of clay pavers or precast concrete paving blocks
Part 3 Code of practice for laying precast concrete paving blocks and clay
pavers for flexible pavements
Part 4 Code of practice for the construction of pavements of precast concrete
flags and natural stone slabs
Part 5 Guide for the design of pavements (other than structural aspects)
Part 6 Code of practice for the construction of pavements Ð Kerbs, channels
and edgings
Part 7 Code of practice for the construction of pavements of natural stone setts
Part 8 Guide for the structural design of lightly trafficked pavements
constructed of precast concrete flags or natural stone slabs

BS 7533 : 1992 will be withdrawn on the publication of Parts 1 and 2.


Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

As a code of practice, this British Standard takes the form of guidance and
recommendations. It should not be quoted as if it were a specification and particular
care should be taken to ensure that claims of compliance are not misleading.
Compliance with a British Standard does not of itself confer immunity
from legal obligations.

Summary of pages
This document comprises a front cover, an inside front cover, pages i and ii, pages 1
to 15, an inside back cover and a back cover.

ii  BSI 1997
BS 7533 : Part 3 : 1997

Code of practice

1 Scope 3.8 roadbase


This Part of BS 7533 gives recommendations for the One or more layers of material placed above the
laying of precast concrete paving blocks conforming sub-base that constitutes a structural element of a
to BS 6717 : Part 1 and for clay pavers conforming to flexible or composite pavement.
BS 6677 : Part 1 intended for flexible pavements for 3.9 sub-base
roads, industrial areas and other paved surfaces
One or more layers of material placed immediately
subjected to all categories of static and vehicular
above the subgrade.
loading and pedestrian traffic. Recommendations for
repairs and reinstatement are given in annex A. 3.10 subgrade
The principles given apply to all shapes and sizes of Part of the soil, natural or constructed, that supports
paving units covered by BS 6717 : Part 1 and the loads transmitted by the overlying pavement.
BS 6677 : Part 1, although the figures in this code of 3.11 capping layer
practice all show rectangular paving units.
Layer of granular or treated material at the top of
the subgrade to provide a working surface and an
2 Normative references improved foundation for the pavement, and to
This incorporates, by dated or undated reference, provide a wearing platform during construction.
provisions from other publications. These normative 3.12 surface course
references are made at the appropriate places in the
text and the cited publications are listed on the Layer of interlocked paving units that acts as a
wearing surface and forms part of the structure of
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

inside back cover. For dated references, only the


edition cited applies; any subsequent amendments to the pavement.
or revisions of the cited publication apply to this 3.13 inboard cuts
Part of BS 7533 only when incorporated in the Cut unit to break a bond to allow the cut at the edge
reference by amendment or revision. For undated to be greater than one quarter of a paving unit.
references, the latest edition of the cited publication
applies, together with any amendments. 3.14 laying pattern
Arrangement of paving units to form specific
3 Definitions patterns or bond either for structural requirements
or for visual effects.
For the purposes of this Part of BS 7533, the
definitions given in BS 6717 : Part 1, BS 6677 : 3.15 jointing sand
Part 1 and BS 6100 : Part 2 apply, together with the Sand applied to fill the joints between paving units.
following.
3.16 joint width
3.1 paving unit Distance between adjacent paving units or units and
Either a concrete paving block or a clay paver. restraint.
3.2 creep
Horizontal movement of units, resulting from the 4 Construction of pavement
action of braking, accelerating or cornering forces 4.1 Subgrade, sub-base and roadbase
imposed principally by vehicular traffic.
Construction of the subgrade, sub-base and
3.3 edge restraint roadbase, including compaction, should generally be
Device that serves to prevent lateral movement of in accordance with relevant current practice as
paving units and to prevent loss of the laying course described in the Specification for Highway Works [1]
material. except for reinstatements where reference should be
3.4 intermediate restraint made to annex A.
Device that is used to provide restraint of paving The subgrade, sub-base and roadbase, if present,
units at intervals of the paving surface. should be presented so that:
a) the surface levels are within the tolerances
3.5 interlock given in annex B;
Effect of frictional forces between paving units b) the longitudinal falls and the crossfalls of the
which prevents them moving vertically in relation to completed pavement allow the water to run off,
each other. thus avoiding ponding.
3.6 laying course NOTE 1. A minimum longitudinal fall of 1.25 % and a minimum
crossfall of 2.5 % are recommended for carriageways using
Layer of sand on which paving units are bedded. paving units as a channel. For other areas a 1 % longitudinal
3.7 laying face and 1.25 % crossfall are recommended and for carriageways
using proprietary drainage systems a 2.5 % crossfall is
Working edge of the surface course to which paving recommended with a longitudinal fall as recommended by the
units are being placed. supplier.

 BSI 1997 1
BS 7533 : Part 3 : 1997

c) the surface is tight and dense enough to prevent 4.3.2 Moisture content
laying course material being lost into it during The moisture content of the laying course should be
construction and use; uniform. The material needs to be moist without
d) provision is made to prevent migration of the being saturated.
laying course material into the drainage system, When the sand is squeezed in the hand and the
e.g. by using a geotextile; pressure released, the sand should show no free
e) the extent of the site preparation includes water and should bind together.
enough room to provide adequate foundations and If the prepared laying course becomes saturated
backing for any edge restraint. prior to laying the paving units, it may be removed
NOTE 2. Consideration should be given to the drainage of the and replaced, or allowed to dry to an acceptable
laying course if there is a risk of a significant hydraulic head of moisture content. To control the moisture content of
water developing within this layer.
a stockpile, covers may be used.
4.2 Restraint
4.3.3 Preparation of laying course
4.2.1 Edge restraints When laying on a sub-base, the target laying course
Edge restraints need to be sufficiently robust to thickness after final compaction should be 50 mm.
withstand override by the anticipated traffic, to When laying on a roadbase, the target laying course
withstand thermal expansion and to prevent loss of thickness after final compaction should be 30 mm.
the laying course material from beneath the surface
course. For laying course tolerances, see table B.1. The
laying course material should not be used as a
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

The edge restraint should present a vertical face regulating course or to achieve falls and should be
down to the level of the underside of the laying uniform in thickness.
course.
One of the following methods of screeding the laying
The surface course should not be vibrated until the course should be used for concrete block paving.
edge restraint, together with any bedding or concrete
haunching, has gained sufficient strength. It is a) Pre-compaction. Spread the material in one
essential that edge restraints are adequately secured. layer, compact this layer using a plate vibrator
making allowances for the reduction in thickness
NOTE 1. Examples are shown in annex C.
achieved during compaction, and level the surface
At the intersection of different materials, for example by screeding.
paver/bitumen bound material, an edge restraint
b) Partial pre-compaction. Spread the material in
should be used.
a loose uncompacted layer to about the required
NOTE 2. Typical examples are kerbs, channels, established depth below the surface profile. Compact this
structures or rigid abutments such as securely fixed paving
blocks. layer using a plate compactor (see 4.4.4). Spread a
further layer of material about 15 mm in thickness
4.2.2 Intermediate restraint and screed it to create a loose surface on which
In certain applications, particularly on steep slopes, paving blocks can be placed.
intermediate restraints might be required. An c) Compaction after laying blocks. Spread the
example is shown in annex C. material loose in a uniform layer, and screed it to
NOTE. Experience suggests that these should be at not greater a thickness required to give the specified design
than 15 m centres, depending upon the loadings, traffic, etc. thickness after the paving blocks have been laid
4.2.3 Temporary restraint and vibrated into place.
Temporary restraints should be used to prevent For clay pavers, the recommended method of
paving units moving during construction and are screeding the laying course is method a).
particularly important if a partially completed NOTE 1. Where previous experience of a particular material is
pavement is to be trafficked or when it is necessary lacking, a small trial area will be needed to determine the
allowance for the sand surcharge.
to preserve the integrity of the laying face at the end
of the working period. If any disturbance of the laying course material by
pedestrian or wheeled traffic occurs prior to placing
4.3 Laying course paving units, areas of laying course material should
4.3.1 Material be rescreeded or recompacted to achieve uniformity
of compaction.
Naturally occurring sand from the quaternary
geological series or sea-dredged sands selected and After the careful removal of the screeding rails, the
graded according to use as given in table D.2 should disturbed area should be filled and re-screeded with
be used. Other material and crushed rock fines laying course material using a float and manual
should only be used for category IV applications. compaction.
NOTE. The laying course should contain no cementitious material NOTE 2. During breaks in laying, it can be useful to leave an area
which may detract from the flexible nature of the pavement. of laying course ahead of the laying face.

2  BSI 1997
BS 7533 : Part 3 : 1997

The area of laying course prepared should generally 4.4.3 Cutting and trimming
be such that at the end of a working day, its
boundary is not less than 1 m ahead of the laying 4.4.3.1 General
face. The paved area should be covered with full-sized
All areas of prepared laying course material should paving units. Where paving units need to be trimmed,
be protected and not left exposed overnight. (see sizes smaller than a quarter of the original plan size
4.3.2.) of the unit should be avoided. To assist the accuracy
of cutting paving units against a vertical face, typical
NOTE 3. If the tolerances given in annex D are exceeded, this may
affect the performance of the pavement.
details are shown in E.2.
Whole paving units should be laid first, followed by
4.4 Installation of wearing course paving units cut around obstructions and adjacent to
4.4.1 Laying pattern the edge restraint. This can be achieved by inboard
Details of the laying pattern should be specified cutting where necessary or complementary fittings
before commencement of laying. Typical laying can be used to complete the pavement.
patterns are shown in annex E. NOTE 1. To achieve a straight cut face, concrete paving blocks
are usually cut using a hydraulic or mechanical block-splitter. Clay
Where rectangular units are being used in areas pavers should preferably be cut using a multi-bladed mechanical
subjected to vehicular traffic, herringbone pattern paver splitter or a bench mounted water cooled power saw with
should be used to minimize creep and to ensure an appropriate blade.
better distribution of imposed wheel loads. Basket The accuracy of cutting the unit should be such that
weave bond pattern should only be used in the joint between the cut unit and the full unit or the
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

pedestrian areas. Running bond pattern is usually edge restraint should be not more than 5 mm.
confined to pedestrian areas but has been NOTE 2. The herringbone bond naturally rakes back on either side
successfully used in areas subject to occasional light of the face, allowing the workers to operate on both leading
vehicular traffic. edges.
NOTE. Shaped blocks determine the pattern in which they can be NOTE 3. Against curved edges, it might not always be possible to
laid. maintain a 5 mm joint.
Cut paving units or complementary fittings should be
4.4.2 Laying paving units. incorporated into curved lengths of running bond
Paving units should be placed on the prepared laying pattern to prevent cross joints coinciding and to
course so that the surface levels are within the re-establish the correct pattern.
tolerances given in table B.1 after completion of the NOTE 4. Paving units and complementary fittings are available to
final vibration operation. Any minor adjustments assist with the formation of boundaries and with changes in
necessary to maintain the laying pattern should then direction.
be made. The purpose of the spacer nibs is not to 4.4.3.2 Trimming and laying around obstructions
establish the joint width but to minimize any
potential damage to the paving units during the The paving units should be trimmed to fit after
construction process. A string line may be used to laying full paving units around any obstruction with
check the bond pattern. joints between ironwork and paving units not
exceeding 5 mm. Where this is not possible, surround
An order of laying which maintains an open laying the obstruction with C35 air entrained concrete
face should be followed. The first row of paving conforming to BS 5328 or equivalent, with maximum
units should be aligned against a straight section of aggregate size of 10 mm, to form a regular shape of
the edge restraint, intermediate or temporary sufficient dimension. The thickness should be not
restraint or by using a straight edge or string line. less than the total depth of the paving unit and
The alignment of paving units should be checked laying course down to the ironwork, and the width
periodically for all bond patterns, e.g. by using string not less than 100 mm to provide structural integrity.
lines, and adjustments made where necessary. Wherever possible, when new ironwork is being used
The achievement of straight joint lines, particularly in conjunction with paving units, careful choice of
with mechanical laying methods, might not be shape and size of these products should be made to
possible, owing to permitted manufacturing ensure minimum cutting (see figure C.2). If ironwork
tolerances and variations in the surface profile of the has protrusions which prevent the use of a unit of
pavement. full thickness, a concrete surround should be used.
Paving units should be laid with a joint width Paving units should not be reduced in thickness.
typically within the range of 2 mm to 5 mm. The joint NOTE 1. Careful selection of raw materials should be made to
width will be influenced by the paving unit shape achieve an adequate colour match. Proper curing of the concrete
is essential. The use of bitumen sprays, curing agents, wet
and the laying pattern. The width of the joint should material or plastic sheeting held in place has been found effective.
not include the chamfer dimension (if any). Care should be taken to avoid damaging the finished face of the
units with cementitious material.

 BSI 1997 3
BS 7533 : Part 3 : 1997

NOTE 2. Concrete should be mixed and laid as dry as possible in NOTE. Vacuum sweepers should not be used on the wearing
order to achieve the desired surface finish and should be course for at least three months after laying in order to reduce the
compacted in place to reduce any air bubbles and voids. Rapid risk of jointing sand being lost. Joint sealant may be used to
setting cementitious mortar may be used in accordance with stabilize the sand in joints where vacuum sweepers are likely to
manufacturer's instructions. be used.

4.4.4 Compaction and joint filling


4.4.4.1 Plate compactor 5 Construction in inclement weather
A plate compactor should be used for compaction. In adverse weather conditions, the units should not
Plate compactors as described in annex F have been be laid on saturated laying course material. The
found suitable for compacting the laying course and filling of joints is not possible in damp conditions. In
the surface. such conditions, sufficient sand should be brushed
into the joints as to allow site traffic to deliver the
NOTE. Some manufacturers recommend the use of a compactor
with a neoprene sole plate to protect special surfaces. units for laying to continue. The joints should be
topped up at the earliest opportunity.
4.4.4.2 Concrete block paving
The surface course should be fully compacted using
a plate compactor in order to achieve the required
6 Additional work after early
compaction of the laying course. Joints should be trafficking
refilled as necessary and the paving revibrated with The surface course should be inspected soon after
two or more passes. completion and at regular intervals thereafter.
4.4.4.3 Clay pavers Additional jointing sand should be brushed in where
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

necessary.
Before compaction, jointing sand conforming to the
requirements of table D.3 should be brushed over the In time, detritus will accumulate in the joints,
surface and into the joints until the joints are full. tending to seal them. Until this has occurred, the
Surplus sand should be removed. The surface course paving should only be brushed by hand. Mechanical
should be compacted using a plate compactor fitted sweepers, in particular sweepers with high suction
with a neoprene sole plate, making two or more forces, should not be used or used only with care in
passes. This process should be repeated as order to avoid the risk of losing the jointing sand
necessary. from between the paving units, thus adversely
affecting the performance of the pavement.
4.4.4.4 Joint filling NOTE. When the jointing sand needs to be stabilized,
Filling the joints between paving units is essential. It surface-applied elastomeric sealers may be applied in strict
is recommended that dried free-flowing silica sand is accordance with the manufacturer's instructions. This treatment
impedes the unwanted removal of the sand by suction cleaners
used. Materials conforming to the grading in and at the same time reduces the ingress of water during the early
table B.3 should be used. Sand which might stain the life of the pavement. This treatment might have an effect on the
pavement surfaces should not be used. colour of the paving unit and its initial slip/skid resistance and
could require continual maintenance.
4.4.4.5 Completion of compaction
The compaction should be carried out as soon as
possible after laying but not within 1 m of any laying
face. Apart from this edge strip, areas of paving
should not be left uncompacted at the completion of
the day's work.
The finished surface levels should be checked for the
tolerances given in table B.1.
The surface course should be compacted to ensure
complete filling of the unit-to-unit joint by the
surface-applied jointing sand. Where necessary,
further sand should be added and the paving
revibrated. Joint filling and final compaction should
be completed as soon as practicable after laying
(see clause 4.4.4.4). The process of joint topping up
should be repeated, when necessary, by brushing in
further joint filling sand until the integrity of the
pavement is established. This is particularly relevant
during the initial period of the pavement life.
After final compaction of the surface course, and
wherever possible, a thin layer of jointing sand
should be left on the surface to help ensure that the
joints remain filled in the short term.

4  BSI 1997
BS 7533 : Part 3 : 1997

Annexes

Annex A (normative) A.5 Reinstatement


Reinstatement A.5.1 Conventional reinstatement
Replace the granular material and sub-base and
A.1 General
thoroughly compact.
Where reinstatement is required as a result of statutory NOTE. Owing to the variable nature of excavated material and the
undertaker's work, the design and construction of the difficulties associated with its replacement, it is recommended
reinstatement should satisfy the requirements of the that new Department of Transport DoT Type 1 granular sub-base
Highway Authorities and Utilities Committee (HAUC) material conforming to the specification for Highway Works [1] is
used for this purpose.
Specification for the Reinstatement of Openings in
Highways [2]. Compaction should be carried out by back filling in
NOTE. In certain cases, the use of Type 1 sub-base material and compatible layers with the compaction plant. Each
foamed concrete is not permitted and specific reference should be layer should be thoroughly compacted with a plate or
made to that document. trench vibrator of an output which satisfies the
A.2 Opening up the pavement requirement of the HAUC Specification [2]. The
existing pavement materials should be replaced with
Paving units which have been laid and trafficked for equivalent depths of new material.
any length of time are tightly locked together and it
could be difficult to remove the first few units without DoT Type 1 granular sub-base material and, if needed,
breakage. One method for opening up an area for roadbase materials should be reinstated to replace
access is to break up and remove two or three paving missing layers.
units and then carefully lift others to expose the When complete, the top of the reinstatement should be
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

working area. This has the disadvantage of requiring compacted level with the existing sub-base or roadbase
replacement paving units for those which have to be construction.
broken. Alternatively, the method of A.3 and A.4 A.5.2 Foamed concrete reinstatement (where
should permit the salvaging of the whole units without permitted)
breakage.
With this method, all excavated material should be
A.3 Removal of the first unit removed from site because no other materials are
A.3.1 As much sand as possible should be removed required except for any surrounds to services, the
from the joints surrounding the unit using a foamed concrete and laying course sand. The
bricklayer's small trowel or other suitable tool. excavated material should be replaced with foamed
concrete up to the underside of the laying course.
A.3.2 The unit should be levered out using suitable NOTE. Foamed concrete is either delivered to site in a
levers or with a proprietary `paving unit extractor', or truck-mounted mixer or produced at the site by trailer-mounted
one unit should be broken out. equipment.
The material is self levelling and flows to fill the
A.4 Removal of subsequent units
excavation above the newly exposed or installed
Once the first unit is removed, subsequent units should utilities. The concrete should be placed up to the top
be lifted clear. of the sub-base or roadbase (whichever is higher) and
Passing a vibrating plate over the surface of the units screeded level. Sand and paving units should not be
adjacent to the opening might assist in breaking the compacted until the foamed concrete has attained
interlock, or units adjacent to the area being loosened sufficient strength to allow adequate compaction of the
may be tapped down with the shaft of a hammer or laying course.
other suitable tool to achieve the same. This method
A.6 Reinstatement of pavement surfacing after
should be continued until an area of paving has been
trenchwork
removed, at least two rows beyond the excavation
area. During the operations, it is likely that the edge units
and underlying sand will be disturbed and these layers
The units should then be cleaned with a stiff brush and
should be removed.
stacked in a position which will be convenient for
reinstatement. At least a further two rows of units beyond each edge
of the excavation should be removed, cleaned and
stacked. The adhering jointing sand from the edges of
exposed paving units should be scraped away. Fresh
laying course to approximately two thirds of the
finished thickness should be added and fully
compacted with a plate compactor, if possible, to a
level which is below the adjacent compacted sand.
Sand should then be spread over the area and
screeded to stand slightly proud of the laying course
material.

 BSI 1997 5
BS 7533 : Part 3 : 1997 Annex A

A notched screeding board may be used to achieve a Annex B (normative)


slightly cambered profile over the width of the trench.
Alternatively the same profile can be achieved by
Tolerance of the surfacing
setting three screed rails into the sand, down the Recommended tolerances are given in tables B.1,
length of the trench (suitable lengths of narrow B.2 and B.3.
diameter pipe may be used). The central rail should be NOTE. Certain applications e.g. aircraft pavements, may require
positioned higher than the two at each edge so that the stricter tolerances, particularly for the surface course.
finished level will be higher by approximately 6 mm at
its edges and 12 mm at its centre. The original cleaned Table B.1 Tolerance of surface levels
units should then be relaid tightly, as far as possible Layers of pavement Maximum
maintaining the bond. permissible
After completion and vibration of the units the deviation from the
design level
cambered surface should be left proud by mm
approximately 2 mm at its edges and 5 mm in the
Sub-layer Sub-base +20
centre. With trafficking during subsequent months, this 215
camber normally compacts to a level surface. 0
Road-base
A rubber hammer may be used to tap the final unit 212
into place. Surface course Overall +6
26
Once the units have been relaid and bonded into the
existing pavement each side of the trench, compaction
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

and joint filling of the paving units should be carried Table B.2 Tolerance of laying course thickness
out. Thickness Tolerance
If it is not possible to complete the reinstatement with mm mm
whole units, a stretcher course should be included and 50 +15
units cut to fit to this. 220
If the original pavement has been sealed, the replaced 30 +12
0
area should be resealed.

Table B.3 Surface regularity


Flatness 10 mm under a 3 mm straight edge
Level 2 mm between adjacent units

The surface course should be between 5 mm


and 10 mm above adjacent gullies and between 3 mm
and 6 mm above surface drainage channels and outlets.
It is important to avoid ponding at these locations

6  BSI 1997
Annex C BS 7533 : Part 3 : 1997

Annex C (informative)
Typical restraint details

,,,,
,,,,
Mortar bed

,,,,
,,,, Paving units

,,,,
Laying course

Concrete Sub-base

NOTE: Not applicable to clay paving


a)

,,,,
,,,
,,,,
Paving units
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

Laying course

,,,,
Mortar bed
Sub-base
Concrete

b)

,,,,
,,,, Paving units

,,,,
Laying course

,,,,

,,
Concrete Sub-base

c)

,,

 
,,,
,,
d)
,,
Mortar bed

Figure C.1 Typical restraint details

 BSI 1997

,,,
,,
,,,
,, Concrete

7
BS 7533 : Part 3 : 1997 Annex C

,,,
,,, ,,,
,,,
a)

,,, ,,,
Stretcher course

,,, ,,,
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

b)



,,
,,,
,,,,,
,,
,,,
Concrete surround

,,, ,,
,,
,,
c)
,,,
Figure C.2 Detail at ironwork

8  BSI 1997
Annex C BS 7533 : Part 3 : 1997

,,,



,,,
Set in wet concrete

,,,
,,,



,,,
Laying
course



Sub base

Cement & sand

,,,,

mortar bed

In-situ concrete foundation


a)

,,,
,,,,



Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

,,,


Laying
course

Sub base

Cement & sand


In-situ concrete foundation mortar bed

b)

,,,,
,, ,,,
,,,,
,, ,,,
,,,,
In-situ concrete foundation
Laying
course

c)
Figure C.3 Typical detail around drainage channels

 BSI 1997 9
BS 7533 : Part 3 : 1997 Annex D

Annex D (normative)
Grading and application for laying course
sand

Table D.1 Laying course application


Sand category Application
IA Pavements receiving severely channelized traffic, aircraft pavements and bus stations
IB Industrial pavements
Loading bays
II Adopted highways and other roads
Petrol station forecourts
Pedestrianization projects regular heavy trafficking
Car parks receiving some heavy traffic
Footways regularly overridden by vehicular traffic
III Pedestrianization projects receiving only occasional heavy traffic
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

Car parks receiving no heavy vehicles


IV Private drives
Areas receiving pedestrian traffic only
Footways likely to be overridden by no more than occasional vehicular traffic

Table D.2 Grading for laying course sand


Sieve size Percentage passing each sieve
%

Category IA Category IB Category II Category III Category IV

5 mm 90Ð100 90Ð100 90Ð100 89Ð100 89Ð100


2.36 mm 75Ð100 75Ð100 75Ð100 65Ð100 65Ð100
1.18 mm 55Ð90 55Ð90 55Ð90 45Ð100 45Ð100
600 mm 35Ð65 35Ð65 35Ð65 25Ð80 25Ð80
300 mm 10Ð45 10Ð45 10Ð45 5Ð48 5Ð48
150 mm 0Ð10 0Ð10 0Ð10 0Ð15 0Ð15
75 mm 0.3 max. 0Ð0.5 0Ð1.5 0Ð3 0Ð5

10  BSI 1997
Annex D BS 7533 : Part 3 : 1997

Table D.3 Grading for jointing sand


Sieve size Percentage passing
%
2.36 mm 100
1.18 mm 95Ð100
600 mm 50Ð100
300 mm 15Ð60
150 mm 0Ð15
75 mm 0Ð3

The test method used for determining the grading for


laying course sand and jointing material should be the
washing and sieving method described in BS 812 :
Section 103.1. For category 1 sands, the test should be
carried out on five sub-samples, each not less
than 1000 g, and the mean taken of the results.
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

 BSI 1997 11
BS 7533 : Part 3 : 1997 Annex E

Annex E (informative)
Laying patterns

a) 45° Herringbone
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

b) 90° Herringbone

c) Running bond

d) Basket weave
Figure E.1 Laying patterns

12  BSI 1997
Annex E BS 7533 : Part 3 : 1997

a) Single stretcher course


Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

b) Double stretcher course

c) Soldier course
Figure E.2 Laying patterns at edges

 BSI 1997 13
BS 7533 : Part 3 : 1997 Annex F

Annex F (normative)
Compactor details

Table F.1 Compactor details


Site category Min. plate area Min. effective force per Frequency Min. mass
unit area of plate
m2 kN/m2 Hz kg

I and II 0.25 75 65Ð100 200


III and IV 0.2 60 75Ð100 80
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

14  BSI 1997
BS 7533 : Part 3 : 1997

List of references (see clause 2)

Normative references

BSI publications
BRITISH STANDARDS INSTITUTION, London

BS 812 Testing aggregates


BS 812 : Part 103 Method for determination of particle size distribution
BS 812 : Section 103.1 : 1985 Sieve tests
BS 5328 Concrete
BS 6100 Glossary of building and civil engineering terms
BS 6100 : Part 2 Civil engineering
BS 6677 Clay and calcium silicate pavers for flexible pavements
BS 6677 : Part 1 : 1986 Specification for pavers
BS 6717 Precast concrete paving blocks
BS 6717 : Part 1 : 1993 Specification for paving blocks
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

Other publications
[1] GREAT BRITAIN. Specification for Highway Works 1993. London: HMSO (incorporating amendments)
[2] GREAT BRITAIN. Highways Authorities and Utilities Committee (HAUC) Specification for the Reinstatement of
Openings in Highways 1992. London: HMSO (incorporating amendments)
|
|
|
|
|
|
|
|
|
BSI Ð British Standards Institution
|
|
|
|
|
|
| BSI is the independent national body responsible for preparing British Standards. It
|
| presents the UK view on standards in Europe and at the international level. It is
| incorporated by Royal Charter.
|
|
| Revisions
|
|
| British Standards are updated by amendment or revision. Users of British Standards
|
| should make sure that they possess the latest amendments or editions.
|
|
| It is the constant aim of BSI to improve the quality of our products and services. We
|
| would be grateful if anyone finding an inaccuracy or ambiguity while using this
| British Standard would inform the Secretary of the technical committee responsible,
|
| the identity of which can be found on the inside front cover. Tel: 020 8996 9000.
|
| Fax: 020 8996 7400.
|
|
| BSI offers members an individual updating service called PLUS which ensures that
|
| subscribers automatically receive the latest editions of standards.
|
|
| Buying standards
|
| Orders for all BSI, international and foreign standards publications should be
|
| addressed to Customer Services. Tel: 020 8996 9001. Fax: 020 8996 7001.
|
|
| In response to orders for international standards, it is BSI policy to supply the BSI
|
Licensed Copy: Akin Koksal, Bechtel Ltd, 10 December 2002, Uncontrolled Copy, (c) BSI

| implementation of those that have been published as British Standards, unless


|
| otherwise requested.
|
|
| Information on standards
|
| BSI provides a wide range of information on national, European and international
|
| standards through its Library and its Technical Help to Exporters Service. Various
|
| BSI electronic information services are also available which give details on all its
|
| products and services. Contact the Information Centre. Tel: 020 8996 7111.
|
| Fax: 020 8996 7048.
|
|
| Subscribing members of BSI are kept up to date with standards developments and
| receive substantial discounts on the purchase price of standards. For details of
|
| these and other benefits contact Membership Administration. Tel: 020 8996 7002.
|
| Fax: 020 8996 7001.
|
|
| Copyright
|
|
| Copyright subsists in all BSI publications. BSI also holds the copyright, in the UK, of
|
| the publications of the international standardization bodies. Except as permitted
| under the Copyright, Designs and Patents Act 1988 no extract may be reproduced,
|
| stored in a retrieval system or transmitted in any form or by any means ± electronic,
|
| photocopying, recording or otherwise ± without prior written permission from BSI.
|
|
| This does not preclude the free use, in the course of implementing the standard, of
|
| necessary details such as symbols, and size, type or grade designations. If these
|
| details are to be used for any other purpose than implementation then the prior
| written permission of BSI must be obtained.
|
|
| If permission is granted, the terms may include royalty payments or a licensing
|
| agreement. Details and advice can be obtained from the Copyright Manager.
|
| Tel: 020 8996 7070.
|
|
|
|
|
|
|
|
|
BSI |
|
389 Chiswick High Road |
|
London |
|
W4 4AL |
|
|
|
|
|
|

You might also like